Questions tagged [metrics]
Quantitative or qualitative data about how project activities, processes, or outcomes are measured.
98
questions
0
votes
0
answers
29
views
How to create a report for an epic - issues created, added, removed, and closed as done?
I am trying to create a report (either Jira or eazyBI) that shows entries within an epic or initiative on a monthly basis - the entries newly created, removed, and closed as done.
We have 2 ...
1
vote
3
answers
489
views
How can I close an Epic with open defects?
I have an Epic. Some defects are closed, but one defect is still opened and deferred until the next release. How can I close the current Epic since one ticket is still not closed?
0
votes
1
answer
47
views
estimating time for a step that has batch process in project management
Im trying to estimate cycle time of a process. For example if I am making widgets where each widget type has different process times. However in one of the steps in the process, it is a batch process ...
0
votes
1
answer
74
views
Development Team Objectives [closed]
I run a development team of around 15 developers/testers. The organisation hasn't been very objective driven in the past and it's something I would like to change. Can anyone offer any advice on how ...
1
vote
1
answer
55
views
How to handle unequally distributed material cost in EVM
I am looking into Earned Value Management and seem to be unable to find anything useful on how to deal with large material cost, which are not equally spread over the project.
All examples that I have ...
9
votes
9
answers
4k
views
Is a project manager responsible for completing a project on time?
Of course, a project manager should strive to complete a project on time, but is it correct to say that it is a project manager's professional responsibility? I mean that no matter how professional a ...
9
votes
6
answers
1k
views
Is tracking billable time for Scrum ceremonies in JIRA an anti-pattern?
We use Story Points for estimating complexity of User Stories, but we bill hours to the client. This is the very first Scrum project within our company, and we don't have enough data to calculate a ...
0
votes
1
answer
27
views
I need a way to group or nest items within columns
I am trying to analyze a data set that has nested data. I have a column that contains projects, a column that contains activities of those projects, and dates that those activities were completed. I ...
1
vote
1
answer
30
views
How to create data entry template to be updated monthly by 20 different parties online - focus is recycling data?
The task at-hand is I coordinate the activity of 20 organisations, each of whom I need to collect monthly data from directly, about the tonnages and types of elecronic items they collected for reuse ...
8
votes
4
answers
2k
views
Is gauging a team's performance using scores assigned by other stakeholders valuable?
We have a new way of gauging teams.
All the individuals involved (business owners, managers, stakeholders) except the team itself gauge how they felt the team did using a score. If the score is ...
1
vote
1
answer
121
views
Aggregate KPI for time and performance
I have a project KPI that I can measure daily: the use of a bottleneck resource, measured as the % against a target value of hours of use.
Example:
Week_1
day_1: 100%
day_2: 95%
day_3: 95%
day_4: ...
1
vote
2
answers
3k
views
How to Calculate Effort Variance in Scrum
My team currently works in 3 week sprints and we are capturing Key Performance Indicator (KPI) for each sprint. One of the KPIs is Effort Variance (EV) per sprint
My question is at the end of the ...
2
votes
2
answers
66
views
Net Promoter Score-like metric for internal "monopolistic" product
I'm working on product that is integrated as part of the bigger package of products. One kind of stakeholder are other product teams that request features and use features from us. Other kind of ...
14
votes
3
answers
3k
views
Is velocity a valid measure of team and process improvement?
I've asked this question to few scrum masters: "How do you tell, that your team is improving? How do you tell that actions taken during retrospective result in real improvement in efficiency/...
4
votes
1
answer
93
views
How to make Agile metrics useful to stakeholders and project managers
I have started using Actionable Agile lately. This tool is essentially used for Agile Metrics e.g. Cycle time, throughput, monte-carlo predictability etc.
Does anyone know how I can translate this ...
2
votes
1
answer
57
views
Why is customer churn rate calculated in relation to users at the beginning of a period, not people at beginning plus acquired?
Let's take the customer churn definition from this article, that I have also seen in other sources.
Let’s do the maths with one example: On January 1st you have 1000 customers. 100 of them are not ...
