Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

Filter by
Sorted by
Tagged with
1
vote
1answer
163 views

How to link BCWP to a customized column I created for physical percent complete

As physical % complete does not roll-up summary tasks, I created a column called 'physical percent complete'. I think I need to link this column to Budgeted Cost of Work Performed (BCWP), just so I ...
1
vote
2answers
547 views

Work days and Duration does not match

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days ...
0
votes
2answers
44 views

Actual Duration Calculated by MS Project vs Actual Duration of the Project as of the Status Date

My project started in Jan 2020 and as of Jun 2020, we have spent a total of 80 working days ( minus weekends and public holiday). However, the actual duration given by the MS Project is over 90 ...
0
votes
2answers
805 views

How to show resource usage for the current project only?

In MS Project, is there a way to show resource usage for the current Project only? When viewing the resource usage report, the totals by resource include allocation for all projects. Can it be ...
1
vote
2answers
10k views

How to configure the project schedule for parallel tasks?

I have a resource with 50% availability for a project. I have set the Units in MS Project for 50% for him. He has a number of tasks assigned to him that can be done in parallel. How do I configure ...
4
votes
2answers
6k views

How can two tasks begin on the same day without a resource-conflict?

In MS Project (current version), I have the following task setup and can't find a solution: Short translation for columns: Vorgangsname = Taskname Arbeit = Work Dauer = Duration Anfang = Beginning ...
1
vote
1answer
48 views

Working time not calculating correctly in tasks

I am using MS Project 2016. I am working on a large project working 10 hour days 6 days per week. I have adjusted working times and days and set Sunday to a non working day. But the finish dates ...
0
votes
1answer
21 views

Showing successor task names in MS Project

I'm new to MS Project. I have a view where I want to get a list of successors for a list of tasks. I've added the Successors column and that gives me the list I want, but it's their unique IDs. Is ...
0
votes
1answer
22 views

How to create a resource usage calendar across multiple Project Online projects

The division I work in has 3 PMs that share resources. We have a three fold need we're trying to engineer a solution for within the Microsoft Office ecosystem. We need to create a resource allocation ...
1
vote
1answer
33 views

Forward and Backward Pass Activity on Node Diagrams in MS Project 2010

I want to make Forward and Backward Slack Activity on Node Diagrams in MS Project 2010. I display the Network Diagram view and choose Format > Box Styles. I Click the More Templates button and in ...
0
votes
1answer
14 views

Is there a way to preview User's time sheet in Project Web App?

There was an option for an admin to preview the time sheet for a user in Project Web App (PWA). Admins can navigate to time sheets and preview only own time sheets. Is there a way to somehow preview a ...
3
votes
0answers
116 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
0
votes
0answers
38 views

How can I show tasks only where the predecessor is complete for task owners in Project online

Currently task owners can see all tasks, but I only want these visible where the predecessors are 100% complete. Is there a way of doing this in MS Project online?
0
votes
1answer
29 views

Display in the Details View --> Task Form: Sorting Predecessors by Task ID, not alphabetically

I'm using MS Project 2013 Professional In the Details View using Task Form, displaying Predecessor view, it is sorting alphabetically by Task Name when I would rather see it sorted by Task ID. I do ...
3
votes
1answer
89 views

Change task distribution with % completed

I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration. e.g. Mon 2h | Tue ...
0
votes
0answers
13 views

Split task delay report

I have a baseline schedule, for few task delay to be inserted as split in tasks due to bad weather. Now I need to know, how to create a report for split tasks, delayed with reason to be displayed for ...
1
vote
3answers
1k views

Microsoft Project - view resources in hours not percentage

I had assigned resources to tasks in Microsoft Project gantt chart and I would like to see them in hours per resource, not percentages. I know that I can see hours in Resource Usage chart, but maybe ...
0
votes
1answer
59 views

Fix task time of day (Trip planning with MS Project)

