Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

Filter by
Sorted by
Tagged with
4
votes
7answers
40k views

MS Project 2013: Overall duration, taking account of non-business days

In Microsoft Project 2013, is there a way of showing "total duration taking account of non-business days", rather than simply "total number of business days"? For example (using a standard calendar): ...
0
votes
1answer
9 views

How to assign multiple resource in task for different duration?

For example I have an activity “Support execution” and it’s duration for 12 hours. To execute this task I need resource X1, B1, C1 & D1. X1 required from the start of activity till end means 12 ...
0
votes
1answer
140 views

Total cost increases every week,

I am using the MS project,i have noticed that the total cost column of the project increases every time i enter actual work. i am not sure why is that! could it be because some of the ressources are ...
0
votes
1answer
554 views

MS Project 2016 updating Actual Cost figures for Cost Resources that are set to accrue at the end of the task

I am having an issue where MS Project 2016 is prorating the actual cost figures for cost resources that have been set to accrue at the end of the tasks. I have tried everything I can think about and ...
1
vote
1answer
58 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
0
votes
1answer
27 views

How create task with fixed work which change duration so that enough work is spent on the task

How do I create a task in Microsoft Project Pro 2019 that takes 1 person 8h to complete. I don't care about the duration or anything else, only that there are 8h spent working on the task. Normal ...
0
votes
1answer
142 views

Ms project - assign different resources with different schedules to a task

I'm new at ms project and I have some questions. Let's suppose that I have a human resource named "T1" that works from 2 pm to 11 pm, and that we have a machine named "m1" that can be working all day....
0
votes
2answers
179 views

How to get Project to _not_ auto-update

I have been tasked to use Microsoft project in a group assignment to help manage it, but I'm having trouble getting the durations and dates to not auto update. I basically would like to have the ...
1
vote
1answer
959 views

PWA / Enterprise custom columns - formula not working

I'm using Project Online and am trying to create a custom calculated column which shows me the percentage difference between my "Actual Cost" and a custom column called "Profitability". I'm having ...
0
votes
1answer
198 views

MS Project - how to set a task to finish before else start after a set period

I'm trying to set a task to either be wholly complete by 1st Dec, if not then start after 1st Jan (i.e. don't start at all if it can't be completed by 1st Dec). I don't want to split the task. Is ...
7
votes
2answers
41k views

In MS Project 2010, is it possible to renumber the task ids?

I'd like the task id field to increment in the same order as the start date, but I have added tasks between existing tasks, so when I sort by start date, the task ids go 1, 8, 15, 2, 4, 5, 7, etc. ...
0
votes
2answers
3k views

Print a MS Project Gantt chart for each resource

I wonder if there is a function in MS Project to print the Gantt chart view for each resource, i.e., when issuing the schedule to everyone I print to PDF: Complete Schedule Summaries only Each ...
1
vote
1answer
37 views

Master Project in MSProj10 moves the dates in the subprojects

When I add in the subprojects to the Master Project, the date ranges are unaffected UNTIL I expand the subproject - at which point - the dates all shift to the right. Can I prevent this?
0
votes
1answer
1k views

Tracking Gantt Chart Not Showing All Tasks

I am trying to do an earned value analysis and there are tasks in my normal Gantt chart that when I switch the view to tracking gantt are not visible. Could this have to do with where I set my status ...
0
votes
1answer
4k views

Start-to-Start and Finish-to-Finish Logic in MS Project

Let's say I have three tasks. I want Task2 (hammock activity) to start at the same time as Task1 but finish at the same time as Task3. Is there a clever way of doing this? This task will adjust it's ...
1
vote
1answer
38 views

Custom Column Calculation

We use MS Project for work. I want to create a column that multiplies the cost of 'work' resources by 5% and 'cost' resources by 15% for each task line. In Excel I know I could use an 'ifs' ...
0
votes
0answers
23 views

