Questions tagged [estimation]

For questions about the estimation of the project's parameters, such as time or cost.

Filter by
Sorted by
Tagged with
0
votes
0answers
29 views

When the Putnam estimation model is said to be correct or incorrect? [closed]

The target is to check whether the calculated effort (PME) by Putnam estimation model is correct or incorrect if we have has the skill factor B=0.16 and the rest of variables we can decide by own for ...
3
votes
5answers
5k views

Should there be testing-only user stories?

We estimate stories as 1, 2, 4, 6, or 8 points. Consider a story with less development work but huge testing effort. Let's say we estimate that story as 8 points. We see the following options: Let ...
2
votes
1answer
182 views

How can I calculate how many developers do I need and how long it takes to complete the project? [closed]

I am trying to create an LMS system using Angular and NativeScript. It's a LMS web application like Adobe connect (although a simplified version) that will be written in Angular 8 for example, and a ...
0
votes
2answers
72 views

How to estimate and plan with a distributed, part-time team?

The situation: We are a small, fully-distributed software solutions provider. We serve multiple clients, and given our size that means every team member is on multiple, part-time billable teams. ...
2
votes
6answers
1k views

A simple estimation accuracy formula that always yields 0-100?

I'm just beginning, and despite my search, I cannot find any simple formula that would return a number between 0 and 100%, i.e. I do not care whether there was over or underestimation. The simplest ...
1
vote
4answers
1k views

How do you measure time units in sprint velocity?

I am trying to get my head around "Story points" using the Scrum methodology. As a starting point, I have been following the following article: http://scrummethodology.com/scrum-effort-estimation-and-...
0
votes
1answer
96 views

Mobile apps: integrate backend work in velocity?

Here is my situation: I work with two SCRUM teams, iOS and Android Each of the SCRUM team has its own Product and Sprint backlogs We have shared Sprint Plannings, Reviews and Retrospectives (both ...
5
votes
5answers
11k views

How to estimate accurate velocity when team members are on leave

I am a Scrum Master of a team with 12 members. I know that the size of the team is large at this point, but as we grow further we will divide the team into multiple Scrum Teams. Our estimations for ...
0
votes
1answer
94 views

Outsourcing company: Usage of velocity for offers

Currently I am working in an outsourcing company and our management has decided to use the following scheme for "Velocity of the developers": Each developer has a velocity quotient: Senior Developer:...
15
votes
4answers
3k views

Should velocity increase with time?

Some scrum masters are concerned with "bumping up" a team's velocity during a sprint, as if a higher velocity is better. But points are a relative measure of the work that a team needs to do for ...
1
vote
6answers
1k views

Velocity of the team

If i have been provided with the information of six sprints having story points like 20,21,22,23,24,25,26 then what should be the velocity of the team ?
1
vote
4answers
136 views

Team added “Daily Scrum” as a task in Jira. How do I get rid of this?

So I am just joining a new team. This team is using "Daily Scrum" as a task because according to them it is a "task". Obviously I want to help them understand that it is not a task, just like ...
0
votes
2answers
71 views

When should we stop estimating?

When using Scrum, are the estimated story points for completing an User Story sufficient, or should the estimate be taken at the task level?
2
votes
2answers
119 views

What is an “e zero” estimate

I am often asked to provide an "e zero" estimate for a piece of work. I have been assuming up to now that it means "rough estimate". Does anyone have any link to what this means specifically. I ...
0
votes
2answers
64 views

Fibonacci scale project estimates: how is it not vulnerable to misunderstanding by management?

The Fibonacci sequence is to assist developers with project estimates. The concern is that we consistently see management use the points derived from Fibonacci sequence estimates to determine project ...
1
vote
3answers
77 views

Tracking progress of a team working on small tasks

Our software team works on small tasks. Each task takes about 2 weeks. There are developers whose performance is twice bigger than the other's (the level is the same). Everybody just writes how much ...
0
votes
2answers
47 views

Tasks during sprint planning

For the next sprint, Jira displays the total number of story points in the backlog, calling it "Estimate.". This number leaves out tasks, which are estimated in hours, not story points. This makes it ...
5
votes
3answers
360 views

Dev went on vacation leaving his work unfinished. How to manage this without informing the customer?

