Questions tagged [ms-project-2013]

The tag has no usage guidance.

13 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
1
vote
1answer
55 views

How can I show the month for a Enterprise Custom Date Field in the Project Center for Grouping?

I setup a Enterprise Custom Field for a Key Date that leadership wants to group by year and month. I thought I could just make 2 new Enterprise Custom Fields, one to parse out the Month and the other ...
1
vote
1answer
89 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
1
vote
0answers
214 views

Resource time not allocating correctly in Project 2013

I'm planning a project where I want my resources to dedicate one day week each to project work. I've created a calendar for each resource which blocks out their day, so there are Tuesday only, ...
1
vote
2answers
1k views

Work days and Duration does not match

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days ...
0
votes
0answers
26 views

change working time doest affect existing task in project

Microsoft Project--- In our project calendar we have changed working time from 8 hours to 9 hours all times are correctly set 8 to 12 and 1 to 6 for monday to friday but after changing default end ...
0
votes
1answer
73 views

Percentage Values In Timeline (MS Project)

in the photo below you will notice four work packages. Each one is 70% done (column % Work Complete). Nevertheless, for the first three activities in the timeline I see 9%, 6% and 31% completion ...
0
votes
2answers
72 views

Entering Contract Start and Contract End Date in MS Project

What is the best approach for having contract start and end dates in MS Project? The issue I am facing is the following: I entered both dates as milestones. all project activities are of course ...
0
votes
1answer
35 views

MS Project 2013 does not Sync with Sharepoint online

I am using Sharepoint online part of Office 365 and Microsoft Project Professional 2013. When I try Open with Project option from Sharepoint Online , MS Project opens up and asks for username and ...
0
votes
2answers
228 views

Total cost increases every week,

I am using the MS project,i have noticed that the total cost column of the project increases every time i enter actual work. i am not sure why is that! could it be because some of the ressources are ...
0
votes
0answers
231 views

How to draw stacked column chart with custom text fields?

I am working on a report on MS Project 2013. In this report there is chart. The chart is based : NumberOftasks (Y-axis) which is a custom field of type number. Localization (X-axis) which is done by ...
-1
votes
1answer
304 views

Add a PWA Enterprise Custom Field to Project Pro

I've added an Enterprise Custom Field to tasks in Project Web Access (under Sharepoint 2013) but when I open an existing project published on PWA in Project Pro 2013 I don't see the new field. It ...
-1
votes
1answer
87 views

How can I view the tasks which are assigned to my organizational team members?

I am a team lead and we are using Microsoft Project Server 2013. My team members have many tasks assigned across different projects. How can I view the tasked assigned to my team members within ...
-2
votes
1answer
2k views

what is the reason of calculating duration in Microsoft Project in decimal form?

when I enter the start times and end times of tasks, software calculates duration of task in decimal form. I have checked calender setting and I think it is correct but I can't solve this problem. I ...