0

I am using Gantter and/or ProjectLibre (which are both almost identical to Microsoft Project in functionality). I think that if there is a solution to this in Microsoft Project, then it will work in either of these too.

Here is the scenario:
Task 1: Work 5d (40h): Resource A
Task 2: Work 2d (16h): Resource B
Task 3: Work 20d (160h): Predecessor Task 2: Resources A and B

I would like Resource B to start Task 3 at the end of 2 days and Resource A to start Task 3 at the end of 5 days.

Note that "Work" above is the effort estimated by us for the task.

Ideally, Task 3 should start on day 3 with Resource B who should spend 11.5 days on it and Resource A should spend 8.5 days once Task 1 is done.

However, when I allocate 2 resources to the task with 100% units, it gets divided equally into 10 days each. The Task 3 starts on day 3 and I get over-allocated resources message because Resource A spends 3 days on both Task 1 and Task 3.

I know I can do this allocation manually by detailing the resource assignment. The question is can this be automated in some way? It's bizarre that this has to be done manually. I assume that it must be a pretty common requirement? Or am I mistaken?

1 Answer 1

1

Ignore it. It doesn't matter. Chasing a perfectly leveled resource allocation will cost you a ton of effort to get it just right and will be perfect for one day--the day of baseline. The very second you start to load actuals and progress, your resource allocation will go up and down to some degree. You would never--hopefully--chase the leveling. Instead, you would use the tool's warning of a over loaded resource to see if you need to intervene. If you know you don't need to because of other known factors, e.g., resource A won't start for a few days, then you would simply ignore the tool's warning.

So load the scenario as you described in the tool, allow resource A to be "over utilized" a bit. Baseline and go. It will not materially affect your schedule analysis one bit.

2
  • Hmmm ... so in short, there's no way automated way to do it? Though the engineer in me cringes at such inaccuracy, I agree with you that it's better to take a big-picture view and move on.
    – Myu Zyc
    Nov 6, 2012 at 3:27
  • I don't know if there is an automated way or not. I was only commenting on that it doesn't materially matter. Nothing wrong with having precision in your initial schedule, which you will likley have to do manually, I just would not recommend you putting too much time getting there based on the reasons I wrote above. Nov 6, 2012 at 15:05

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.