I have a project plan for a project that we already started and I want the plan to reflect the schedule moving forward, say as of tomorrow. I have a handful of dependencies and resources assigned.
I want to make the start and end dates reflect/auto-schedule based on the remaining work column.
The current columns I have that may be confusing me here are:
- Duration - appears to match work in hours but bubbles up to days on super tasks; may be redundant for me
- Work - defined in hours, see above
- Remaining Work - auto calculated into hours based on % complete column
- % Complete - a % that I'm updating on many tasks. This is my main area where I keep updating it daily
- Start - all tasks are set to auto-schedule and this seems to be tied to the resource and predecessor as well as either the Work column or Duration but I want to to be based on Remaining Work
- Finish - all tasks are set to auto-schedule and this seems to be tied to the resource and predecessor as well as either the Work column or Duration but I want to to be based on Remaining Work