Questions tagged [ms-project-2016]

The tag has no usage guidance.

0
votes
0answers
9 views

Level Resource (all resources) vs Level All - gives different results, why?

This is driving me crazy! In my 1250 line plan (MS Project 2016) with 7 resource types, I find that the results of leveling are different depending on whether I do it via "Level Resource" (with all ...
0
votes
1answer
16 views

Autosave: How to prevent it being re-enabled with each new session

I find the Autosave feature to be very intrusive and it also interferes with some macros I run. I know how to disable it via File/Options/Save/untick the box, but even if I then immediately save my ...
0
votes
2answers
29 views

Sharing a file without them being able to edit the main file

I need to either create or share my project with others. I don't want them to be able to make changes to my project though. I've tried creating a new one, but they still are able to make changes to ...
1
vote
1answer
28 views

Leveling; getting unexpected results

I have spent hours reading up on the leveling algorithm and trying various alternative approaches but I have a problem I simply can't figure out. I'm using MSP 2016. My schedule consists of around ...
-1
votes
1answer
17 views

MS Project 2016 updating Actual Cost figures for Cost Resources that are set to accrue at the end of the task

I am having an issue where MS Project 2016 is prorating the actual cost figures for cost resources that have been set to accrue at the end of the tasks. I have tried everything I can think about and ...
1
vote
1answer
25 views

Printing specific date range in ms project 2016

I am trying to print a specific date range from a gantt chart view in ms project 2016, but all that prints out is the whole project. Can you help?
-1
votes
1answer
32 views

MS Project - Multi-year Inflation

I am managing a 3 year project in a country where the average annual inflation rate is 12%. Instead of going through every item and entering "+12%" into the cost rate table for each item, is there a ...
1
vote
1answer
25 views

How to Import Resource Availability from Excel when it varies by month

I have a number of generic resources, eg Engineers, where each individual is treated as interchangeable with all the other Engineers. I want to show their availability as for instance 100% in October ...
1
vote
2answers
56 views

Auto populate project level Priority field based on lookup to Excel file table

I have multiple small plans (managed by PMs) embedded in a master plan file which I manage. The PMs can add tasks to the sub plans as necessary. After receiving each sub plan and refreshing the ...
1
vote
0answers
24 views

MS-Project 2016: Sort does not work

With MS-Project 2016 (version up-to-date) I have created a custom report (showing filtered tasks). I want to sort it ascending by Finish date (soonest finish on the top). But it does not work. It ...
-1
votes
1answer
22 views

MS Project, add hours directly in resource usage

at my work we use MS Project 2010 to run our Monday morning scheduling meeting, from Resource Usage view. In the version I inherited on my work computer, I can change the number of hours or add a new ...
0
votes
0answers
21 views

How can you represent a task which only takes place at specific days on MS Project?

I want to represent a task which only takes place at specific days on MS Project: for example, on 01/01/2018 between 9:00 and 11:00, on 03/03/2018 between 10:00 and 12:00 and on 12/03/2018 between 11:...
0
votes
2answers
372 views

How to show slippage in MS Project 2016?

Probably a noddy question, but need to ask. I'd like to be able to demonstrate real time slippage on my plan, for remodeling impact purposes. I have both original baseline dates and current dates ...
0
votes
1answer
43 views

How to calculate the completion percentage relation by start and finish dates

I need to calculate the current date in relation to the start and end dates of a task and would expect to see a field that shows the completion percentage. Something like this Question or this ...
0
votes
0answers
19 views

Recommendation for MS Project courses

I'm looking for some recommendations on courses for building and managing a Microsoft Project Schedule. I've looked over this SE question for reference material and books. If anyone knows any good ...
0
votes
1answer
64 views

How to work with estimated end dates in MS Project?

I am new to MS Project and already asked a question here that revealed my incomplete knowledge of the scheduling process. After reading some articles and watching videos like this one, I think of ...
0
votes
1answer
131 views

Task update approvals on a PWA Timesheet automatically changes MS Project duration on task and overall finish date for Project

A resource is assigned to an automatically scheduled task with start date: 2/12 and finish date:2/22. The baselined, saved and published project is scheduled to finish 2/23. The resource does not ...
0
votes
0answers
31 views

MS Project 2016 - Work hours do not add up

A section in my project has 12 sub tasks, each at 178 hours. So why does the total show 2135.92 and not 2136 hours? Other sections do add up. Working in MS Project 2016 (16.0.4549.1000) on a 32 ...
-2
votes
3answers
211 views

Does Microsoft TFS have all I need for Agile Project Management?

If I want to use Agile, and use a Scrum implementation, will TFS do all I need? Or do I need something else? I have MS Project 2016 (not using Project Server), and it has an Agile template, but most ...
0
votes
0answers
15 views

How to change a Resources working hours from a specific date onward?

I have a resource who currently has custom working hours. The resources hours will be changing in a couple of months time and I would like to see how this is going to affect the project without ...
-1
votes
1answer
171 views

How to pause task to complete another task

I currently have 2 identical projects beginning at different times (will be adding more). The manager has a number of "Review" tasks spread out in the project as well as some of his own work. The ...
-1
votes
2answers
80 views

Scheduling: Remaining Work

Let's say I have a task that I've know is going to take 12 hours to do. But when I schedule resources, I only scheduled 6 hours of resources. How could I show that the resources are under scheduled. ...
0
votes
1answer
283 views

How to assign a resource with two units to the task?

