0

Using MS Project 2010 & new to resource pools and sharer plans. If I have a sharer plan open, and make changes to tasks/assigments -- is the resource pool file updated somehow, even if it's not open in Project at the same time?

1

Open the Resource pool first and close it last

When you open a sharer file that shares resources from a pool, you should have seen a dialog like this: Open resource pool

In any case, if you didn't have the pool file open, that project would have used own resources when making assignments (nothing else is available). I am afraid you will have to fix this manually.

For future reference, you should open the Resource pool first and close it last.

| improve this answer | |

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.