1
vote
2
answers
251
views
Did I input the correct ACWP, BCWS and BCWP values? [EVMS]
I know I performed the calculations correctly but I'm not confident about the 3 values in red
0
votes
2
answers
6k
views
How can we track Business as Usual (BAU) work?
My team, which consists of network architects and developers has been running Scrum for the past couple of months and the biggest issue we have is how we're supposed to record BAU work.
We consider ...
1
vote
3
answers
161
views
Can code base metrics be used for budgeting for software engineering or code maintenance?
Recently my manager asked my team for some metrics on the code base, in order to budget for my team. These are the metrics requested:
Number of source code files
Code Lines
Comment Lines
Blank Lines
...
1
vote
2
answers
284
views
How will team changes impact velocity of a Scrum project?
Question
If there are 8 members in a team assigned to complete the project. 20% of the team left during the particular sprint. Does the velocity change? If so, what would the velocity changes be?
...
1
vote
1
answer
158
views
How can the team improve the likelihood of completing each increment?
If a Development Team doesn't have the skills or tools to create a “Done" increment, are there techniques that can be used immediately that will allow progress on the increment to be easier to track? ...
3
votes
3
answers
1k
views
How to count the amount of times a JIRA issue has been in a specific state?
In my project one of the metrics we want to use is the amount of times a JIRA issue is moved back from "QA" to "Development." We call it "comeback rate."
Looking for % of items that were resolved by ...
5
votes
2
answers
458
views
Velocity calculation based on number of user stories completed in a sprint
In one of the projects, the velocity calculation is done based on the number of user stories that the team is delivering in each sprint.
They are using story points to size but still the velocity is ...
6
votes
2
answers
3k
views
What metrics can we generate from t-shirt sizes (rather than story points) when estimating user stories?
If I am using T-shirt sizing for my user story estimates, what metrics I can measure and report? We currently use a Sprint burn-down chart when using story points.
1
vote
1
answer
162
views
What metrics should be used for tracking the quality of research project?
It is known that software development tasks should be controlled by some project management metrics, that show the progress of work at each particular moment of time.
What metrics are better to be ...
2
votes
4
answers
191
views
Agile ("Scrum") "Metrics" Question
My team has recently transitioned from essentially zero project management (other than the "put out fires as they happen while trying to stay on top of current workload") to something more Agile with ...
0
votes
3
answers
346
views
If you measure requirement volatility, how do you handle inconsistent requirement size?
I would like to measure requirement volatility but the problem is that our specification is not consistent in size of requirements. Sometimes, one requirement describes a whole workflow. Sometimes it ...
6
votes
1
answer
321
views
What Does "Commitment" Look Like with Agile Projects?
When engaging with a client on a project that will be developed using agile methodologies, what is being promised in the delivery of the project? How do you know if that promise is objectively met?
...
1
vote
1
answer
599
views
How to use historical cycle time to forecast project completion
I have been inspired by Daniel Vacanti's talk (link) about using cycle time to forecast project completion.
So I collected the following user stories metric in the course of four sprints:
Average ...
0
votes
3
answers
831
views
Metrics to measure teamwork / team spirit
I recently started as manager of a team of 10 developers that did manage itself before. I noticed that they do not act that well as a team but rather everybody fights for his own. There are a lot of ...
3
votes
1
answer
529
views
Sprint planning, review: velocity,capacity, forecast and how this values relate?
I'm fairly new to Scrum and its sprint planning/retro (etc), our team today was trying to calculate velocity, capacity and forecast for the following sprint, but we just realised that no one actually ...
1
vote
3
answers
694
views
How to measure bug incidence in Production?
We have a fully automated deploy process but as we now sometimes we break things.
When this happens the developer just apply a hot fix in (branch, fix and opens a PR) the trunk development. As you ...
1
vote
2
answers
733
views
Cycle Time - Story vs Task?
I am trying to measure the cycle time of my team. The problem is that the issues (tasks or stories) have very different sizes. Sometimes someone just creates a task like: "Create a backend api", that ...
3
votes
1
answer
300
views
If SAFe must be continuously calibrated and measured in ideal days, why does the framework say recalibration is unnecessary?
