Questions tagged [ms-project-2013]

The tag has no usage guidance.

Filter by
Sorted by
Tagged with
1
vote
1answer
24 views

Assigning MSP resources with future availability to tasks

I have a project with a bunch of tasks of 20 days each and each of those tasks is assigned to 1 of 4 full time resource. There are no scheduling dependencies so I am allowing Project to auto level ...
1
vote
1answer
60 views

How can I show the month for a Enterprise Custom Date Field in the Project Center for Grouping?

I setup a Enterprise Custom Field for a Key Date that leadership wants to group by year and month. I thought I could just make 2 new Enterprise Custom Fields, one to parse out the Month and the other ...
0
votes
0answers
26 views

change working time doest affect existing task in project

Microsoft Project--- In our project calendar we have changed working time from 8 hours to 9 hours all times are correctly set 8 to 12 and 1 to 6 for monday to friday but after changing default end ...
0
votes
1answer
77 views

Percentage Values In Timeline (MS Project)

in the photo below you will notice four work packages. Each one is 70% done (column % Work Complete). Nevertheless, for the first three activities in the timeline I see 9%, 6% and 31% completion ...
0
votes
2answers
74 views

Entering Contract Start and Contract End Date in MS Project

What is the best approach for having contract start and end dates in MS Project? The issue I am facing is the following: I entered both dates as milestones. all project activities are of course ...
1
vote
2answers
64 views

Simultaneous use of resources

I’m trying out Project 2013 to use to run a test lab, so apologies for the noob question. This seems like a basic scenario but what I’ve found on this forum is “Project doesn’t work like that”: I have ...
0
votes
1answer
41 views

MS Project 2013 does not Sync with Sharepoint online

I am using Sharepoint online part of Office 365 and Microsoft Project Professional 2013. When I try Open with Project option from Sharepoint Online , MS Project opens up and asks for username and ...
1
vote
1answer
331 views

Microsoft Project - Using "As late as possible" instead of SF dependencies

Im new to project and im trying to link task 2 to a activity in task 1 so that all of the earlier activities in task 2 then work backwards. I have read that i should be using "as late as possible" ...
0
votes
2answers
241 views

Total cost increases every week,

I am using the MS project,i have noticed that the total cost column of the project increases every time i enter actual work. i am not sure why is that! could it be because some of the ressources are ...
1
vote
2answers
101 views

Macro Planning Road Map

I would like to have your opinion on an issue I am facing in project management. I would like to create a Roadmap 2020 for my team, a kind of macro planning. A concrete example, I have a list of ...
2
votes
1answer
84 views

Work resources that don't influence the duration of the task

I work on a construction project. I have a task that needs 1000h to be completed. Depending on the amount of manpower, the duration of the task will vary. To complete the task I need scaffolding that ...
1
vote
1answer
109 views

Microsoft Project 2013 - Auto leveling according to Resource Availability

I am building a project plan on Microsoft Project 2013 and can't understand why it is not allocating a resource. I have a task set as auto scheduled, fixed work, with a 7 day effort assigned to a ...
2
votes
1answer
110 views

How to add dynamic date footer to project print-out?

I see other people printing our project's Gantt chart with an up-to-the-date date on the bottom. How do they to do that? Is it automatic or must one do something every time one prints the chart?
1
vote
2answers
1k views

Work days and Duration does not match

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days ...
1
vote
1answer
91 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
0
votes
1answer
95 views

MS Project burndown for outline level

I'm working on creating a burndown graph for a large project that I'm trying to schedule, but I don't want the sub-tasks to be counted as a remaining actual task for the burndowns. Is there a method ...
1
vote
1answer
90 views

MSProject show main resource on Summary tasks

How can I show the main (resource with maximum hours) for Summary tasks. I suspect I would need to set a custom text field to show this, but how would I structure this? thanks
-1
votes
2answers
105 views

Task Approval before Publishing

I have received a requirement to customize our Project Server 2013 implementation as follows: Several project managers can add tasks to the same project plan A centralized focal point is responsible ...
0
votes
1answer
226 views

MS Project 2013: Can I avoid MSP auto-changing my assignment units to less than 100%?

