Questions tagged [estimation]

For questions about the estimation of the project's parameters, such as time or cost.

Filter by
Sorted by
Tagged with
4
votes
4answers
722 views

Developer keeps underestimating tasks time

This is one of my first projects in charge, and I am leading a team of 2 dev, a senior and a mid-level one. The mid-level developer is underestimating his time on most tasks. He is telling me that ...
10
votes
9answers
2k views

At whose expense is the stage of preparing a contract performed?

Let's suppose a customer needs a software product and comes to a software development vendor. The customer describes the product and maybe even provides business requirements documentation (BRD). Then ...
3
votes
4answers
88 views

How should I deal with common dependencies when estimating stories in Scrum?

There's something that has always bothered me with Scrum. Hopefully I can get some insight here. With Scrum, we try to break the backlog down in vertical slices. Let's say stories A and B. These ...
2
votes
2answers
127 views

How to estimate sprint velocity when there is a change in story points in scrum

Initially, the Product Backlog contained 350 story points of PBIs. After completing 7 sprints of development, the Product Backlog contains 140 story points of PBIs . The average velocity is 30 per ...
4
votes
2answers
111 views

Planning Poker Reluctance

I am joining a new team that has been struggling with sizing for years. They have not been making sprints. They have been setting their own Story Points, and historically they have correlated them to ...
9
votes
4answers
3k views

Does the scrum master also estimate user stories?

We recently started working with scrum on an new (large) project. I am a developer but do not take part in that project other than my role as scrum master. I know about the software they use, but don'...
4
votes
3answers
210 views

Has anyone actually tried “The Bermuda plan” and if so, how did it go?

The Wikipedia page on Brook's Law includes the following sentence: The Bermuda plan, where most developers on a project are removed ("sent to Bermuda") and the remaining are left to ...
0
votes
2answers
101 views

How to estimate amount of work/man hours for an unfamiliar task? This project is fixed bid project from customer

How to estimate amount of work/man hours for an unfamiliar task? This project is fixed bid project from customer. And most of our project is fixed bid project, for the past 3 - 4 project we are ...
1
vote
1answer
266 views

How do you estimate epics?

Let's say we have a brand new project and we want to raughly come up with a bunch of releases and its dates to give the business a vague idea of when we will finish. Obviously we have all our user ...
12
votes
7answers
1k views

In scrum, how do you track/estimate points when multiple tickets overlap their work?

I've never been fully able to answer this question, and from a lot of searching I haven't been able to get the right keywords to find anyone who's asked this question in the way I mean it. Say that ...
0
votes
1answer
50 views

How to better use Story Points in our teams?

I have several development teams that moved from hours to Story points 6 months ago. Since then, we have experienced several issues with using Story Points, and I hope you can help me and us: When ...
1
vote
1answer
95 views

Minimum number of items in the Product Backlog for an Affinity estimate

I found this question in an exam and I'm puzzled: Affinity estimate is a technique used for arriving at a high level estimate quickly. What should be the minimum number of items in the Product ...
5
votes
7answers
1k views

How reliable is velocity?

I'd actually like to devide the question in the title in two related sub questions: In your experience, how reliable is the velocity in letting the product owners forecast the delivery date of a ...
8
votes
7answers
3k views

Estimating when my project will be done

Suppose my project has 150 story points of work remaining to be done. Over the last 10 iterations the team has achieved the following velocities of 16, 12, 13, 5, 14, 7, 6, 12, 16, and 14. Assume two-...
6
votes
5answers
730 views

We have a velocity of zero

I am a Scrum Master for a small development team of 7 developers and 3 testers with 2 week sprints. The product we are working on is large with a lot of modules. The breakdown of the modules is ...
1
vote
2answers
637 views

How to Calculate Effort Variance in Scrum

My team currently works in 3 week sprints and we are capturing Key Performance Indicator (KPI) for each sprint. One of the KPIs is Effort Variance (EV) per sprint My question is at the end of the ...
3
votes
2answers
162 views

What’s the name for the estimation method where only one team member estimates at a time and others have a veto right?

