Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

3
votes
1answer
61 views

How to divide a generic resource?

I am still new at using ms project Professional. My project has already assigned resources. For instance, let's take developers who together have a maximum effort of 200%, which means I have 2 ...
3
votes
1answer
49 views

MS Project - Link multiple columns to the Resource Sheet

I have (somehow) managed to create one column which successfully links to the Resource Sheet. When using the drop down, it brings up all of the names in the resource sheet, and allows you to choose ...
3
votes
1answer
2k views

How do you calculate the number of days between two tasks in Microsoft Project?

I've created an event planning project that explains all of the relevant tasks before, during, and after a given event in MS Project 2003. I would like to calculate the number of days between a given ...
2
votes
1answer
127 views

Looking for a way to remove an errant calendar from MS Project Professional 2013

I have a project file with a project calendar that shows up in the Change Working Time dialog box's For Calendar dropbox that is not being using in the project file. I've looked in the Calendar tab in ...
2
votes
1answer
3k views

Is there a way to use your customized fields in reports created in MS project 2013?

I have some customized fields that I've created. I really need to find a way to use them while I'm creating customized reports in MS project, but I just see the built-in fields when I want to create ...
1
vote
1answer
13 views

How do I Create Custom Drop down that allows multiple selections (like resource selection works)

I have a project that has multiple workstreams. In much the same way a single task may require multiple people to work on it, it also may touch multiple workstreams. I created a custom column ...
1
vote
1answer
187 views

Work days and Duration does not match

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days ...
1
vote
1answer
31 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
1
vote
1answer
57 views

MS-Project historical timeline

I am using Microsoft Project 2003 for an historic timeline, this means historical dates that go back 1000s of years. I realize using ms-project may be overkill, but it is actually the same as a ...
1
vote
1answer
25 views

Master Project in MSProj10 moves the dates in the subprojects

When I add in the subprojects to the Master Project, the date ranges are unaffected UNTIL I expand the subproject - at which point - the dates all shift to the right. Can I prevent this?
1
vote
1answer
778 views

PWA / Enterprise custom columns - formula not working

I'm using Project Online and am trying to create a custom calculated column which shows me the percentage difference between my "Actual Cost" and a custom column called "Profitability". I'm having ...
0
votes
1answer
11 views

Display in the Details View --> Task Form: Sorting Predecessors by Task ID, not alphabetically

I'm using MS Project 2013 Professional In the Details View using Task Form, displaying Predecessor view, it is sorting alphabetically by Task Name when I would rather see it sorted by Task ID. I do ...
0
votes
1answer
24 views

MS Project: Sub-tasks causing unexpected 'Late Start'

I'm attempting to build a schedule and use MS Project to calculate dates and flow, based on constraints and task linking, but am unable to overcome an apparent issue with how the 'Late Start' is ...
0
votes
1answer
33 views

Fix task time of day (Trip planning with MS Project)

I'd like to be able to fix the time of day that a given task must start at and its duration without specifying the actual start date. In this scenario, the date would depend on the end time & date ...
0
votes
1answer
18 views

Microsoft Project - how to calculate start dates based on a set time from the finish date?

I have multiple tasks that have different durations that I want to start at different times from a go live date, i.e. finish date for an entire project. For example: Project must finish on 01 Dec ...
0
votes
1answer
15 views

Microsoft Project 2019 - problem allocating resources to tasks outside their calendar working hours

We have a standard calendar work week. (Monday to Friday with weekends off) Our resources have "standard" calendar - so scheduling as standard for them is a normal work week. However, we have ...
0
votes
1answer
71 views

Microsoft Project IIF (immediate if) limitations

I'd like to understand better the restrictions applied to IIF (immediate Ifs) on MS Project 2016, such as: how many nested iifs are allowed how many characters are accepted in a formula how many ...
0
votes
1answer
340 views

Tracking Gantt Chart Not Showing All Tasks

I am trying to do an earned value analysis and there are tasks in my normal Gantt chart that when I switch the view to tracking gantt are not visible. Could this have to do with where I set my status ...
0
votes
1answer
272 views

Working and non working days

I want to ask if I need to have non working days and working days in a same day. Can we do that in microsoft project? For example Saturday (same date) for items Consultant approval I want to set it ...
0
votes
1answer
41 views

MS Project 2016 updating Actual Cost figures for Cost Resources that are set to accrue at the end of the task

I am having an issue where MS Project 2016 is prorating the actual cost figures for cost resources that have been set to accrue at the end of the tasks. I have tried everything I can think about and ...
0
votes
1answer
96 views

Ms project - assign different resources with different schedules to a task

I'm new at ms project and I have some questions. Let's suppose that I have a human resource named "T1" that works from 2 pm to 11 pm, and that we have a machine named "m1" that can be working all day....
0
votes
1answer
73 views

Dashboard question on microsoft project

Completion % captures the current progress.. I understand that. Is there a way to come up with completion % if all work (hypothetically) was completed on time as of today? e.g., Assume the total ...
0
votes
1answer
45 views

Problem adding resources in MS Project

When I assign a resource in Project, it lists the resource in the resource column and creates a new line listing only the resource. How do I turn this off?
0
votes
1answer
271 views

Task update approvals on a PWA Timesheet automatically changes MS Project duration on task and overall finish date for Project

A resource is assigned to an automatically scheduled task with start date: 2/12 and finish date:2/22. The baselined, saved and published project is scheduled to finish 2/23. The resource does not ...
0
votes
1answer
125 views

How to link BCWP to a customized column I created for physical percent complete

As physical % complete does not roll-up summary tasks, I created a column called 'physical percent complete'. I think I need to link this column to Budgeted Cost of Work Performed (BCWP), just so I ...
0
votes
1answer
414 views

how to distribute the work of an activity between specific number of individuals of a kind from a work resource

I have added a work resource entry "Laborers" with Max. Units 10000% in the Resource Sheet. The resource calendar for this resource is standard and all the units are available. Now I want the work of ...
0
votes
1answer
610 views

How to assign a resource with two units to the task?