I would like to discuss and hear some advice from you about a pretty common situation. We develop the functionality that has huge business value for the customer’s project and thus the customer is ...
0
votes
1answer
55 views

How are low ambiguity and low complexity tickets dealt with when they have a high work cost?

In our scrum team, we can often get user stories which are not very complex and not ambiguous but have a high amount of leg work associated. Example: We receive a user story to replace the name of a ...
4
votes
4answers
5k views

When should I assign 0 and 0.5 story points to user stories in Scrum?

I am not a Scrum Master or a Ph.D. in math. How do stories with 0 and 0.5 points apply to stories on the Scrum board?
1
vote
1answer
63 views

Is there any estimation method to estimate end user testing?

Is there any estimation technique that can help us to estimate the number of needed test cases in traditional software projects? For example, we have a Software requirements specification (SRS) with ...
3
votes
5answers
846 views

Should a good project manager be a good risk manager and a good estimator as well?

I'm taking project management class. It is hard to understand the relationship between estimation, risk management, and project management. Could you explain it based on your experience? My lecturer ...
1
vote
1answer
123 views

How can we persuade team members to estimate in story points instead of hours?

We use story points to estimate our user stories. We find that story points solve the problem of underestimating the amount of actual work which is required to complete a task, as it takes the ...
2
votes
2answers
40 views

When choosing the largest and smallest stories in a backlog for estimation how does it impact each sprint?

An article I came across suggested that we should pick the largest and smallest story in the prioritised backlog and relatively estimate the remaining stories. This makes sense. However, I was ...
3
votes
2answers
70 views

Should single user story contain estimations for each involved guild in full-stack development team

Problem We're working in a full-stack development team composed of three guilds (backend, frontend, QA), so as a team we share a single sprint board. User stories we take into our sprints are written ...
11
votes
3answers
2k views

Is there any published research about story points vs time estimation?

We're getting started with Scrum and have had a few debates about whether we should estimate in story points or ideal hours. The team is pretty divided, so I'd like to know if any real studies have ...
12
votes
4answers
675 views

How can I improve a project schedule on a project I took over and complete it on time?

I just took over a project from a Project Engineer and just saw a revised project schedule. The revised schedule shows the project will be delayed by 3 months. I am trying to complete it within the ...
3
votes
7answers
398 views

Adding estimation points for learning / context switching

In our scrum team, team members tend to add extra points in estimation when there is a "learning" part involved. Here's a simple silly example. Let's say all the people in a team are experts in C# ...
1
vote
3answers
2k views

Current best metrics related to requirements, design and architecture

So my boss put forth a 'research and find out question' to me: Are there ANY (absolutely any, no matter the dumbest, but any) metrics for requirements management? Eg. Requirements completeness, ...
0
votes
1answer
50 views

RFI response form asks for “Assumptions” as just a single money amount

I am surprised by the last row in this RFI response form: My project's initial fees are 1m$, recurring fees are 100k$/year, under the assumption that I provide only the software and they run it on ...
0
votes
1answer
98 views

Scrum task estimation methodologies

I want to know about tasks analysis and estimation methods that can be used in a Scrum process to make task estimations for a sprint. Deciding whether a story(task) is small or large requires some ...
2
votes
1answer
87 views

Estimating Fixed Price Project Cost Payments via Monthly Milestones

I have spent the last few days searching for an answer on how to use MS Project (2010 in my case) to estimate a project's cost via milestones that are split along a long program (2.5 years). The ...
1
vote
2answers
66 views

Should we estimate business users' availability for an agile project?

I recently submitted my project estimations for peer review and I have been advised that we need to estimate the business users' availabilities that will be required to complete each Sprint. I was ...
2
votes
3answers
81 views

When is user stories estimation supposed to take place?

