Questions tagged [ms-project]

Use this generic tag for questions that apply to most versions of Microsoft Project. For version-specific questions, please use an alternate tag instead of the catch-all tag. Version tags currently include: ms-project-2003, ms-project-2007, ms-project-2010, ms-project-2013, and ms-project-2016.

Filter by
Sorted by
Tagged with
0
votes
1answer
207 views

MS Project, add hours directly in resource usage

at my work we use MS Project 2010 to run our Monday morning scheduling meeting, from Resource Usage view. In the version I inherited on my work computer, I can change the number of hours or add a new ...
1
vote
1answer
267 views

MS Project - Predecessor 'or'

How do I enter 'or' logic into the predecessor field? For instance, task 4 can start when task 1, 2, or 3 ends. We don't know which of 1, 2, or 3 will begin or end first. Thank you
1
vote
1answer
186 views

Printing Gantt charts

When I try to print my Gantt schedule, it hides a bunch of my information rows. How can I fix this? See the comparison between actual Gantt and print preview below:
2
votes
1answer
97 views

Estimating Fixed Price Project Cost Payments via Monthly Milestones

I have spent the last few days searching for an answer on how to use MS Project (2010 in my case) to estimate a project's cost via milestones that are split along a long program (2.5 years). The ...
0
votes
1answer
24 views

Calc days based on Start and Finish date - MS project

When I'm editing start or finish dates, Project moves the other based on the duration. How do I make it change the duration instead so I don't have to keep moving the start and finish dates back? ...
1
vote
1answer
262 views

How can I show a list of all tasks without incomplete predecessors in Microsoft Project?

I would like to see a list of all tasks that satisfy one of the following: The task has no predecessors Every predecessor that the task has is marked as 100% complete. I can add simple filters from ...
1
vote
1answer
36 views

How can you represent a task which only takes place at specific days on MS Project?

I want to represent a task which only takes place at specific days on MS Project: for example, on 01/01/2018 between 9:00 and 11:00, on 03/03/2018 between 10:00 and 12:00 and on 12/03/2018 between 11:...
3
votes
0answers
130 views

How can I create a task for two developers to support testing?

I'm trying to create a timeline for server migration. Typically when it comes to testing our developers spend about 25% of their time supporting the testing. (Running batch processes, answering ...
1
vote
2answers
402 views

How do I identify critical path in MS Project?

I'm using MS Project for my project management works. Would like to know how do I identify the critical path of the project and the dependencies?
0
votes
1answer
180 views

Ms project - assign different resources with different schedules to a task

I'm new at ms project and I have some questions. Let's suppose that I have a human resource named "T1" that works from 2 pm to 11 pm, and that we have a machine named "m1" that can be working all day....
0
votes
2answers
5k views

How to show slippage in MS Project 2016?

Probably a noddy question, but need to ask. I'd like to be able to demonstrate real time slippage on my plan, for remodeling impact purposes. I have both original baseline dates and current dates ...
0
votes
1answer
131 views

Dashboard question on microsoft project

Completion % captures the current progress.. I understand that. Is there a way to come up with completion % if all work (hypothetically) was completed on time as of today? e.g., Assume the total ...
2
votes
1answer
163 views

MS-Project historical timeline

I am using Microsoft Project 2003 for an historic timeline, this means historical dates that go back 1000s of years. I realize using ms-project may be overkill, but it is actually the same as a ...
0
votes
1answer
562 views

How to calculate the completion percentage relation by start and finish dates

I need to calculate the current date in relation to the start and end dates of a task and would expect to see a field that shows the completion percentage. Something like this Question or this ...
1
vote
2answers
1k views

How to organize a 6-month project plan for agile?

We have a charter to build a product in 6 months. I'll preface this by saying that my manager wants us to use waterfall, even though our development process is agile. With that said, I have been ...
3
votes
1answer
365 views

MS Project 2010 - Create project from a set of variables

Being new to MS Project, I am wondering if I can create a project based on a defined template modified by some variables. I am dealing with several (20+) projects I have to manage parallel. The ...
0
votes
1answer
1k views

In Microsoft Project how to get change in resource max units to cascade to tasks automatically

I had already defined a bunch of tasks, and assigned resources 1 and 2. The durations of the tasks were calculated on the resources Max Units availability at the time of assignment. Later I went ...
0
votes
1answer
478 views

How to get a correct duration in MS Project?

I have two effort driven tasks with a work of 8h for each of them. If I delete the duration of task 5, Project fills the field with 1 day? What I need to do is update the work for this task, for ...
-1
votes
1answer
34 views

How to communicate/word cost ranges?