I'd like to be able to fix the time of day that a given task must start at and its duration without specifying the actual start date. In this scenario, the date would depend on the end time & date ...
4
votes
1answer
98 views

Determine to which task a resource is allocated on a particular day

Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
0
votes
1answer
76 views

MS Project Configuration - 80% allocation to project, max of 50% per task per day

I'm a newbie to MS Project here, so I was wondering if someone could point me in the right direction, or tell me if I'm barking up the wrong tree. Is there a way to constrain a resource in MS Project ...
0
votes
1answer
56 views

In MS Project :the resource calendar did not show up in the gantt chart but it shows at the resource usage sheet

the resource calendar did not show up in the gantt chart but it shows at the resource usage sheet: i mean that, i assigned the Friday and Saturday as days off in some resources (i am using the ...
1
vote
0answers
27 views

How to cross project plan for enterprise resources, with leveling support in Microsoft Project Server

I'm using Microsoft Project Server on Sharepoint to manage project throughout the organization. I have some enterprise (work) resources, that are simultaneously active on multiple projects. The ...
2
votes
1answer
469 views

Microsoft Project - how to calculate start dates based on a set time from the finish date?

I have multiple tasks that have different durations that I want to start at different times from a go live date, i.e. finish date for an entire project. For example: Project must finish on 01 Dec ...
1
vote
0answers
13 views

MS Project. Need a field that flags what tasks have only completed predecessors that I can bring through to MS Project online

I'm using MS Project which is connected to a PWA. All users complete their tasks on the online 'Tasks' page. For the task owners, I need a flag that tells them that all the predecessors for their task ...
0
votes
1answer
2k views

MS Project predecessor formula

I am going to build a project with several tasks and subtasks that have the same structure. For example: SECTION A task 1 task 2 task 3 SECTION B task 1 task 2 task 3 ....... What I would like to do ...
0
votes
1answer
619 views

how to distribute the work of an activity between specific number of individuals of a kind from a work resource

I have added a work resource entry "Laborers" with Max. Units 10000% in the Resource Sheet. The resource calendar for this resource is standard and all the units are available. Now I want the work of ...
0
votes
1answer
979 views

How to assign a resource with two units to the task?

I want to assign a resource -Excavator- to a task -Task#1 : duration = 4 month- : 2 units in first 2 months and 5 units in second 2 months.
0
votes
1answer
3k views

Is it possible to show the percentage of completed task in the Timeline in MS Project?

I am using Microsoft Project 2013. I would like to visualize in the Timeline the percentage of completed task, for example 33%... Is this possible ?
0
votes
1answer
536 views

Task update approvals on a PWA Timesheet automatically changes MS Project duration on task and overall finish date for Project

A resource is assigned to an automatically scheduled task with start date: 2/12 and finish date:2/22. The baselined, saved and published project is scheduled to finish 2/23. The resource does not ...
11
votes
10answers
19k views

Showing Microsoft Project files to people without Project

The project managers at my company were asked to use Microsoft Project 2013 to track our projects, but many of the business stakeholders do not have Project installed. It looks like I cannot just ...
3
votes
0answers
41 views

Hiding a specific time period in Microsoft Project

Question Good morning, Is it possible on MS Project Pro 2019 to hide a period of time between two dates? Background Our construction projects are divided into 3 stages: (1) pre-construction, (2) ...
0
votes
1answer
125 views

Total cost increases every week,

I am using the MS project,i have noticed that the total cost column of the project increases every time i enter actual work. i am not sure why is that! could it be because some of the ressources are ...
1
vote
0answers
23 views

MS Project, Resource Availability, Task Usage work hours

I've been using other tools for awhile and have to jump back into MS Project. I started a high level plan with tasks and resources, however, I'm having trouble remembering the specifics around Task ...
0
votes
1answer
460 views

MS Project 2016 updating Actual Cost figures for Cost Resources that are set to accrue at the end of the task

I am having an issue where MS Project 2016 is prorating the actual cost figures for cost resources that have been set to accrue at the end of the tasks. I have tried everything I can think about and ...
1
vote
1answer
51 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
1
vote
2answers
87 views

Macro Planning Road Map

I would like to have your opinion on an issue I am facing in project management. I would like to create a Roadmap 2020 for my team, a kind of macro planning. A concrete example, I have a list of ...
1
vote
1answer
26 views

Can I link or have formulas between task times?

