3

Using Microsoft Project 2010, how do I view how much a resource costs the project between a specific time period?

For example, I want to view how much the "HR" resource cost the project between September 13th, 2012 and November 15th, 2012.

0

You should be able to use the costs or custom reports in project 2010 and get reports based on your requirements.

0

I have been talking to someone who has used MS project for a while now, as far as he knows this is not possible to do. He suggested I print out the total for each week and add them up manually.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.