Using Open Project, how can one calculate staff-hours?
Using Project -> Project Information -> Statistics
, is work
it? ("Work" is 1,219 hours in my example below)
Project Management Stack Exchange is a question and answer site for project managers. It only takes a minute to sign up.
Sign up to join this communityUsing Open Project, how can one calculate staff-hours?
Using Project -> Project Information -> Statistics
, is work
it? ("Work" is 1,219 hours in my example below)
Work is indeed effort-hours, rather than duration. Someone works for two hours on a task over two days results in 2 work hours, and 2 Days of duration.