Curious if there is a way to avoid Microsoft Project auto-adjusting the assignment units, when I add a resource in the Resource name column. In the project settings all resources are set to 100% ...
1
vote
1answer
1k views

Why are tasks split while updating plan?

I inserted the actual start for updating a task and then inserted the %comp and reschedule and resource leveling for the plan with ms project 2013. The problem is that the task has been split in ...
2
votes
1answer
86 views

How to Specify how Text Colours Should Override Each Other in MS Project

This is a little embarrassing, but I cannot figure out how to do this. I have added Text Style formatting, but I need to change the priority of the formatting. I have Critical Path tasks formatted ...
0
votes
2answers
369 views

Start and stop in MS Project

I have a lot of situations where there is a small project that is, let's say, 50 percent done. Then it's completely put on hold, and restarted a month later. How is it best to accurately reference ...
1
vote
1answer
52 views

MS Project Column Time different from Project Time

In MS Project 2013 I am attempting to get a particular column to show time unit in Days but leave the default Project Time Unit as minutes for all of the other columns. I can set the Project default ...
-1
votes
1answer
309 views

Add a PWA Enterprise Custom Field to Project Pro

I've added an Enterprise Custom Field to tasks in Project Web Access (under Sharepoint 2013) but when I open an existing project published on PWA in Project Pro 2013 I don't see the new field. It ...
2
votes
1answer
422 views

Looking for a way to remove an errant calendar from MS Project Professional 2013

I have a project file with a project calendar that shows up in the Change Working Time dialog box's For Calendar dropbox that is not being using in the project file. I've looked in the Calendar tab in ...
0
votes
1answer
28 views

MS Project 2013 cost adjustment

I would like to know what is the best way to handle cost adjustment to the baseline in MS project. Do you save the baseline when you adjust the cost when you get new estimate or not?
0
votes
1answer
331 views

Why does my Earned Value curve go back to zero

I managed to simulate a project in MS Project 2013. I created an initial planning, assigned ressources and put this in a baseline. Then I imagined two status for my project in two different dates. ...
1
vote
1answer
28 views

Un-wordwrapping columns in MS Project 2013

There doesn't seem to be an easy way to "un-wordwrap" columns in MS Project 2013. According to the docs, if I toggle wordwrap off and then manually adjust each row, wordwrap will snap off. I was ...
0
votes
2answers
124 views

Must every task in MS project be linked with each other?

The project is composed of three groups of teams, each team will contribute to the project plan. The team has listed their tasks, my question is whether all tasks should have a predecessor and/or ...
1
vote
1answer
993 views

MS Project autoschedule - full days of work are bleeding into next day

I'm scheduling weeks of work in Microsoft Project (2013) wherein each task will normally take a full day of work/duration for a crew. I'm scheduling them for 10-hour days and the duration of the work ...
1
vote
1answer
802 views

Can't find the Task Name column in MS Project 2013

When I create a new project in MS Project 2013, there is no option to add the Task Name column. I've tried clicking on Add New Column but Task Name doesn't appear there: The following (from a ...
0
votes
1answer
181 views

Scheduling hours over a fixed duration in MS-Project 2013

I am new to Project and, rather than spending anymore time reading the web, I thought I'd appeal to some experts. In our company we often schedule tasks similar to the made-up one just below. We are ...
3
votes
2answers
3k views

How can I display buffers in MS Project?

I work on a subproject, the timelines of most work packages we are managing are non critical. In most cases, we have a scenario like this: Team A needs to work 10 days, but can do this anytime during ...
0
votes
2answers
6k views

Show resources grouped by high-level summary task in MS Project

I'm managing a project in MS Project Pro 2013 with several phases, which I have distinguished by summary tasks. Under these summary tasks I have plenty of other tasks, several again summarized. Note ...
0
votes
2answers
180 views

How to edit groups of tasks in Microsoft project?

