I work on a project with many changes. To get data about how these changes affect my project, I want to show my boss about my plan gantt & actual gantt on the same diagram. Could I do this with Microsoft Project? if yes, please show me how!

2 Answers 2

1

I don't think you can. Especially with a complex project trying to have two Gantt charts essentially overlapping is going to get messy and difficult to interpret. A better bet may be to create a table of four columns:

  • First column is the milestone
  • Second column is baseline completion date
  • Third column is predicted ("actual") completion date
  • Fourth column is variance
4

Set your view to tracking Gantt. After you baseline your schedule, there will be two bars on each package. One shows your baseline, the other shows your actual. If you have your packages predecessor and successor logic captured well, the actual gantt will show your finish variances throughout the entire project, including your critical path.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.