Linked Questions
16 questions linked to/from Capture burned (story) points for a partially complete task moved to next sprint
34
votes
7
answers
32k
views
How do you schedule delivery dates in Scrum?
I've run into a constant issue. When a project starts, the client typically has a list of functionalities to be built in to the application. As a team we would like to follow Scrum. But the next thing ...
25
votes
4
answers
7k
views
Why does Pivotal Tracker discourage estimating points for bugs and chores?
Pivotal Tracker "strongly discourages" estimating velocity points for bugs and chores – you have to change a setting and accept a warning to be able to do it.
They explain why here, but I just don't ...
22
votes
6
answers
5k
views
In scrum should incomplete stories be re-estimated or does the original estimate get burned down when it's finally completed?
If I have a story that's been estimated at 10 story points and we don't manage to complete it in a sprint how do you handle estimates for the sprint in which it's next included (assuming it gets ...
17
votes
4
answers
5k
views
Should velocity increase with time?
Some scrum masters are concerned with "bumping up" a team's velocity during a sprint, as if a higher velocity is better. But points are a relative measure of the work that a team needs to do for ...
4
votes
5
answers
2k
views
What is a productive, efficient Scrum team?
How does a Scrum Master, a Product Owner know whether a Scrum Team gives much or little usefulness to a customer?
In other words, what is a productive, efficient Scrum team?
9
votes
4
answers
2k
views
When can a project's wrong estimates be justified?
This question is not about project estimation techniques, initial processes, etc. Assume everything was done correctly.
Recently, we gave an estimation for an Android application with development ...
8
votes
1
answer
3k
views
What are "Consumed Story Points" in Trello?
Some Scrum add-ons allow you to enter both estimated story points and consumed story points. What are consumed story points and how do you measure/estimate them?
4
votes
5
answers
1k
views
Why is it important to only have PBIs completable in a single Sprint?
In Scrum it is emphasized that the Sprint Goal is achieved and that the developers determine which work can be completed in the Sprint. I often get the following question:
Why can't we start a story ...
12
votes
1
answer
1k
views
If we can’t finish all tasks, does this mean we are doing Scrum wrong?
I'm working in an online mobile game development team, and we've been doing Scrum for several sprints.
There are various reasons, but we seem never able to finish all items selected for an sprint.
...
8
votes
2
answers
673
views
In Scrum, what should we do with partly-completed work started at the end of a Sprint?
I get most of Scrum. However, I can't get my head around what to do with work in progress at the end of a Sprint.
If we are working in a swarm, we can defer the end of a Sprint, or bring it forward ...
3
votes
3
answers
1k
views
Stories in test at end of sprint
We are a small team (3 devs and 2 testers) and we have successfully used Scrum for 6 months, despite being a really small team for this methodology. I am a rookie as a Scrum Master.
Now, we have ...
5
votes
4
answers
2k
views
What can we do with a "mispointed" story in Scrum?
Is it OK to repoint the story at the beginning of the new sprint to reflect the size that we have now discovered it to be so our velocity is more accurate?
On rare occasions, our team will work a ...
1
vote
2
answers
3k
views
How to Calculate Effort Variance in Scrum
My team currently works in 3 week sprints and we are capturing Key Performance Indicator (KPI) for each sprint. One of the KPIs is Effort Variance (EV) per sprint
My question is at the end of the ...
2
votes
3
answers
323
views
How can I effectively differentiate the Sprint Goal from the Sprint Backlog?
I'm facing a situation where I have to explain with an example the difference between a Sprint Goal and a Sprint Backlog. Here's how I understand it:
The Sprint Goal is an objective that needs to be ...
3
votes
4
answers
388
views
How to estimate without relying on SMEs to estimate based on similar projects?
I create MS Project schedules for the government and recently moved to a new position on a staff where I am being asked to develop and control schedules for tasks that are rather vague, i.e. create a ...