Is it possible to use a formula to get information from "TASK A" as an input "work" in task B? Example: Task A is fixed duration of 2 weeks. I have assigned some resources and the total work they do ...
1
vote
0answers
11 views

Enterprise custom fields are not rolling up in project center view

I am trying to sum project values by their project types. I created a project view then added some calculated enterprise custom fileds and ms project calculated fields like actual work and baseline ...
1
vote
1answer
47 views

How to assign 1 resource to a fixed work task where the resource has 50% availability for the first 2 days and then 100% availability after that?

I have a project that I am trying to schedule and am having a little difficulty. I am a MS project novice and will try to explain the problem in a simple example. I have 1 task which is fixed work. ...
0
votes
1answer
128 views

Ms project - assign different resources with different schedules to a task

I'm new at ms project and I have some questions. Let's suppose that I have a human resource named "T1" that works from 2 pm to 11 pm, and that we have a machine named "m1" that can be working all day....
0
votes
2answers
174 views

How to get Project to _not_ auto-update

I have been tasked to use Microsoft project in a group assignment to help manage it, but I'm having trouble getting the durations and dates to not auto update. I basically would like to have the ...
1
vote
1answer
941 views

PWA / Enterprise custom columns - formula not working

I'm using Project Online and am trying to create a custom calculated column which shows me the percentage difference between my "Actual Cost" and a custom column called "Profitability". I'm having ...
0
votes
0answers
74 views

Macro Planning View Team Capacity / Workload view

My need would be to have a team view macro planning in relation to the workload of each subject. Microsoft project works by resource and not by team. How can I model this global capacity per 3-...
0
votes
1answer
195 views

MS Project - how to set a task to finish before else start after a set period

I'm trying to set a task to either be wholly complete by 1st Dec, if not then start after 1st Jan (i.e. don't start at all if it can't be completed by 1st Dec). I don't want to split the task. Is ...
0
votes
2answers
19k views

Push all dates back by 7 days in a project (project 2013)

I am doing a project for college and I am being forced to use project 2013... I have got a very basic understanding, but I need to push all dates from a certain point back by 7 days, I was wondering ...
1
vote
1answer
65 views

Microsoft Project - Using “As late as possible” instead of SF dependencies

Im new to project and im trying to link task 2 to a activity in task 1 so that all of the earlier activities in task 2 then work backwards. I have read that i should be using "as late as possible" ...
0
votes
2answers
3k views

Print a MS Project Gantt chart for each resource

I wonder if there is a function in MS Project to print the Gantt chart view for each resource, i.e., when issuing the schedule to everyone I print to PDF: Complete Schedule Summaries only Each ...
1
vote
1answer
36 views

Master Project in MSProj10 moves the dates in the subprojects

When I add in the subprojects to the Master Project, the date ranges are unaffected UNTIL I expand the subproject - at which point - the dates all shift to the right. Can I prevent this?
1
vote
0answers
14 views

How to display individual resources with rolled up summary tasks?

I’m trying to see if there’s a view that can display each individual’s assigned task, with rolled-up summary tasks. Right now I have my project set up with summary tasks (milestones) and sub-tasks ...
0
votes
1answer
1k views

Tracking Gantt Chart Not Showing All Tasks

I am trying to do an earned value analysis and there are tasks in my normal Gantt chart that when I switch the view to tracking gantt are not visible. Could this have to do with where I set my status ...

1
2 3 4 5
12