2

I want to print the task list and the Gantt chart in a specific date range (as illustrated in the image below). How can I do it? The default print scheme wastes paper and is difficult to read. I have gone through all the print options provided in MS Project but it didn't help.

print only tasklist & gant

3 Answers 3

3

Have you tried using the Date Selection provided in the Print Dialog? Date selection options are highlighted in blue color in the following screenshot:

enter image description here

I tried it in MS Project 2007 and it worked fine. Full chart was taking 3 pages, when I used the date range then the chart got printed in 2 pages.

enter image description here

1
  • this is soooooo helpful. thank you. finally!
    – user7900
    Jan 21, 2014 at 4:57
1

I filter the date range in project; I have a standard project filter & view for "Six Month Horizon" which includes only those tasks that start or end in the next six months.

That may help.

0

Using a new column for specific "Marked Tasks" is a pretty good way ahead, see :

http://support.microsoft.com/kb/141654

1
  • Although we can consider Microsoft link reliable (it's unlikely to have it down / deleted) would be good to explain at least a few steps directly in your answer to avoid relying on external sources on your answers. Tks
    – Tiago Cardoso
    Jul 17, 2014 at 23:43

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.