Questions tagged [ms-project-2010]

This tag is for all questions that involve Microsoft Project version 2010.

5 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
3
votes
0answers
133 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
1
vote
0answers
53 views

MS Project 2010 task calendar not working

I've created a task calendar for certain transports that can only occur on Wednesdays, with only Wednesdays marked as working time. But when I apply that calendar to the transport milestone items, MS ...
0
votes
1answer
73 views

Percentage Values In Timeline (MS Project)

in the photo below you will notice four work packages. Each one is 70% done (column % Work Complete). Nevertheless, for the first three activities in the timeline I see 9%, 6% and 31% completion ...
0
votes
2answers
72 views

Entering Contract Start and Contract End Date in MS Project

What is the best approach for having contract start and end dates in MS Project? The issue I am facing is the following: I entered both dates as milestones. all project activities are of course ...
0
votes
0answers
106 views

Adding Multiple Deadlines to One Task

I am a new user to Microsoft Project. My company are currently using Project 2010 so I am having to use this version. I noticed that I can add deadlines to individual tasks, which is really useful for ...