1

Using Open Project, how can one calculate staff-hours?

Using Project -> Project Information -> Statistics, is work it? ("Work" is 1,219 hours in my example below)

enter image description here

1 Answer 1

2

Work is indeed effort-hours, rather than duration. Someone works for two hours on a task over two days results in 2 work hours, and 2 Days of duration.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.