I am trying to put together a programme plan, collaborating all of the individual project plans into one programme plan.
Every time I copy and paste one of the project plans into my new programme plan (even if there is nothing else in the plan) all of the dates change.
Without going through each task a rectifying the date change, there is not much that I can think to do.
Removing automatic scheduling allows me to copy and paste the dates, but I need the format of the plan to stay the same, so automatic scheduling needs to be on.