I would like to know when the estimates are supposed to be produced. Last time I was part of a Scrum team, I think we were providing initial estimates (that would then be quickly reviewed and ...
0
votes
0answers
49 views

How to calculate earned value (EV) in this example?

You are managing a project with a total planned budget of $100,000. To date, you have actually spent $41,000. When you look at all the activities you have completed to date, you see that you ...
0
votes
1answer
129 views

How to implement TFB / NFC / 1 (Sprint) estimation technique?

Reading some old posts like this one, I noticed that the TFB / NFC / 1 (Sprint) estimation technique could be useful for teams moving towards agility. Happens that I failed to find over the internet ...
4
votes
3answers
142 views

Do bugs from previous Sprints need to be estimated?

For example: in Sprint 2, on story, A Tester raises 4 bugs. 2 bugs got fixed in the same Sprint. The remaining 2 were pushed to the Product Backlog. At Sprint 6, we are picking those 2 bugs of story A ...
1
vote
1answer
73 views

Lean Kanban without estimates or time logging

I work in academia (research). Tasks are varied and almost always involve delving into topics that produce more tasks when you are more informed. A pull system seems appropriate rather than an ...
3
votes
3answers
726 views

Calculating project forecasts in Jira

As a Scrum Master, I want to help my Product Owner to make an educated guess of when features in a project will be implemented, in order to communicate with stakeholders so that they can manage Scope. ...
0
votes
5answers
2k views

Project Management Gantt Tool makes All Tasks Concurrent

All the gantt tools I have tried make all tasks concurrent, until I specify start date or dependencies. I do not yet know the start date, and not all tasks have dependencies (well not enough to fully ...
1
vote
2answers
114 views

How to estimate a Research and Development project?

Our software team has been doing a lot of R&D work to improve the performance of our product. Of course, the management team would like to know how long it's going to take to improve the ...
4
votes
4answers
902 views

Story Points flaw?

Forgive me f this has been asked before, I read some similar questions (linked below), but didn't find the answer I was looking for. Our team is fairly new to them and trying to figure out how to ...
23
votes
4answers
4k views

Task estimation for PMs who are not developers

While working Agile, how can a PM estimate a task when he/she is not a developer?
16
votes
6answers
3k views

In scrum should incomplete stories be re-estimated or does the original estimate get burned down when it's finally completed?

If I have a story that's been estimated at 10 story points and we don't manage to complete it in a sprint how do you handle estimates for the sprint in which it's next included (assuming it gets ...
6
votes
2answers
293 views

Estimate Item Delivery from Throughput plus blockers

We are combining all of our projects into one Kanban board. Since we are only ever one team, it seems to make the most sense to combine everything to one board and prioritize as we can all only work ...
7
votes
4answers
144 views

What is the term for actual delivery time will be varied by 4 times from estimation?

I remember I once read in Wikipedia about a law stating that the actual delivering time will always be 4 times less to 4 times more from the estimated time, even when you aware that law and know every ...
5
votes
2answers
567 views

Adding test cases to user stories (Backlog items) before the sizing session

Scenario: I was asked by management if it is a good idea to add test cases to user stories before the sizing session. This will involve investigating the item, writing test cases, speaking to ...
2
votes
4answers
225 views

We work with fixed scope, price and time - why should we use Story points?

We deliver projects in fixed price, fixed time and fixed scope environment. We have a contract that specify those, specifications of features. Recently, an agile couch was trying to convince me to ...
2
votes
1answer
68 views

How to treat users stories which were almost completed at the previous sprint? [duplicate]

How to treat users stories which were almost completed at previous sprint but didn't meet Definition of Done due to testers were late for some reason. Suppose one of those stories was 5 story points, ...
3
votes
3answers
79 views

How to structure estimation requests when there is a middle-man

We have a long term project, call it Project A. Our direct client (DC) is an organization between us and the Product Owner (PO). Every now and then we're being asked for estimates. The problem is ...