Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

0
votes
1answer
16 views

Autosave: How to prevent it being re-enabled with each new session

I find the Autosave feature to be very intrusive and it also interferes with some macros I run. I know how to disable it via File/Options/Save/untick the box, but even if I then immediately save my ...
0
votes
0answers
23 views

Work days and Duration does not match

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days ...
-1
votes
0answers
18 views

Ressources issue [on hold]

agile-project-management I'm using MS Project 2013 (pro) for Project, time and planning management. (using Already used time, Work to do, and others things.) For this I use 2 main views : Gantt ...
0
votes
0answers
12 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
0
votes
2answers
28 views

Sharing a file without them being able to edit the main file

I need to either create or share my project with others. I don't want them to be able to make changes to my project though. I've tried creating a new one, but they still are able to make changes to ...
0
votes
0answers
20 views

Resource leveling: Consistently get different result if I level twice, even with Clear before leveling ticked. Why?

In my plan of around 1250 tasks, consisting of 250 unrelated projects each with 5 tasks, and where the resources are generic resource types (eg PE, FE, PM etc) I find that when I first click Level All ...
0
votes
1answer
15 views

Tracking Gantt Chart Not Showing All Tasks

I am trying to do an earned value analysis and there are tasks in my normal Gantt chart that when I switch the view to tracking gantt are not visible. Could this have to do with where I set my status ...
1
vote
1answer
28 views

Leveling; getting unexpected results

I have spent hours reading up on the leveling algorithm and trying various alternative approaches but I have a problem I simply can't figure out. I'm using MSP 2016. My schedule consists of around ...
0
votes
1answer
24 views

MS Project - Summary Task split by leveling

I have a summary task, and have the 'Leveling Can Split' option set to No. The four subtasks which are in sequence, also have LCS set to No. In the Leveling options I also have 'Leveling can create ...
1
vote
0answers
23 views

Determine to which task a resource is allocated on a particular day

Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
0
votes
0answers
25 views

Check the last update of subprojects in MS Project

To see what all my PMs are doing, I have a Master project where I include all projects of my PMs as subprojects. That way I have an overview over all tasks in the company and since all have to use the ...
0
votes
1answer
46 views

Working and non working days

I want to ask if I need to have non working days and working days in a same day. Can we do that in microsoft project? For example Saturday (same date) for items Consultant approval I want to set it ...
1
vote
1answer
38 views

EOT and LOT vs EET and LET

Are the Earliest Occurrence time and Latest occurrence time same as the Earliest Event time and Latest event time or are they different? If they are different can you please explain to me what are EOT ...
-1
votes
1answer
17 views

MS Project 2016 updating Actual Cost figures for Cost Resources that are set to accrue at the end of the task

I am having an issue where MS Project 2016 is prorating the actual cost figures for cost resources that have been set to accrue at the end of the tasks. I have tried everything I can think about and ...
1
vote
1answer
23 views

Printing specific date range in ms project 2016

I am trying to print a specific date range from a gantt chart view in ms project 2016, but all that prints out is the whole project. Can you help?
-1
votes
1answer
21 views

MS Project burndown for outline level

I'm working on creating a burndown graph for a large project that I'm trying to schedule, but I don't want the sub-tasks to be counted as a remaining actual task for the burndowns. Is there a method ...
-1
votes
1answer
32 views

MS Project - Multi-year Inflation

I am managing a 3 year project in a country where the average annual inflation rate is 12%. Instead of going through every item and entering "+12%" into the cost rate table for each item, is there a ...
1
vote
1answer
25 views

How to Import Resource Availability from Excel when it varies by month

I have a number of generic resources, eg Engineers, where each individual is treated as interchangeable with all the other Engineers. I want to show their availability as for instance 100% in October ...
0
votes
2answers
39 views

ConsolidateProjects Method: how can I import Sub Project Summary task Custom field contents?

If possible I want to avoid using Resource Pools and embedded project files as I have had problems with these in a Sharepoint environment, so I am exploring using the ConsolidateProjects Method to ...
2
votes
1answer
30 views

How to make identical changes to multiple sub project files

I am about to create a master plan that will contain over 200 small sub project files. Each sub project file will have common elements such as standard Custom fields. I have created a template for ...
1
vote
2answers
56 views

Auto populate project level Priority field based on lookup to Excel file table

I have multiple small plans (managed by PMs) embedded in a master plan file which I manage. The PMs can add tasks to the sub plans as necessary. After receiving each sub plan and refreshing the ...
-1
votes
1answer
69 views

MS Project 2013: Summary task not showing duration correctly

I am working on MS Project 2013. The summary task No. 6 is not showing the duration correctly. Refer to the picture below. Please help.
3
votes
3answers
118 views

Need help- Documentation for non-technical people using Agile

Now we are using Agile and hardly create BRD\FRD, we create user stories, and all this is good for everyone working in the same department. Including the stakeholders. However, if I would like to ...
-1
votes
1answer
44 views

Why does the graphic indicator not show for milestone task?