I want to assign a resource -Excavator- to a task -Task#1 : duration = 4 month- : 2 units in first 2 months and 5 units in second 2 months.
0
votes
1answer
70 views

Gantt Chart Style Change for 2016

I have just changed over to MS Project 2016 Pro from 2010 and have noticed that the Gantt Style is different. The better aesthetic look of the rounded bars and shading in 2010 has gone in 2016. Does ...
0
votes
1answer
128 views

Project 2016 update task start dates - am I asking too much?

new to the site and to Project so please bear with me. I'm tinkering with Project and have set up a simple schedule, 4 auto schedule tasks, all effort driven and linked FS. Task 2 has a duration of 2 ...
0
votes
1answer
178 views

Microsoft Project 2016 resource calendar seems to be ignored and no overallocation detected

yesterday I was trying to put in my resource sheet a part-time worker. I changed his calendar appropriately and then assigned him. At that point something strange happened. I summarized everything ...
0
votes
1answer
74 views

MS Project Update Project and Level All

I have a bunch of tasks set up to get done by a dozen teams. The teams are in as resources that have varying sizes. 200%, 400%, 600% whatever.. When I report the tasks, some have been started and ...
0
votes
0answers
41 views

Resource representing a group in MS Project

I want to make a very high level gantt with MS Project. Let's say I have an estimate of effort in days. Let's say I have a team of 15 people that have approximately the same amount of statutory ...
2
votes
1answer
143 views

How to set a specific resource in MS Project to have a max work capacity of 7 hours a day?

I'm working on this slightly complicated project schedule in MS Project 2016. I'm not new to MS Project and have used it for several years, but not necessarily an expert either. For my project, I need ...
2
votes
2answers
508 views

Overrun on Duration

I'm working on a school project and we are having trouble updating our MS Project 2016 file. For a little background: The tasks all have fixed duration and some have dependencies on others being ...
1
vote
1answer
639 views

Project Server 2016 doesn't send task assignment alerts to resources

I have SharePoint Server 2016 and Project Server 2016. I turned on notification sending in Central Administration and for each resources, but resources don't receive any alerts/notifications after ...
1
vote
1answer
106 views

MS Project doesn't calculate task finish date correclty

I have an issue with MS Project 2016. I have a task which starts on May 9th and is estimated to 72 hrs. I have assigned a resource, which is available 4 hours per day (I assigned the resource using ...
1
vote
4answers
383 views

MS Project Calendar

I'm new MS Project user; I'm trying to sync my Ms Project 2016 calendar with Outlook 2013, I want tasks due dates give notification in Outlook. How can I do that?
3
votes
1answer
601 views

Sending Email Notification when Assigning Task to Resources in Project Server 2016 Web App

I use Project server 2016 and I created a Project web app site. I created an enterprise project and entered the team data. Now I am able to assign tasks to resources. What I want is for the team ...
0
votes
1answer
322 views

How to manage “pools of resources” in Microsoft Project 2016?

I need to create multiple pools of resources (each containing interchangeable resources within). To clarify I need a pool of front-end developers, another of back-end developers, and a pool of testers....
0
votes
1answer
63 views

MS Projects show task always in timesheet

I am currently using Microsoft projects 2016 with time sheets. How can i create a task which is always shown in my time sheet with 0 planned work time? I have administrative tasks beside my project ...
0
votes
1answer
52 views

Task Duration and work

I am trying to carry out following and having difficulty but I cannot figure out why, I am not expert at MS Project. I have one "100% completed" task with duration 35days No Resources have been ...
0
votes
2answers
177 views

In Microsoft Project, the values for my Work column appear to be wrong

I'm just getting started with Microsoft Project and I'm using it to plan out a project we have. There are several tasks on it where I would like the whole team (5 people) to work on a Task. My ...
0
votes
1answer
582 views

How to do resource allocation between overlapping tasks in MS Project?

I am building a capacity planning model in Project 2016. My goal is to illustrate that in real life no one does a single task 100% of the time. I want to show that 10% of the resources' time is ...
0
votes
0answers
24 views

Show days to end when text in column is No or W.I.P

When a column with a dropbox shows the value "No" or "W.I.P" (work in progress) the Days to End must be shown in another column. What I need is when there is a "Yes" in the Work Ready column the text "...
0
votes
3answers
5k views

Why is MS Project 2016 Showing a $0 for BCWP on a completed task

I am not understanding how MS Project (2016, in this case) calculates the BCWP component of Earned Value. To illustrate: below is a one-task project. The task is five days long, has one resource ...
1
vote
2answers
7k views

How to configure the project schedule for parallel tasks?

I have a resource with 50% availability for a project. I have set the Units in MS Project for 50% for him. He has a number of tasks assigned to him that can be done in parallel. How do I configure ...
0
votes
2answers
778 views

MS Project 2016 is returning too many hours in summary tasks for Work

I am using MS Project 2016. Summary calculations for duration are all correct, but SOME of the summary calculations for Work are double or quadruple what they should be, as if it's including subtotals ...
-1
votes
1answer
599 views

How can I set up a supervisor to multiple workers in multiple tasks in MS Project

I have 4 tasks, and I have assigned 2 workers to each task. As these tasks will be done at the same time, and are correlated, I want to assign a supervisor to these 8 workers. So, basically this ...
1
vote
2answers
134 views

lag must be exactly 2weeks

I have a number of tasks which have 3 subtasks each that MUST start and be completed exactly 2 weeks from each other. (each subtask is half day) i.e. task1: (subtask1 @ day1, subtask2 @ day14, ...