Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

Filter by
Sorted by
Tagged with
0 votes
2 answers
69 views

Change from waterfall to agile [closed]

I have been working on different kind of software projects implementation using the water fall methodology. now some of my clients want to shift to agile methodology. what do I need to take into ...
0 votes
1 answer
28 views

Add predecessor to all tasks "x" number of tasks before it - microsoft project

Currently scheduling a 26 level building, and all 26 levels follow the same schedule. For example: Level A -Task A -Task B -Task C Level B -Task A -Task B -Task C Task X occurs on each level and it's ...
  • 1
0 votes
0 answers
28 views

Global calendars in Formula

I have the following problem and can not find a solution on google. ProjDateAdd([Start9];[Duration9];"myCal") The formula is in the field finish9 and only works if the global calendar "...
0 votes
1 answer
33 views

MS Project - Measuring Tasks by Days

Is there a way to discard of hourly measurement in MS Project, and instead having it track only the amount of days I input?
0 votes
1 answer
45 views

MS Project: How to plan tasks that have no particular order?

I am involved in software development and I have a total of 35 features that need to be implemented in our software. Each feature has been estimated for the time it will take, and there are 5 ...
0 votes
0 answers
31 views

BAC not getting updated

I am trying to make changes to ms project file. I added tasks to wbs for new config and assigned resources And then saved this to Baseline 1. And then, even changed the baseline under advanced ...
0 votes
1 answer
45 views

Scenario Analysis

I am fairly new to MS project, challenge is that the project is already delayed, and I need to test, if adding more tasks, in which we are getting external consultants will speed up the development ...
0 votes
1 answer
24 views

Dynamically linking a date

Here is my question: I have a go/no-go meeting on the calendar for go-live. We always do go lives on Tuesday. I want to dynamically link the date to always pick the next Tuesday after the go-live. ...
0 votes
4 answers
88 views

Toggling the format of dates in MS Project

I often have to change the format of the date to check and "adjust" new sequences activities. It is very inconvenient to click always through the menu so I tried to find some VBA-macros for ...
  • 1
0 votes
0 answers
20 views

How can I find the "Build Team" data in the OData REST API?

MS Project. In my project I can Build a team Assign team members to tasks. Now the task assignments are easy to read from the REST based oData API calls... but how do I find "The Team" ...
  • 113
0 votes
1 answer
48 views

How to stop MS Project from changing durations when adding resources?

I need to add 2 extra people to a certain task that currently has 4 resources assigned. As soon as I add one, project automatically extends the duration of the task without reason. I've tried ...
0 votes
0 answers
46 views

Clear cache in MS Project Standard 2019

MS Project Professional allows you to do cache clearing, but is there a way to do cache clearing in MS Project Standard? If MS Project Standard does not provide this possibility from the menus is it ...
  • 158
1 vote
1 answer
75 views

How can a generic resource be overallocated?

MS Project. My understanding is that a generic resource is specifically of infinite availability. That's why it's generic. So in the very early stages of our journey to implementing resource ...
  • 113
1 vote
2 answers
60 views

Is it possible to have personal backlogs and planning according to the prioritization of the tasks?

Microsoft Project is ok for setting up for Gannt Chart and baseline but it is not possible to see individual plans and schedules. Is it possible to integrate all? is it possible to have personal ...
  • 111
0 votes
0 answers
31 views

MS Project Calendar Mismatch between Server and Client

we use MS Project Professional, connected to Project Server 2016. Our standard working times on the server calendar are as follows: Mon 8.00 - 12.00, 13.00 - 16.30; Tues 8.00 - 12.00, 13.00 - 16.30; ...
1 vote
1 answer
109 views

Calculation of ACWP, BCWP and BCWS in MS Project

I took a look at how MS Project calculates EVM metrics and I have a doubt that I would like to clarify. Before performing the calculations of ACWP, BCWP, and BCWS, I defined a baseline. To avoid ...
  • 158
1 vote
0 answers
23 views

