Using Open Project, how can one calculate staff-hours?

Using Project -> Project Information -> Statistics, is work it? ("Work" is 1,219 hours in my example below)

enter image description here

2

Work is indeed effort-hours, rather than duration. Someone works for two hours on a task over two days results in 2 work hours, and 2 Days of duration.