This method is usually used for estimating quickly on a large chunk of user stories to get a feeling on the overall project effort or part of it. I know this estimation method has a name but I have ...
20
votes
9answers
8k views

How should a Scrum master handle disagreements about story-point estimates in Scrum?

For example : Some see its userstory (e.g. 2 points) and others see technical complications and judge that the story should be 20 points. The 2-point voters say, "I understand your opinion, but don't ...
34
votes
7answers
15k views

Is Planning Poker Bad for Software Development Teams?

We have a project manager that is adamant about planning poker. I have found that this adds stress to everyone on the team, and the times are always wrong. We have different skill levels on the team ...
0
votes
3answers
109 views

When estimating with story points should developers and QA provide their estimate based on their individual idea of complexity?

The question was as follows (and from the QA member of the team): Should I think about how complex it is from a QA AND a developer's perspective? Or just from a QA's perspective? Since story points ...
0
votes
3answers
101 views

How to estimate delivery date with unidentified tasks

Given a software project which is complete when all of its deliverables are delivered, in which each deliverable has sub-deliverables, in which each sub-deliverable has multiple tasks assigned to it ...
1
vote
2answers
93 views

How should I handle project cost (in time) to a client without committing too much work?

currently we have a client that have a series of requirements (very broad and general) for an app. I as the PM was asked by my boss to estimate how much hours of work were required to make that app. ...
7
votes
2answers
347 views

Any research of the accuracy of Story Points?

One of the main questions about Story Points is what is their accuracy. Has any research or survey been performed to analyse their precision? For example what is the accuracy of the completion date ...
5
votes
5answers
4k views

Definition of a Story Point [closed]

As far as I'm aware there's no definition of Story Points and how to compare them. Each person in a team may have his personal understanding of the correlation between an effort and Story Points. Isn'...
0
votes
2answers
116 views

Slowing down of an agile team as the development progresses

Let's consider an agile software project. In the beginning of a project each Story can be implemented quite quickly because the code base is small, there're few dependecies between different parts ...
0
votes
1answer
153 views

Kanban Estimation using Littles Law

I am new to Kanban, I am aware that Kanban is a flow system and estimation is optional. My stakeholders have requested the following: Provide a delivery date for the remaining items (WIP)? If the ...
1
vote
3answers
258 views

how to do spike/research story which can run more than 1 sprint

I past I have done a research/spike story which was a new area for me. Building big excel, debug ntml2 jar for authentication issue. our sprint was 2 weeks and it runs for more than 1 sprint, what ...
0
votes
1answer
157 views

Total cost increases every week,

I am using the MS project,i have noticed that the total cost column of the project increases every time i enter actual work. i am not sure why is that! could it be because some of the ressources are ...
2
votes
3answers
230 views

Task estimation and probable risks

Let's suppose we are estimating a task (not by the planning poker). We have discovered that there are a few possible problems (risks): Risk 1 - with the probability p1, ..., risk N - with the ...
1
vote
4answers
194 views

Team added “Daily Scrum” as a task in Jira. How do I get rid of this?

So I am just joining a new team. This team is using "Daily Scrum" as a task because according to them it is a "task". Obviously I want to help them understand that it is not a task, just like ...
2
votes
2answers
112 views

How to estimate and plan with a distributed, part-time team?

The situation: We are a small, fully-distributed software solutions provider. We serve multiple clients, and given our size that means every team member is on multiple, part-time billable teams. ...
0
votes
2answers
77 views

When should we stop estimating?

When using Scrum, are the estimated story points for completing an User Story sufficient, or should the estimate be taken at the task level?
2
votes
2answers
403 views

What is an “e zero” estimate

I am often asked to provide an "e zero" estimate for a piece of work. I have been assuming up to now that it means "rough estimate". Does anyone have any link to what this means specifically. I ...
0
votes
2answers
157 views

Fibonacci scale project estimates: how is it not vulnerable to misunderstanding by management?