I want to assign a resource -Excavator- to a task -Task#1 : duration = 4 month- : 2 units in first 2 months and 5 units in second 2 months.
0
votes
1answer
138 views

MS Project - how to set a task to finish before else start after a set period

I'm trying to set a task to either be wholly complete by 1st Dec, if not then start after 1st Jan (i.e. don't start at all if it can't be completed by 1st Dec). I don't want to split the task. Is ...
0
votes
1answer
1k views

MS Project predecessor formula

I am going to build a project with several tasks and subtasks that have the same structure. For example: SECTION A task 1 task 2 task 3 SECTION B task 1 task 2 task 3 ....... What I would like to do ...
0
votes
1answer
431 views

How to manage “pools of resources” in Microsoft Project 2016?

I need to create multiple pools of resources (each containing interchangeable resources within). To clarify I need a pool of front-end developers, another of back-end developers, and a pool of testers....
0
votes
1answer
3k views

Start-to-Start and Finish-to-Finish Logic in MS Project

Let's say I have three tasks. I want Task2 (hammock activity) to start at the same time as Task1 but finish at the same time as Task3. Is there a clever way of doing this? This task will adjust it's ...
0
votes
1answer
2k views

Is it possible to show the percentage of completed task in the Timeline in MS Project?

I am using Microsoft Project 2013. I would like to visualize in the Timeline the percentage of completed task, for example 33%... Is this possible ?
-1
votes
1answer
59 views

Resource Planning Question

Does anyone know how to plan one resource in Project 2010 when the touch time for that resource for the task such as reviewing something is only 5 hours, but I am obligated to have the object in a ...
-1
votes
1answer
26 views

How to put regular “post to facebook” tasks in MS-Project?

I'm new to project management, among other tasks our company has decided to post messages to social media regularly. Say we want to post every week, how would you write these tasks in MS-Project? ...
-1
votes
1answer
76 views

MS Project: How to deal with a reopened task

There have a task which we assume be completed for a while, but just now we figured out that task is incomplete. How should I deal with that reopened task ? Should I set a baseline and then clean the ...
-1
votes
1answer
778 views

What is the formula to automatically update task progress (% Complete) based on custom flag indicator

In my project I have roughly 45 ongoing tasks that in themselves aren't remarkably important to track progress against and I want to set an automatic rule on these tasks to continuously update ...
-1
votes
1answer
314 views

MS Project displaying work hours extremely wrong compared to duration and resource allocation

I am having an issue with working hours in my project plan with the work hours showing millions of hours even though when factoring duration and resources this is off by a huge margin. For Example: ...
-1
votes
1answer
225 views

Split task in case of interruption: know when start, postpone finish based on interruptions

I'm new in Microsoft Project & in the forum, so forgive me if my comment is just imposible to manage... I have a team in which some of the members get continuous interruptions due to urgent ...
-1
votes
1answer
244 views

MS Project time management scheduling

I am trying to figure out if it is possible to make a project auto-predict time usage for my team but only allow each project to use a certain % of time a day. Ex. I have Project 1-4 and employee 1-3....
3
votes
0answers
50 views

Prevent hourly tasks spanning days

Is there a simple way to block tasks from spanning days? I have some tasks such as interviews & exams which are 2 or 4 hours long but they obviously cannot span days. However MS project is ...
3
votes
0answers
36 views

Determine to which task a resource is allocated on a particular day

Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
2
votes
0answers
35 views

Change task distribution with % completed

I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration. e.g. Mon 2h | Tue ...
2
votes
0answers
41 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
2
votes
0answers
38 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for a server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
1
vote
0answers
280 views

Project Online - Enterprise Custom Field Not Calculating Formula Correctly?

I am new to MS Project (~1 week experience) and could use some help with an Enterprise Custom Field I'm trying to create. I'm using Project through Project Web App in Office 365 (I assume this is ...
1
vote
0answers
23 views

Add columns in master project from external project tasks

I have created a master project ( in ms project 2010 and published in ms epm 2013)that contains only key milestones tasks from external projects. Hence this master project plan contains high level ...
1
vote
0answers
59 views

MS-Project 2016: Sort does not work

With MS-Project 2016 (version up-to-date) I have created a custom report (showing filtered tasks). I want to sort it ascending by Finish date (soonest finish on the top). But it does not work. It ...
1
vote
0answers
48 views

MS Project 2010 task calendar not working

I've created a task calendar for certain transports that can only occur on Wednesdays, with only Wednesdays marked as working time. But when I apply that calendar to the transport milestone items, MS ...
1
vote
0answers
188 views

Resource time not allocating correctly in Project 2013

I'm planning a project where I want my resources to dedicate one day week each to project work. I've created a calendar for each resource which blocks out their day, so there are Tuesday only, ...
0
votes
0answers
972 views

MS Project: Percentage of elapsed work time of project

Suppose we have a project, that its progress is not going exactly on the plan (e.g. we have worked on some future tasks and some previous tasks are not completed on the schedule). and also some ...