I've created a recurring task in MS project and I'd like to assign resources (staff) to that resource but when I add the resource(s) to the task the Work hours multiply to extremes and I don't understand why..
For example I have Project Meeting as a recurring task, it's duration is 217.13 days and the Work is set to 22 hours. However, when I assign a resource this jumps to 1759 hours. If I add another resource this jumps to 3496 hours.
What's going on?
Edit: It only seems to happen when I add to "resource names" rather than "assigning" resources. So.. what's the difference?