Questions tagged [ms-project-2007]
This tag is for all questions that involve Microsoft Project version 2007.
18
questions
0
votes
3
answers
175
views
Entering Contract Start and Contract End Date in MS Project
What is the best approach for having contract start and end dates in MS Project?
The issue I am facing is the following: I entered both dates as milestones. all project activities are of course ...
1
vote
1
answer
326
views
Plot CVI and SVI in EVA graphical report
I am using Project 2007 to perform the calculation related to the EVA methodology. Everything works as expected, and when I generate the earned value over time graphical report I have the correct ...
0
votes
1
answer
373
views
Display completion % by custom columns instead of summary tasks?
I have a project structured with the below tasks:
Summary task A: Project Initiation
Sub task A1
Sub task A2
Summary task B: Project Design
Sub task B1 (Workstream 1)
Sub task B2 (Workstream 1)
...
1
vote
1
answer
130
views
MS Project 2007 Start End Date Mismatch
I have kept the correct start and end date but the duration is getting wrongly calculated.
The start date is 11-June-2015 and end date is 16th -Sept -2015 . They are appearing fine in MPP. But the ...
1
vote
1
answer
913
views
Using MS Project 2007 for Manufacturing Build Time
Is there a way for MS Project 2007 to calculate durations based on a give time/part and total number of parts. For example:
A manufacturing process can process 1 part every 30 sec and we want to ...
0
votes
2
answers
895
views
Planned work until date in MS Project 2007
I want to know the Planned work until the status date to compare with the Earned work done to this date.
It is a value calculated in ARTEMIS , but I'm new in MS Project and I don't find it.
Like the ...
1
vote
1
answer
601
views
Working with a pool/group of resources
How can I effectively work with a pool of team member (nor the usual resource pool share file in project)?
Let me rephrase.
My resources are spread into pools/groups, that share the same skills and ...
5
votes
2
answers
734
views
Level Remaining Resource Units
My goal is to optimize resource usage when having priority tasks partially allocated.
MS Project 2007 simple two task scenario (My project has thousands of tasks) with automatic leveling:
======-----...
7
votes
2
answers
2k
views
How to permit multiple Project Managers to update a shared project
I have searched and not found an answer for this (nor did Google help). We are on Project Server 2007. I am running a large program with multiple project managers handling different parts of the ...
2
votes
2
answers
4k
views
How do I auto-level a project mid-duration taking into account % complete on tasks?
I have a MS Project 2007 plan with six months of work in it. I'm updating the % Work Complete on the tasks as we progress through the plan each week and month.
I'm moving the "Project Start" date ...
0
votes
1
answer
739
views
Difference in %complete after rescheduling between MSP 2007 and 2010
I have a file that has a single task. its fixed duration and is not effort driven and no resource is defined. duration is set to 10 days. after 5 days, %complete is 10%. after entering this data and ...
1
vote
2
answers
7k
views
How to calculate variance between baseline 1 start and actual start in MS Project (2007)?
I would like to find out the variance between baseline start 1 and actual start. However, I realised that the start variance value as seen from the Variance table actually shows the difference between ...
1
vote
1
answer
176
views
How can we update nested projects in master project
When we open 1 project from MS Project Server , then we can update it easy and fetch changes and publish again to MSPS.
But when we have many project and programs that embedded them in 1 Master ...
1
vote
2
answers
256
views
How to start off a project plan documentation for research oriented projects?
I have planned all the tasks using MS Project 2007. I used shots of Gantt chart, Network diagram and critical path.
Can the project documentation plan have the following contents?
Project ...
5
votes
2
answers
1k
views
How to manage different detail levels in a project plan to be presented to different audiences?
In any given project, a variety of detail levels are needed:
executive summary
technical summary
delivery team summary
delivery details
How can these different levels of detail be contained and ...
1
vote
1
answer
1k
views
How do I get MS Project to give "Actual Finish" using a new baseline?
I have a schedule baselined in MS Project 2007. We have identified, documented and obtained approval for a change to this schedule. I plan to save the new baseline as "Baseline 1" and keep the ...
3
votes
1
answer
744
views
How to add slippage to a project when using Microsoft Project 2007?
I have a plan with original dates that I would like to keep but then I have a project phase that is now delayed. Are there recommended approaches when using Project 2007? Thanks
8
votes
4
answers
35k
views
how can I highlight overdue tasks in MS Project 2007
I am using MS Project 2007. I want to highlight overdue tasks in red color. Is there any way to do so?