I have MS Project 2010 server.
I need to add view or report (whatever fits best), and it may be implemented on client or server (whatever fits best).
I need a crosstab report where Resources will be on one axis, Weeks on another and project list in cells.
Result should look like this:
| Alice | Bob | Jim |
--------------------------------------------
Dec 3 - Dec 9 | Prj1 | Prj1 | |
Dec 10 - Dec 16 | Prj1 | Prj2 | Prj2 |
Dec 17 - Dec 23 | Prj1, Prj2 | Prj2 | Prj2 |
Dec 24 - Dec 30 | Prj2 | Prj2 | Prj3 |
Of course it is acceptable if resources will be vertical, and weeks horizontal.
How should I do this? I tried to setup custom resource assignments view on server but did not succ
Maybe that was discussed already, but I did not find any answer.