TL;DR
SAFe says you don't need to recalibrate estimation, but requires estimates and other metrics to be normalized across one or more Agile Release Trains. Context, question rationale, and the ...
3
votes
7
answers
5k
views
A simple estimation accuracy formula that always yields 0-100?
I'm just beginning, and despite my search, I cannot find any simple formula that would return a number between 0 and 100%, i.e. I do not care whether there was over or underestimation.
The simplest ...
2
votes
4
answers
710
views
Measuring code productivity between team members
First question, so here goes!
Between two programmers on the same team, one has produced more code but more defects, whilst the other has produced around 20% less code but significantly less defects ...
1
vote
3
answers
3k
views
How can I track time spent by assignees on each ticket in JIRA?
I want to track time spent by each agent on each task on a JIRA Kanban board. If an agent was assigned a task and he assigns it back to me, I want to track the time he spent assigned to the ticket. Is ...
3
votes
2
answers
140
views
Should we count a story that is no longer required by Client/PO/Management in our velocity?
We have finished a story which is no longer required by the Product Owner (PO) or Management. The completed story is not going to add any business value. What should we do in this case? Should we ...
0
votes
4
answers
3k
views
How much volatility should be acceptable among Scrum teams?
There is varying volatility across Scrum teams. I understand that volatility can be caused by many variable factors. The table below shows how much it's varying across teams:
Velocity ...
0
votes
3
answers
22k
views
Scrum , Velocity calculation and Sprint Calculation
Following figures showing the performance of a Scrum team during the first 6 sprints of a project.
Sprint: 15 SP
Sprint: 5 SP
Sprint: 20 SP
Sprint: 15 SP
Sprint: 25 SP
Sprint. 10 SP
Question 1: ...
3
votes
2
answers
3k
views
How to calculate velocity when using fibonacci estimates
We are using Scrum and our user stories are estimated using the Fibonacci sequence. I understand the benefit of using the Fibonacci sequence for estimates. In all references to velocity it is ...
3
votes
3
answers
311
views
What is your focus: increasing metrics or improving processes?
I noticed (in our company) that Scrum Masters have one of the approaches:
Start with metrics and work on improving the numbers: e.g. a new user story comes up during sprint, the team might reject it ...
1
vote
4
answers
515
views
How to measure efficiency of tasks for a very small project
I am a programmer using sharepoint, and I am the lead and the project manager since I do not have subordinates under me. My boss is non-technical and doesn't have much visibility in what I do and just ...
7
votes
5
answers
738
views
What is the difference between metric and KPI?
I know that KPI is a metric and metric is not necessarily a KPI, but I still don't understand the difference between these two. Let's take Periscope application as an example. What are possible KPI ...
0
votes
1
answer
422
views
How to measure the value of Product management?
There are 2 types of product management broadly - New Product and Existing products. For an existing product, the task of the product manager is to increase revenue, in a declining market share ...
11
votes
7
answers
4k
views
Sprint Goal and Failure of a Sprint
My organisation is pushing for strictness on what they consider a Sprint Failure or not.
They have decided that if there are any User Stories not fully completed (as per the DoD) at the end of the ...
5
votes
6
answers
2k
views
How does a scrum team measure its productivity against its productivity pre-scrum?
In our company, we are moving some teams to scrum. Before scrum, it seems we don't have a lot of visibility into the productivity of the teams, and we don't necessarily have a way to measure the ...
10
votes
3
answers
610
views
Relevant metrics for issue closure estimation
What metrics can influence or help with such an estimation?
I am mostly interested in applying such metrics on GitHub projects, using their issues history. Based on how fast they solved their ...
0
votes
1
answer
261
views
PMO Value Add Metrics
What would be the best group of metrics to use to measure PMO value in services organization? What do you use in your org,if any? By this I am talking about more of the soft metrics like repeat ...
2
votes
4
answers
2k
views
How do you measure time units in sprint velocity?
I am trying to get my head around "Story points" using the Scrum methodology. As a starting point, I have been following the following article:
http://scrummethodology.com/scrum-effort-estimation-and-...