Stack Exchange Network

Stack Exchange network consists of 174 Q&A communities including Stack Overflow, the largest, most trusted online community for developers to learn, share their knowledge, and build their careers.

Visit Stack Exchange

Questions tagged [ms-project-2003]

The tag has no usage guidance.

1
vote
1answer
50 views

MS-Project historical timeline

I am using Microsoft Project 2003 for an historic timeline, this means historical dates that go back 1000s of years. I realize using ms-project may be overkill, but it is actually the same as a ...
3
votes
1answer
2k views

How do you calculate the number of days between two tasks in Microsoft Project?

I've created an event planning project that explains all of the relevant tasks before, during, and after a given event in MS Project 2003. I would like to calculate the number of days between a given ...
4
votes
1answer
523 views

How can I suppress task type indicators for “The task has a calendar applied to it.”

In an mpp file the owner has set a certain calendar and therefore that calendar setting is shown for every single task in the Indicators column. Is it possible to exclude some indicators from being ...
2
votes
1answer
257 views

Task with specific predecessor and weekday - Project 2003

I'm having trouble to schedule a task that has two date constraints: It must happen 5 days after a precedessor task; It must happen on Mondays. I tried creating and using an specific calendar, that ...
2
votes
3answers
9k views

Handling resources who do not have 100% availability in MS Project 2003

This is a technical question regarding Microsoft Project 2003. I am trying to schedule resources who have other (management) duties not related to the project. My initial thought was to reduce their ...
5
votes
6answers
34k views

How can I update a MS Project plan to show schedule slippage?

Once I've set up my baseline, I like to use the Tracking view to see schedule slippage (ie: is a project going to be "late"?). The problem occurs when I'm updating the % Complete, but a task that was ...
3
votes
1answer
1k views

Resource Calendars in Microsoft Project 2003

I have developers in Quebec and in Ontario, and each province has different holidays. In MS Project 2003, I selected Tools/Working Time and created two calendars called Ontario and Quebec and filled ...