7

I've created a recurring task in MS project and I'd like to assign resources (staff) to that resource but when I add the resource(s) to the task the Work hours multiply to extremes and I don't understand why..

For example I have Project Meeting as a recurring task, it's duration is 217.13 days and the Work is set to 22 hours. However, when I assign a resource this jumps to 1759 hours. If I add another resource this jumps to 3496 hours.

What's going on?

Edit: It only seems to happen when I add to "resource names" rather than "assigning" resources. So.. what's the difference?

0

2 Answers 2

5

More than probably your task is set by default as "Fixed Units" so the initial 22 hours of work are not kept fixed.

Now 217.13 days * 8 hours/day = 1737 hours (the task duration in hours)

Whenever you add a new resource in "Resource names" column MS Project tries to guess what you want to do. And by default he believes you are adding a new resource with 100% allocation so it results:

22 + 1737 (hours the new resource will have to work) = 1759 hours

Adding a new resource results in:

1759 + 1737 = 3496 hours

When you assign all resources at once using the "Task information" dialog, all resources are assigned with 1% allocation.

I suggest you first add resources and then set the desired work. Otherwise MS Project might thing you are trying to do some resource leveling.

1
  • Thanks tiberiug for that detailed explanation. This helped me a lot. Highly appreciated.
    – Zakir HC
    Apr 10, 2013 at 10:56
3

I think it's because of the nature of recurring task itself. Since each resources are assigned to a recurring task, the working hours tend to exceed in each task.

Example of recurring task

I assigned resources to task. The output is shown above.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.