Summary Task Fixed Cost not applying to ACWP

One of our projects look like this: Summary Task 1 | Fixed Cost: 3000 | % Comp.: 100% | ACWP: 7000 ----- Task A | Fixed Cost: 0 | % Comp.: 100% | ACWP: 0 ----- Task B | Fixed Cost: 7000 | % ...
0
votes
1answer
305 views

From Microsoft Project to JIRA

I know that this is a topic that has been talked about a lot but I need to export a project from MS Project to JIRA. I know that there are a few JIRA addons to make this job but they are paid and my ...
1
vote
1answer
40 views

Forward and Backward Pass Activity on Node Diagrams in MS Project 2010

I want to make Forward and Backward Slack Activity on Node Diagrams in MS Project 2010. I display the Network Diagram view and choose Format > Box Styles. I Click the More Templates button and in ...
0
votes
1answer
28 views

Lockdown MS Project

Is there a way to lock MS Project into a read-only file that disallows the read-only user from adding or removing columns, changing the size attributes of existing columns or rows, etc.? The password ...
1
vote
0answers
37 views

Trello/TeamGantt Combination

So I've been looking for something pretty particular when it comes to my project. Long story short is that it is a huge project with a multitude of systems that I want to track, of which each has ...
0
votes
1answer
119 views

Dashboard question on microsoft project

Completion % captures the current progress.. I understand that. Is there a way to come up with completion % if all work (hypothetically) was completed on time as of today? e.g., Assume the total ...
0
votes
2answers
21 views

How do you maintain proper resource leveling in MS Project after baseline since resource leveling shifts to maintain slack+leveling days?

Once you have created your schedule with all the known dependencies, leveled resource assignments, and proper baseline, how do you go about maintaining the leveling? Task A is a driver to task B. Task ...
1
vote
1answer
167 views

How to link BCWP to a customized column I created for physical percent complete

As physical % complete does not roll-up summary tasks, I created a column called 'physical percent complete'. I think I need to link this column to Budgeted Cost of Work Performed (BCWP), just so I ...
1
vote
2answers
617 views

Work days and Duration does not match

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days ...
0
votes
2answers
52 views

Actual Duration Calculated by MS Project vs Actual Duration of the Project as of the Status Date

My project started in Jan 2020 and as of Jun 2020, we have spent a total of 80 working days ( minus weekends and public holiday). However, the actual duration given by the MS Project is over 90 ...
0
votes
2answers
844 views

How to show resource usage for the current project only?

In MS Project, is there a way to show resource usage for the current Project only? When viewing the resource usage report, the totals by resource include allocation for all projects. Can it be ...
1
vote
2answers
10k views

How to configure the project schedule for parallel tasks?

I have a resource with 50% availability for a project. I have set the Units in MS Project for 50% for him. He has a number of tasks assigned to him that can be done in parallel. How do I configure ...
4
votes
2answers
6k views

How can two tasks begin on the same day without a resource-conflict?

In MS Project (current version), I have the following task setup and can't find a solution: Short translation for columns: Vorgangsname = Taskname Arbeit = Work Dauer = Duration Anfang = Beginning ...
1
vote
1answer
51 views

Working time not calculating correctly in tasks

I am using MS Project 2016. I am working on a large project working 10 hour days 6 days per week. I have adjusted working times and days and set Sunday to a non working day. But the finish dates ...
0
votes
1answer
23 views

Showing successor task names in MS Project

I'm new to MS Project. I have a view where I want to get a list of successors for a list of tasks. I've added the Successors column and that gives me the list I want, but it's their unique IDs. Is ...
0
votes
1answer
26 views

How to create a resource usage calendar across multiple Project Online projects

The division I work in has 3 PMs that share resources. We have a three fold need we're trying to engineer a solution for within the Microsoft Office ecosystem. We need to create a resource allocation ...
0
votes
1answer
15 views

Is there a way to preview User's time sheet in Project Web App?

