Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

Filter by
Sorted by
Tagged with
15 votes
2 answers
53k views

In MS Project, can I create a task whose duration depends on two milestones?

I want to show an ongoing "support" task in MS Project, where the start date is driven by one milestone (test environment available), and the end date is set by another milestone (testing complete). I ...
Iain9688's user avatar
  • 6,868
13 votes
7 answers
13k views

How can I use MS Project to manage an agile project

We use MS Project to manage a project. Although I know that MS Project is just a scheduling tool, we use it to get the current state of the project. We update the % complete field at the end of every ...
matrix's user avatar
  • 323
12 votes
10 answers
28k views

Showing Microsoft Project files to people without Project

The project managers at my company were asked to use Microsoft Project 2013 to track our projects, but many of the business stakeholders do not have Project installed. It looks like I cannot just ...
Daniel's user avatar
  • 16.9k
11 votes
4 answers
4k views

Can MS Projects be integrated in SharePoint?

I wonder if it's possible to integrate a template from MS Projects into SharePoint. We have been using this tool to plan and illustrate workpackages. However, since we have moved into a bigger team ...
yeforriak's user avatar
  • 333
11 votes
2 answers
7k views

Is it possible to link msproject with the TFS system?

I wonder if it is possible to create and manage tasks in microsoft project 2010 and commit the modifications to the TFS project's tasks? It will be practical to raise the percentage of a task in ...
bAN's user avatar
  • 245
8 votes
4 answers
36k views

how can I highlight overdue tasks in MS Project 2007

I am using MS Project 2007. I want to highlight overdue tasks in red color. Is there any way to do so?
matrix's user avatar
  • 323
7 votes
3 answers
6k views

Should Summary Tasks or Detail Tasks be Predecessors?

When setting up a project, what are the advantages and disadvantages to using Summary Tasks vs Detail tasks as predecessors? If it matters, I am experimenting with MS Project 2010 as a tool.
Kyle Brandt's user avatar
7 votes
2 answers
47k views

In MS Project 2010, is it possible to renumber the task ids?

I'd like the task id field to increment in the same order as the start date, but I have added tasks between existing tasks, so when I sort by start date, the task ids go 1, 8, 15, 2, 4, 5, 7, etc. ...
Scott C Wilson's user avatar
7 votes
4 answers
6k views

Catch-Up Scheduling

Say I have a project X that is due to be complete by Date Y Right now we are 10% behind schedule (Should be say 50% and right now 40%), How can I estimate what level of "effort" is required to catch ...
onaclov2000's user avatar
7 votes
2 answers
2k views

Why does MS project multiply the duration of tasks?

I've created a recurring task in MS project and I'd like to assign resources (staff) to that resource but when I add the resource(s) to the task the Work hours multiply to extremes and I don't ...
Sheldon's user avatar
  • 211
7 votes
5 answers
22k views

How can I add contingency to tasks in Microsoft Project?

I'm trying to transfer an existing project plan to Microsoft Project (meaning I can't change how it's organised). Each task has a duration in days then a contingency in days showing how much the task ...
parsley72's user avatar
  • 171
7 votes
1 answer
2k views

MS Project - Span a task over many days AND allow successor to start right after

I am planning my Master thesis through Microsoft Project. Since some tasks can be exhausting (e.g. writing), I would like to distribute some selected tasks over many days. For example, I am estimating ...
Max H.'s user avatar
  • 71
7 votes
2 answers
2k views

How to permit multiple Project Managers to update a shared project

I have searched and not found an answer for this (nor did Google help). We are on Project Server 2007. I am running a large program with multiple project managers handling different parts of the ...
Shannon Davis's user avatar
6 votes
8 answers
10k views

Version Control for Microsoft Project files

In software it is a best practice to store the source code in Version Control software (also called VC, Configuration Management or CM, SCM for Software CM). This lets one go back and look at 1) ...
Brian Carlton's user avatar
6 votes
3 answers
12k views

How to sort by task numbers?

I’m running into a formatting issue that I’ve never seen before with Project. If I have a list of tasks under a summary task and then insert a new task in the middle of the list, after I change views ...
Ben March's user avatar
6 votes
3 answers
1k views

Microsoft Project 2010 - Need Project Design Advice

I'm designing an IT project sheet for my department. I have a certain methodology in mind, but i'm trying to translate it into Project's configuration. Here's what I'd like to do: I want to set max ...
user avatar
6 votes
3 answers
24k views

Using Microsoft Project for managing a Scrum project

I am part of a Scrum team and we are constrained to use Microsoft Project (MSP). I understand that MSP is not primarily an Agile project management tool and I would very much to use something like ...
Ather's user avatar
  • 885
5 votes
8 answers
2k views

What is good PM software for an iterative system development approach?