Why for milestone task, the graphic indicator did not show? The formula to consider is the following: IIf(CDbl([Baseline Finish]>60000)," Not Baseline",IIf(([Baseline Duration]=0 Or [Duration]=0),...
0
votes
1answer
20 views

MSProject show main resource on Summary tasks

How can I show the main (resource with maximum hours) for Summary tasks. I suspect I would need to set a custom text field to show this, but how would I structure this? thanks
-1
votes
1answer
33 views

Change manually to auto schedule

I want to change the start date of a specific section in my project. When I do that, it automatically changes the mode of this section from auto to manually schedule. Is it possible to change the ...
1
vote
0answers
24 views

MS-Project 2016: Sort does not work

With MS-Project 2016 (version up-to-date) I have created a custom report (showing filtered tasks). I want to sort it ascending by Finish date (soonest finish on the top). But it does not work. It ...
0
votes
1answer
36 views

I want to create a summary task without indenting the subtasks

Is there a way to create a highlevel task that will summarize all the subordinate tasks without indenting the subtasks?
-1
votes
1answer
22 views

MS Project, add hours directly in resource usage

at my work we use MS Project 2010 to run our Monday morning scheduling meeting, from Resource Usage view. In the version I inherited on my work computer, I can change the number of hours or add a new ...
1
vote
1answer
39 views

MS Project - Predecessor 'or'

How do I enter 'or' logic into the predecessor field? For instance, task 4 can start when task 1, 2, or 3 ends. We don't know which of 1, 2, or 3 will begin or end first. Thank you
1
vote
1answer
78 views

Printing Gantt charts

When I try to print my Gantt schedule, it hides a bunch of my information rows. How can I fix this? See the comparison between actual Gantt and print preview below:
0
votes
1answer
33 views

Estimating Fixed Price Project Cost Payments via Monthly Milestones

I have spent the last few days searching for an answer on how to use MS Project (2010 in my case) to estimate a project's cost via milestones that are split along a long program (2.5 years). The ...
0
votes
1answer
19 views

Calc days based on Start and Finish date - MS project

When I'm editing start or finish dates, Project moves the other based on the duration. How do I make it change the duration instead so I don't have to keep moving the start and finish dates back? ...
1
vote
1answer
31 views

How can I show a list of all tasks without incomplete predecessors in Microsoft Project?

I would like to see a list of all tasks that satisfy one of the following: The task has no predecessors Every predecessor that the task has is marked as 100% complete. I can add simple filters from ...
0
votes
0answers
21 views

How can you represent a task which only takes place at specific days on MS Project?

I want to represent a task which only takes place at specific days on MS Project: for example, on 01/01/2018 between 9:00 and 11:00, on 03/03/2018 between 10:00 and 12:00 and on 12/03/2018 between 11:...
0
votes
0answers
32 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for a server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
1
vote
2answers
65 views

How do I identify critical path in MS Project?

I'm using MS Project for my project management works. Would like to know how do I identify the critical path of the project and the dependencies?
0
votes
1answer
72 views

Ms project - assign different resources with different schedules to a task

I'm new at ms project and I have some questions. Let's suppose that I have a human resource named "T1" that works from 2 pm to 11 pm, and that we have a machine named "m1" that can be working all day....
0
votes
2answers
361 views

How to show slippage in MS Project 2016?

Probably a noddy question, but need to ask. I'd like to be able to demonstrate real time slippage on my plan, for remodeling impact purposes. I have both original baseline dates and current dates ...
0
votes
1answer
48 views

Dashboard question on microsoft project

Completion % captures the current progress.. I understand that. Is there a way to come up with completion % if all work (hypothetically) was completed on time as of today? e.g., Assume the total ...
1
vote
1answer
48 views

MS-Project historical timeline

I am using Microsoft Project 2003 for an historic timeline, this means historical dates that go back 1000s of years. I realize using ms-project may be overkill, but it is actually the same as a ...
0
votes
1answer
43 views

How to calculate the completion percentage relation by start and finish dates

I need to calculate the current date in relation to the start and end dates of a task and would expect to see a field that shows the completion percentage. Something like this Question or this ...
1
vote
2answers
140 views

How to organize a 6-month project plan for agile?

We have a charter to build a product in 6 months. I'll preface this by saying that my manager wants us to use waterfall, even though our development process is agile. With that said, I have been ...
3
votes
1answer
44 views

MS Project 2010 - Create project from a set of variables

Being new to MS Project, I am wondering if I can create a project based on a defined template modified by some variables. I am dealing with several (20+) projects I have to manage parallel. The ...
0
votes
1answer
204 views

In Microsoft Project how to get change in resource max units to cascade to tasks automatically

I had already defined a bunch of tasks, and assigned resources 1 and 2. The durations of the tasks were calculated on the resources Max Units availability at the time of assignment. Later I went ...
0
votes
1answer
70 views

How to get a correct duration in MS Project?

I have two effort driven tasks with a work of 8h for each of them. If I delete the duration of task 5, Project fills the field with 1 day? What I need to do is update the work for this task, for ...
0
votes
0answers
26 views

ms project scheduling

Quick question about scheduling and resources I am small general contractor. When I do my labor estimates or scheduling I base the day on a 4 person crew(32 person hours). So what I am trying to do in ...
-1
votes
1answer
31 views

How to communicate/word cost ranges?

When you display cost estimates, when it comes to ranges, what words do you use to convey: Lower End of the Range, and higher End of the range. The terms I chose (Min/Max) were not liked , so I was ...
0
votes
0answers
19 views

Recommendation for MS Project courses

I'm looking for some recommendations on courses for building and managing a Microsoft Project Schedule. I've looked over this SE question for reference material and books. If anyone knows any good ...
0
votes
0answers
24 views

Microspft project showing incorrect baseline hours when baseline the tasks

Microsoft project plan: I am trying to baseline the newly added tasks, but the total hours is showing differently each time when I baseline it. It shows some random decimals values. All points are ...