I want to change hundreds of tasks in a project from "fixed work" to "fix duration" type. When I select multiple tasks - the "Information" dialog changes only one if them. I have also tried to add a ...
1
vote
1answer
461 views

MS Project 2013 - SubProject Finish Date not Calculating Correctly

I have a Master Project with a subproject. Inside the subproject there are two tasks. If opened alone and calculated (F9) the subproject finish date will roll up correctly. If the Master Project is ...
0
votes
1answer
119 views

MS project 2013 - complex resource allocation

I have used MSP before but not for years. I have some long term tasks and I would like to allocate varying quantities of resource requirement (against single resources) each month on these tasks - ...
1
vote
2answers
1k views

How to get MSProject to automatically increase resource usage to over 100% when the average Acutal Work hours is above the standard day work hour?

Let's assume that the standard number of hours worked per day is 8h I have a task with a Duration of 2 days and 16 Work hours The resource RA is assigned 100% to this task. this task mode is set to ...
0
votes
1answer
79 views

Filter with wrong total actual work

I have a problem with filtering in Microsoft Project 2013. When I create a filter based on some criteria, the results doesn't show correct total work and actual work. In fact, it sums actual work of ...
0
votes
1answer
2k views

MS Project: Finish Variance formula simplification

I've set a formula to monitor variance between baseline and scheduled finish. I know that there is a simple finish variance column for this kind of thing, but in my organization we've got certain ...
-3
votes
3answers
303 views

Earned value analysis by client and vendor

We all know that some project managers (those that follow PMBOK/PMP) do earned value analysis to know SPI and CPI. Schedule Performance Index (SPI) = Earned Value ÷ Planned Value -- How are we doing ...
0
votes
1answer
590 views

Difference between max units and assignment units in MS Project

I know difference between assignment units and Peak units , but can any one explain how max units and assignment units are related to each other ?
1
vote
3answers
141 views

MS Project: Few basis questions on tasks management

I have seen different managers entering preferred Duration in days and some in hours. Is there any best practice? I have seen many manager will update "% complete" to update a task progress. Is this ...
1
vote
1answer
8k views

Changing default time from 0.88 days to 1 day

In Microsoft Project 2013, when I enter a start day of 16/6/2016 and end date of 16/6/2016, the default duration is 0.88 days. When I go into change working time it shows 8 hours per day. Problem is, ...
-1
votes
1answer
87 views

How can I view the tasks which are assigned to my organizational team members?

I am a team lead and we are using Microsoft Project Server 2013. My team members have many tasks assigned across different projects. How can I view the tasked assigned to my team members within ...
0
votes
1answer
461 views

Working (part of) an MS Project schedule backwards

I'm trying to make a portion of my MS Project schedule work backwards, and it's not working quite right. I'm hoping you can help. I have a schedule where Task 45 ends on 2/1/17. Tasks 46 through 50 ...
1
vote
2answers
3k views

Relationship between Work, Duration and Units in Microsoft Project 2013

I am struggling with Work/Duration/Units. Example: I have a product that takes 184 hrs to build, we typically have 5-6 guys working on it and in real time, takes about a week to complete. When I ...
0
votes
1answer
8k views

How to show how late a task is in MS-Project 2013?

When a task is late in the status how can we set it up to show how many days it's late not just late? I want to see on each task how many days it's late.
1
vote
2answers
2k views

Drop-down menus in MS Project 2013 disappeared

In one of my MS Project 2013 files, the drop down menus appear when I hover over the column headers in the Task Sheet view. In another file and new files, the drop down menu option does not appear in ...
0
votes
1answer
41 views

Is there a way to links tasks that have overlapped dates?

for example, if I have two tasks start at different dates that end at the same date. My problem is, if I try to link these two tasks, the dates will automatically change, not the original dates I ...