Is it possible to restore a single project plan from a full database backup

Using MS Project 2013, one of our PCO deleted tasks from a project plan, while work had been entered via timesheets on those same tasks, some of which weren't approved, yet. The project is now in a ...
  • 11
0 votes
2 answers
167 views

Project Plans - MS Project Vs Atlassian BigPicture

I'm an engineering project manager, responsible for the delivery of development projects. We're currently using MS project for project for task and resource management and have been recently ...
1 vote
1 answer
73 views

How to replace resource with another in all tasks

In MS Project 2016, I have a resource: call them Foo. They are assigned hours in many tasks. They must work: Task A: 20 hours Task B: 40 hours ... Task Z: 30 hours Foo quit the company, and we hired ...
0 votes
1 answer
44 views

How to properly model periodic windows of opportunity having to be taken once ("Busses")?

Suppose I have a project "Perform a business meeting" which amounts to the following steps: Prepare the meeting Tell my business partners I'm done preparing, they start their meeting Take ...
  • 101
0 votes
0 answers
100 views

Matrix Project Organisation

I need to prepare a matrix project organization for staffs to be employed in preparing Urban Project Manual using flow diagram. The ideal manpower requirement for plan preparation is as shown below:- ...
  • 23
0 votes
1 answer
88 views

Project plan updates for a very dynamic project

I am currently managing a complex development project, comprising of 17 engineers, due to the nature of the project there are many uncertainties and also the development approach frequently changes I ...
0 votes
1 answer
110 views

Ms Project Macro based on predecessors

New to MS Project Macro, but use to writing some level of macros in excel. I want to write macros that apply different logic only on the predecessors of the activity or selected activities. e.g filter ...
0 votes
1 answer
79 views

MS Project (2013): How to assess impact of overtime?

I have set up what I think is a relatively simple 2013 project using the default settings. I start with some manually scheduled milestones at the beginning followed by a bunch of auto-scheduled tasks. ...
0 votes
1 answer
1k views

MS Project: Task not adjusting to predecessor dates (auto-scheduled, 0% progress, tried unlinking/relinking etc)

I'm trying to link 2 tasks in Project and having issues with autoschedule. I set the first task to manual and put in the dates. However, when I set the second task to autoschedule and link it to the ...
1 vote
0 answers
88 views

Automatically plan tasks as close as possible to deadline

I am hoping to use MS project to plan our manufacturing. I have added all of the units we need to manufacture for the coming year, as well as their deadline date (the date the units must be ready to ...
1 vote
2 answers
183 views

repeating processes and then making changes in MS projects

IN excell "=" duplicates the original cell ( does not copy once off) so if the original cell changes the duplicate cell also changes. How do I do the same when I repeat a process a multiple ...
0 votes
1 answer
75 views

Resource List Display on Gantt Chart

Apologies upfront, complete novice to MS Project. I've got a project where I am trying to present the resources I will need for each task. When I allocate resources to the task and display them on ...
0 votes
1 answer
132 views

Finish Date not correct

I have one task that starts on 8/1/22 and ends on 1/23/23, but the duration is 2.5 days. The end date isn't calculating correctly. I have theses resources assigned to the task, total 27.2 baseline ...
0 votes
0 answers
84 views

Microsoft project Burndown Report dates shifted right by a week

I've created a burndown to show progress over time, but the x-axis dates seem to be shifted to the right by a week: I can clearly see a flattening out of remaining tasks a week earlier, but I don't ...
2 votes
1 answer
202 views

How do I Arrange All MS Project Files Side-by-Side?

I'm aware that MS Project does not allow you to have multiple instances of the application open unlike the rest of MS Office. I know that you can view multiple projects at once by clicking the Arrange ...
0 votes
1 answer
51 views

A resource can be assigned to a task before it's available

I have a resource available from 10am to 6 pm but I can assign a task to that resource with a start time of 9:30 am. I would think that should be disallowed, or at least flagged, but it is not. How do ...
0 votes
1 answer
80 views

Auto-scheduling Milestones Creating Issues

Good afternoon, I have a bunch of project milestones, past and present, that I'm trying to represent in MS Project using the Gantt Chart functionality. I currently have the milestones indented ...
  • 1
1 vote
2 answers
89 views

