I have developers in Quebec and in Ontario, and each province has different holidays. In MS Project 2003, I selected Tools/Working Time and created two calendars called Ontario and Quebec and filled out the holidays appropriate for each. In my resource sheet, I made the base calendar for each developer match their province.
With that in place, I created a task for a Quebec developer that takes 9 days and scheduled it as Must Start On Monday June 18th. There is a holiday in the Quebec calendar for June 25th, so I assumed that the end date would come out as Friday, June 29th, but it shows up as Thursday. MS Project seems to ignore the resource calendar when scheduling this task.
Shouldn't MS Project notice that the specified resource is not available on June 25th in this case? Or have I misunderstood how the resource calendar works?
Thanks, Mike.