Questions tagged [ms-project-2013]

The tag has no usage guidance.

10 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
1
vote
1answer
51 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
1
vote
0answers
207 views

Resource time not allocating correctly in Project 2013

I'm planning a project where I want my resources to dedicate one day week each to project work. I've created a calendar for each resource which blocks out their day, so there are Tuesday only, ...
1
vote
2answers
469 views

Work days and Duration does not match

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days ...
0
votes
0answers
22 views

MS Project - How do I calculate / report work by resource group between two dates

I have a request to provide my company an estimate of the number of work hours / days expected by the business to be involved a project so that they can perform their hiring forecasts for the year. I'...
0
votes
1answer
100 views

Total cost increases every week,

I am using the MS project,i have noticed that the total cost column of the project increases every time i enter actual work. i am not sure why is that! could it be because some of the ressources are ...
0
votes
0answers
24 views

Values such as (EV) and (PV) does not show in some tasks

I have been working on a project for a while now, i've always faced the issue that the MSP project does not show me all the values like the planned value (BCWP), BCWS... ( in some task it is shown) ...
0
votes
0answers
209 views

How to draw stacked column chart with custom text fields?

I am working on a report on MS Project 2013. In this report there is chart. The chart is based : NumberOftasks (Y-axis) which is a custom field of type number. Localization (X-axis) which is done by ...
-1
votes
1answer
276 views

Add a PWA Enterprise Custom Field to Project Pro

I've added an Enterprise Custom Field to tasks in Project Web Access (under Sharepoint 2013) but when I open an existing project published on PWA in Project Pro 2013 I don't see the new field. It ...
-1
votes
1answer
86 views

How can I view the tasks which are assigned to my organizational team members?

I am a team lead and we are using Microsoft Project Server 2013. My team members have many tasks assigned across different projects. How can I view the tasked assigned to my team members within ...
-2
votes
1answer
2k views

what is the reason of calculating duration in Microsoft Project in decimal form?

when I enter the start times and end times of tasks, software calculates duration of task in decimal form. I have checked calender setting and I think it is correct but I can't solve this problem. I ...