I have a list of tasks, each measured in days. The hours-per-day setting on the project is incorrect. When I update it, the tasks change accordingly.
My problem is that it's only the hours-per-day that is wrong; the length of each task is correct in terms of days, so I do not want it to change.
8 hours per day:
Example task - 2 days
Change to 7 hours per day:
Example task - 2.29 days //undesired
There's many tasks so updating them individually is obviously impractical.