I'm working on a microsoft project pro problem and need help. I have two summary tasks A and B starting on the same day. Each Summary task has sub tasks 1,2 with resources allocated to them and obviously both subtasks 1 and 2 result in overallocation of the respective resources.
A
..1
..2
B
..1
..2
The timing of Subtasks 1,2 are ridgid within each Summary task. I want to resource level the subtasks to prevent overallocation but MS Project levels the subtasks by moving just the subtask. How can I get MS Project to maintain the subtasks timing by moving the Summary task (i.e. all the subtasks within) to fix the resource overallocation. Example:
From above MS Project moves subtask 1 within the summary task B to fix the overallocation:
A
..1
..2
B
....1
..2
I want it to move the start date of the summary task to prevent overallocation like this:
A
..1
..2
..B
....1
....2
I didn't think this would be a problem but have not found a way to do it yet... Thanks for your thoughts.