We aren't necessarily using Agile, but we aren't using the Waterfall approach either; it's more of a hybrid of both. I was told that Microsoft Project is great for the Waterfall method, but it's not ...
vol7ron's user avatar
  • 153
5 votes
4 answers
4k views

What is the purpose of the "as late as possible" constraint in MS Project?

I understand that I can use this constraint in MS Project, but really, what is a good use case for this? When does this constraint make sense?
Amrinder Arora's user avatar
5 votes
3 answers
43k views

How can I highlight the "today line" in an MS Project Gantt chart?

I have an eye problem, so I want to make the "today line" in my Gantt chart to be larger and bolder. Is there any way to do so?
Luke's user avatar
  • 485
5 votes
6 answers
25k views

Simple examples of the difference between fixed-work, fixed-unit, and fixed-duration tasks in MS Project

MS Project tasks are either fixed work, fixed unit, or fixed duration, where Duration x Units = Work The documentation describes which variable is recomputed when one of the others is changed, but I ...
Adam Wuerl's user avatar
  • 1,380
5 votes
4 answers
187 views

Is keeping two project plans ever appropriate?

I feel that if I publish a project plan that shows completion on date X, I can't very well push for completion at date (X - 3 weeks). But If I publish a plan that shows date (X-3 weeks), how can I ...
Scott C Wilson's user avatar
5 votes
2 answers
1k views

How to manage different detail levels in a project plan to be presented to different audiences?

In any given project, a variety of detail levels are needed: executive summary technical summary delivery team summary delivery details How can these different levels of detail be contained and ...
warren's user avatar
  • 942
5 votes
2 answers
459 views

How can I manage a Scrum project and meet the requests of the PMO while using Microsoft Project?

I searched other questions and still can't figure out how we can manage a project that uses the Scrum methodology with tools like Microsoft Project. We are a big software company using Microsoft ...
Amir M's user avatar
  • 51
5 votes
2 answers
239 views

Correct task dependency if Item A is required within 5 months of starting Task B

I'm not sure what combination of task dependency type and lead/lag duration to use for the following scenario. Item B is a large, complicated assembly that includes a subcomponent called Item A ...
Adam Wuerl's user avatar
  • 1,380
5 votes
2 answers
744 views

Level Remaining Resource Units

My goal is to optimize resource usage when having priority tasks partially allocated. MS Project 2007 simple two task scenario (My project has thousands of tasks) with automatic leveling: ======-----...
saamorim's user avatar
  • 161
5 votes
1 answer
2k views

Resource-Task table in MS Project

Does anybody know how to export workload of single resources (columns) per task (rows) from MS Project? The result should look as follows: .............Resource 1.....Resource 2.....Resource 3 Task ...
Sina_Alef's user avatar
5 votes
1 answer
3k views

How to calculate execution variance?

Our Program Management office is interested in identifying tasks where the projected execution differs from the planned execution. MS Project's "Duration Variance" field calculates the difference ...
MCW's user avatar
  • 8,738
5 votes
1 answer
8k views

Unable to schedule a 4-hour task completed over 2 days in Gantt Chart

I'm trying to create a detailed Gantt chart, using MS Project 2013, for a project in one of my courses. Being a student, I'm not working the same number of hours every day. For example, I may have a ...
joshuaegclark's user avatar
5 votes
1 answer
2k views

How to create custom fields at project level in MS Project

Currently, I'm trying to create some custom fields, but I don't want to repeat them in all the tasks, I want to use the option of custom fields by project but the option is disabled. I want to know ...
Pipe2290's user avatar
5 votes
1 answer
1k views

MS Project: Leveling subtask resources by moving summary task

I'm working on a microsoft project pro problem and need help. I have two summary tasks A and B starting on the same day. Each Summary task has sub tasks 1,2 with resources allocated to them and ...
Mark's user avatar
  • 51
4 votes
5 answers
16k views

How do I create a MS Project task with less actual work than its duration?