There was an option for an admin to preview the time sheet for a user in Project Web App (PWA). Admins can navigate to time sheets and preview only own time sheets. Is there a way to somehow preview a ...
3
votes
0answers
119 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
0
votes
0answers
38 views

How can I show tasks only where the predecessor is complete for task owners in Project online

Currently task owners can see all tasks, but I only want these visible where the predecessors are 100% complete. Is there a way of doing this in MS Project online?
0
votes
1answer
31 views

Display in the Details View --> Task Form: Sorting Predecessors by Task ID, not alphabetically

I'm using MS Project 2013 Professional In the Details View using Task Form, displaying Predecessor view, it is sorting alphabetically by Task Name when I would rather see it sorted by Task ID. I do ...
3
votes
1answer
91 views

Change task distribution with % completed

I'm using MS Project 2010. When assigning a task with duration say 5 days and work of say 10 hours. Then MSP distributes the occupation for that resource over the whole duration. e.g. Mon 2h | Tue ...
0
votes
0answers
13 views

Split task delay report

I have a baseline schedule, for few task delay to be inserted as split in tasks due to bad weather. Now I need to know, how to create a report for split tasks, delayed with reason to be displayed for ...
1
vote
3answers
1k views

Microsoft Project - view resources in hours not percentage

I had assigned resources to tasks in Microsoft Project gantt chart and I would like to see them in hours per resource, not percentages. I know that I can see hours in Resource Usage chart, but maybe ...
0
votes
1answer
60 views

Fix task time of day (Trip planning with MS Project)

I'd like to be able to fix the time of day that a given task must start at and its duration without specifying the actual start date. In this scenario, the date would depend on the end time & date ...
4
votes
1answer
109 views

Determine to which task a resource is allocated on a particular day

Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
0
votes
1answer
80 views

MS Project Configuration - 80% allocation to project, max of 50% per task per day

I'm a newbie to MS Project here, so I was wondering if someone could point me in the right direction, or tell me if I'm barking up the wrong tree. Is there a way to constrain a resource in MS Project ...
0
votes
1answer
82 views

In MS Project :the resource calendar did not show up in the gantt chart but it shows at the resource usage sheet

the resource calendar did not show up in the gantt chart but it shows at the resource usage sheet: i mean that, i assigned the Friday and Saturday as days off in some resources (i am using the ...
1
vote
0answers
29 views

How to cross project plan for enterprise resources, with leveling support in Microsoft Project Server

I'm using Microsoft Project Server on Sharepoint to manage project throughout the organization. I have some enterprise (work) resources, that are simultaneously active on multiple projects. The ...
2
votes
1answer
628 views

Microsoft Project - how to calculate start dates based on a set time from the finish date?

I have multiple tasks that have different durations that I want to start at different times from a go live date, i.e. finish date for an entire project. For example: Project must finish on 01 Dec ...
1
vote
0answers
16 views

MS Project. Need a field that flags what tasks have only completed predecessors that I can bring through to MS Project online

I'm using MS Project which is connected to a PWA. All users complete their tasks on the online 'Tasks' page. For the task owners, I need a flag that tells them that all the predecessors for their task ...
0
votes
1answer
2k views

MS Project predecessor formula

I am going to build a project with several tasks and subtasks that have the same structure. For example: SECTION A task 1 task 2 task 3 SECTION B task 1 task 2 task 3 ....... What I would like to do ...
0
votes
1answer
638 views

how to distribute the work of an activity between specific number of individuals of a kind from a work resource

I have added a work resource entry "Laborers" with Max. Units 10000% in the Resource Sheet. The resource calendar for this resource is standard and all the units are available. Now I want the work of ...
0
votes
1answer
1k views

How to assign a resource with two units to the task?

I want to assign a resource -Excavator- to a task -Task#1 : duration = 4 month- : 2 units in first 2 months and 5 units in second 2 months.
0
votes
1answer
3k views

Is it possible to show the percentage of completed task in the Timeline in MS Project?

I am using Microsoft Project 2013. I would like to visualize in the Timeline the percentage of completed task, for example 33%... Is this possible ?

1
2 3 4 5