The Fibonacci sequence is to assist developers with project estimates. The concern is that we consistently see management use the points derived from Fibonacci sequence estimates to determine project ...
1
vote
3answers
84 views

Tracking progress of a team working on small tasks

Our software team works on small tasks. Each task takes about 2 weeks. There are developers whose performance is twice bigger than the other's (the level is the same). Everybody just writes how much ...
0
votes
2answers
72 views

Tasks during sprint planning

For the next sprint, Jira displays the total number of story points in the backlog, calling it "Estimate.". This number leaves out tasks, which are estimated in hours, not story points. This makes it ...
5
votes
3answers
414 views

Dev went on vacation leaving his work unfinished. How to manage this without informing the customer?

I would like to discuss and hear some advice from you about a pretty common situation. We develop the functionality that has huge business value for the customer’s project and thus the customer is ...
0
votes
1answer
74 views

How are low ambiguity and low complexity tickets dealt with when they have a high work cost?

In our scrum team, we can often get user stories which are not very complex and not ambiguous but have a high amount of leg work associated. Example: We receive a user story to replace the name of a ...
1
vote
1answer
72 views

Is there any estimation method to estimate end user testing?

Is there any estimation technique that can help us to estimate the number of needed test cases in traditional software projects? For example, we have a Software requirements specification (SRS) with ...
1
vote
1answer
213 views

How can we persuade team members to estimate in story points instead of hours?

We use story points to estimate our user stories. We find that story points solve the problem of underestimating the amount of actual work which is required to complete a task, as it takes the ...
2
votes
2answers
48 views

When choosing the largest and smallest stories in a backlog for estimation how does it impact each sprint?

An article I came across suggested that we should pick the largest and smallest story in the prioritised backlog and relatively estimate the remaining stories. This makes sense. However, I was ...
2
votes
1answer
194 views

How can I calculate how many developers do I need and how long it takes to complete the project? [closed]

I am trying to create an LMS system using Angular and NativeScript. It's a LMS web application like Adobe connect (although a simplified version) that will be written in Angular 8 for example, and a ...
3
votes
2answers
112 views

Should single user story contain estimations for each involved guild in full-stack development team

Problem We're working in a full-stack development team composed of three guilds (backend, frontend, QA), so as a team we share a single sprint board. User stories we take into our sprints are written ...
0
votes
1answer
84 views

RFI response form asks for “Assumptions” as just a single money amount

I am surprised by the last row in this RFI response form: My project's initial fees are 1m$, recurring fees are 100k$/year, under the assumption that I provide only the software and they run it on ...
8
votes
4answers
2k views

How can you estimate a spike story?

We are working on a technology of which the team is not sure how would it go. I would like to estimate and timebox this story. However, the scrum team has to have goal or a shippable product at the ...
0
votes
1answer
107 views

Scrum task estimation methodologies

I want to know about tasks analysis and estimation methods that can be used in a Scrum process to make task estimations for a sprint. Deciding whether a story(task) is small or large requires some ...
1
vote
2answers
76 views

Should we estimate business users' availability for an agile project?

I recently submitted my project estimations for peer review and I have been advised that we need to estimate the business users' availabilities that will be required to complete each Sprint. I was ...
2
votes
3answers
214 views

When is user stories estimation supposed to take place?

I would like to know when the estimates are supposed to be produced. Last time I was part of a Scrum team, I think we were providing initial estimates (that would then be quickly reviewed and ...
0
votes
1answer
362 views

How to implement TFB / NFC / 1 (Sprint) estimation technique?

Reading some old posts like this one, I noticed that the TFB / NFC / 1 (Sprint) estimation technique could be useful for teams moving towards agility. Happens that I failed to find over the internet ...
2
votes
1answer
77 views

Lean Kanban without estimates or time logging

I work in academia (research). Tasks are varied and almost always involve delving into topics that produce more tasks when you are more informed. A pull system seems appropriate rather than an ...

1
2 3 4 5
7