In Jira projects we have a project task called "Project Admin Tasks". It has a start date from the date of the project inception right through to the end of the project i.e. when the project completes ...
Kev's user avatar
  • 141
4 votes
3 answers
48k views

Microsoft Project - How to quick-filter tasks in this week

As subject, on early Monday, I want to see "what we planned to do in this week". At late Friday, I want to see "what has done/delayed in this week". However, I can't find how to quick-filter tasks ...
Luke's user avatar
  • 485
4 votes
7 answers
43k views

MS Project 2013: Overall duration, taking account of non-business days

In Microsoft Project 2013, is there a way of showing "total duration taking account of non-business days", rather than simply "total number of business days"? For example (using a standard calendar): ...
James Croftson's user avatar
4 votes
4 answers
762 views

What is a good example of a project to use to demonstrate how to build a Microsoft Project Schedule

I want to train a few new team members in the use of Microsoft Project. All are familiar with the basics but I want to explain WBS hierarchy and predecessors. I am trying to think of an 'every day ...
SuperPM99's user avatar
4 votes
3 answers
12k views

Conditionally formatting bar styles in Project 2010

In Project 2010, is it possible to conditionally format a bar style/color based on the value of a custom field for a given task? I see a pretty complicated workaround to accomplish this with Project ...
Sean Earp's user avatar
  • 2,955
4 votes
3 answers
272 views

Need help- Documentation for non-technical people using Agile

Now we are using Agile and hardly create BRD\FRD, we create user stories, and all this is good for everyone working in the same department. Including the stakeholders. However, if I would like to ...
user3412252's user avatar
4 votes
1 answer
178 views

How should I schedule around a resource that may be unavailable for up to 5 months a year?

Background: I am managing a Project where I am responsible planning the construction of a visitor center on the peak of a mountain. The Problem: During reading the brief, I have came across the ...
user3650137's user avatar
4 votes
3 answers
2k views

How to Integrate Multiple Project Plans in a Weak Matrix Organization?

How can I approach integrating multiple project plans from different departments into one master plan? Here are the details in this situation: All teams are ultimately working on the same product, ...
snitzr's user avatar
  • 329
4 votes
1 answer
4k views

Microsoft Project - how to calculate start dates based on a set time from the finish date?

I have multiple tasks that have different durations that I want to start at different times from a go live date, i.e. finish date for an entire project. For example: Project must finish on 01 Dec ...
Andrew Baker's user avatar
4 votes
2 answers
2k views

Getting estimated working time from MS Project

Our company has just recently started using MS Project Professional 2010 and we plan to eventually have a Project Server installation. I've created a few projects so far, but still claim to be a ...
user avatar
4 votes
2 answers
3k views

Planning in MS Project: fixed work AND fixed duration

I currently plan a quite complex project in MS Project. At the moment I cannot plan everything out in detail, but I think that in my head I have a good understanding of how long a task will last and ...
Till B's user avatar
  • 143
4 votes
3 answers
806 views

Do you use the WBS or Project Program to structure tasks in MS Project?

When I first started using Microsoft Project, I took it for granted that I should replicate the WBS in the task list and use that to structure my work packages. After working with Project a little ...
Marwan's user avatar
  • 41
4 votes
1 answer
839 views

Portfolio Reports from Microsoft Project files

How can I take schedule information from multiple (40+) Microsoft Project files and create portfolio dashboards and reports. Specifically, I'd like to see Gantt charts for all projects in a stack.
user5014's user avatar
4 votes
4 answers
2k views

Planning of work with taking into account resource availability (MS Project)

I have the following situation in my organization: Some developers are assigned to Project A. Since this project is currently in the final stage of maintenance (bug corrections, etc.) their ...
michal.slocinski's user avatar
4 votes
1 answer
1k views

Hiding a specific time period in Microsoft Project

Question Good morning, Is it possible on MS Project Pro 2019 to hide a period of time between two dates? Background Our construction projects are divided into 3 stages: (1) pre-construction, (2) ...
ChrisD's user avatar
  • 41
4 votes
1 answer
4k views

How do you calculate the number of days between two tasks in Microsoft Project?

I've created an event planning project that explains all of the relevant tasks before, during, and after a given event in MS Project 2003. I would like to calculate the number of days between a given ...
A-Mac's user avatar
  • 49
4 votes
2 answers
7k views

How can two tasks begin on the same day without a resource-conflict?

In MS Project (current version), I have the following task setup and can't find a solution: Short translation for columns: Vorgangsname = Taskname Arbeit = Work Dauer = Duration Anfang = Beginning ...
Peter's user avatar
  • 165
4 votes
3 answers
2k views

7 Day calendar not calculating correctly in MS Project

I have a 7 days calendar and added 30 days lag to a milestone, however MS Project 2010 does not count these 30 days correctly. I have checked the Change Working Time and it is set for 8 hours per day....
Krys's user avatar
  • 41
4 votes
1 answer
853 views

How can I suppress task type indicators for "The task has a calendar applied to it."

In an mpp file the owner has set a certain calendar and therefore that calendar setting is shown for every single task in the Indicators column. Is it possible to exclude some indicators from being ...
BernieM's user avatar
  • 41

1