Microsoft Project Schedules Tasks in the past

I have a project Plan in Microsoft project. While working today, I updated a task's scheduling to be "as soon as possible". Project then scheduled the task for last month. That would be ...
  • 121
0 votes
1 answer
53 views

Export project, and add all non-empty rows into Excel table

When I export a Microsoft Project file into Excel using the export tool, the resulting XLSX file has 1 table called Task_Table1. Unfortunately that table only includes the header row. Is there any way ...
  • 11
0 votes
1 answer
265 views

MS Project Resource Graph with Allocations Shown

Is it possible to create a view of the resource graph with the task allocation identified like a stacked histogram? When someone is over-allocated, I want to easily see what they are allocated to.
1 vote
1 answer
42 views

Assigning MSP resources with future availability to tasks

I have a project with a bunch of tasks of 20 days each and each of those tasks is assigned to 1 of 4 full time resource. There are no scheduling dependencies so I am allowing Project to auto level ...
  • 13
0 votes
1 answer
126 views

Estimate date based on number of resources allocated to project

Is there any way to determine an estimated project date by number of resources allocated? I have set up all my tasks to automatic and effort driven and identified critical tasks and dependencies, but ...
  • 101
0 votes
1 answer
483 views

Unable to Create Report in Excel or Visio when using the Visual Reports Export Function

When I try to create a visual report exporting to Excel or Visio I get the following error message: An Unknown Error Has Occurred An error occurred and the requested action could not be completed at ...
0 votes
2 answers
168 views

Responsible Person for a Task

I'm creating my project in Microsoft Project. What is important to me is who is accountable for a task. For instance, there are 3 tasks that I'm 100% accountable for; 2 tasks that myself and my ...
0 votes
2 answers
54 views

Levelling - where tasks are complete, allow other tasks to fill in

In my projects, tasks are levelled and are therefore scheduled in sequence. In practice, tasks can be worked on in any order. I would like the levelling to fill in where parts of later tasks have been ...
  • 121
1 vote
1 answer
177 views

MS Project chart for multiple projects

I am a project manager and I use MS Project to manage multiple projects. I use a shared resource pool. I have been playing with the charts feature, in the resource file to try to get a chart showing a ...
1 vote
0 answers
20 views

MS Project VBA_File subs not displaying

I have a number of modules written in MS Project that are part of a template for our project managers. Randomly, a user will indicate that the needed macros are not availabe. When I have them share ...
  • 11
0 votes
2 answers
154 views

How can I scale project duration in MS Project?

In MS Project, how can I apply a uniform scale to all durations? For instance if my project was allowed to be done in twice as much time, how would I double the duration of all tasks?
  • 103
0 votes
1 answer
231 views

How to add people to a task to reduce time in MS project

How do I add people to a task to reduce the duration of a task? I have a automatically scheduled task that takes 15 days to complete with one person assigned when i try to add people it doesn't reduce ...
1 vote
0 answers
48 views

MS Project cost

I'm facing a very weird behavior of MS Project when computing the project cost. Once removing subtasks from my original project I realized that changes to some subtasks are not reflected in the ...
  • 158
0 votes
2 answers
111 views

I only have resource man hours? not their names. How would I assign these manhours in MS Project without resource names

at this point on a project I only have resource man hours but I do not know the who is working on what activity just total man hours for activity has been given. How to I assign man hours to all ...
  • 1
0 votes
2 answers
1k views

Why are "start no earlier than" constraints coming during update the schedule

When I am updating the schedule on the current date then some activity showing "Start no earlier than" constraints. I want to know why these constraints are coming. If constraints came means ...
0 votes
1 answer
160 views

Managing tasks per week

I would like to create a weekly deployment schedule for components, which would then be illustrated on a GANT diagram. I would like to create a schedule for the deployment of components by week, which ...
  • 85
0 votes
3 answers
168 views

Variable Duration to Show Increased Speed (MS Project)

In MS Project, is there a way to show the improvement in duration of a repeated task using a variable duration? The project I am working on has multiple tasks that happen over and over again. Over ...

1