When you display cost estimates, when it comes to ranges, what words do you use to convey: Lower End of the Range, and higher End of the range. The terms I chose (Min/Max) were not liked , so I was ...
0
votes
1answer
111 views

How to Kick off a Task with just 1 predecessor complete

So I have Task A,B,C, Task B is based on CSF-5, (needs to have finish date 5 days prior to C date), but I want the task to kick off as soon as Task A is completed. Is there a way to set that? ...
-1
votes
2answers
64 views

Problem adding resources in MS Project

When I assign a resource in Project, it lists the resource in the resource column and creates a new line listing only the resource. How do I turn this off?
0
votes
1answer
697 views

How to work with estimated end dates in MS Project?

I am new to MS Project and already asked a question here that revealed my incomplete knowledge of the scheduling process. After reading some articles and watching videos like this one, I think of ...
0
votes
1answer
625 views

Task update approvals on a PWA Timesheet automatically changes MS Project duration on task and overall finish date for Project

A resource is assigned to an automatically scheduled task with start date: 2/12 and finish date:2/22. The baselined, saved and published project is scheduled to finish 2/23. The resource does not ...
0
votes
1answer
201 views

MS Project 2013: Can I avoid MSP auto-changing my assignment units to less than 100%?

Curious if there is a way to avoid Microsoft Project auto-adjusting the assignment units, when I add a resource in the Resource name column. In the project settings all resources are set to 100% ...
1
vote
1answer
193 views

How to link BCWP to a customized column I created for physical percent complete

As physical % complete does not roll-up summary tasks, I created a column called 'physical percent complete'. I think I need to link this column to Budgeted Cost of Work Performed (BCWP), just so I ...
0
votes
1answer
97 views

Automatically synchronize between Flowcharts (form of PERT charts) and Gantt charts? [closed]

Summary I'm seeking project-management software tools (be they online/cloud or installed software) that support automatic synchronizing between Flowcharts (a form of PERT charts) and Gantt charts. ...
1
vote
1answer
40 views

Master Project in MSProj10 moves the dates in the subprojects

When I add in the subprojects to the Master Project, the date ranges are unaffected UNTIL I expand the subproject - at which point - the dates all shift to the right. Can I prevent this?
0
votes
1answer
49 views

Is it possible to have a Master “master project” in MSProj10- that is to have a subproject that has its own subprojects?

I want to have a Grandmaster of a complex project - that is one that is has subprojects which themselves are made up of subprojects. Will that work in MSProj10
1
vote
1answer
7k views

How to copy and paste a large number of tasks in the same project file?

I have a schedule broken down by building number (bldg. 1-39); I have inputted the tasks for bldg. 1 (approx. 200) and need to copy and paste this to the other 39 buildings. I can't seem to do this ...
-1
votes
1answer
600 views

How to pause task to complete another task

I currently have 2 identical projects beginning at different times (will be adding more). The manager has a number of "Review" tasks spread out in the project as well as some of his own work. The ...
0
votes
1answer
51 views

Allocating more resource into task no impact on overall duration of project, Why? [closed]

I'm a beginner. In my project, I added some resource into 2 tasks. The tasks' combined duration changed from 6 weeks to 2 weeks, but there was no impact on the overall duration of the project. Is ...
1
vote
1answer
1k views

Why are tasks split while updating plan?

I inserted the actual start for updating a task and then inserted the %comp and reschedule and resource leveling for the plan with ms project 2013. The problem is that the task has been split in ...
1
vote
0answers
53 views

MS Project 2010 task calendar not working

I've created a task calendar for certain transports that can only occur on Wednesdays, with only Wednesdays marked as working time. But when I apply that calendar to the transport milestone items, MS ...
-1
votes
1answer
67 views

Resource Planning Question

Does anyone know how to plan one resource in Project 2010 when the touch time for that resource for the task such as reviewing something is only 5 hours, but I am obligated to have the object in a ...
0
votes
1answer
52 views

How to model extended period of 'searching for product' tasks in MS-Project?

We run a sale of second hand goods from clients. We would set a target say 200 items this season and start contacting people we know who have items they want to sell. We would spend about 2 months ...
-1
votes
1answer
45 views

How to put regular “post to facebook” tasks in MS-Project?

I'm new to project management, among other tasks our company has decided to post messages to social media regularly. Say we want to post every week, how would you write these tasks in MS-Project? ...
2
votes
1answer
74 views

How to Specify how Text Colours Should Override Each Other in MS Project

This is a little embarrassing, but I cannot figure out how to do this. I have added Text Style formatting, but I need to change the priority of the formatting. I have Critical Path tasks formatted ...
1
vote
1answer
51 views

MS Project Column Time different from Project Time

In MS Project 2013 I am attempting to get a particular column to show time unit in Days but leave the default Project Time Unit as minutes for all of the other columns. I can set the Project default ...
0
votes
2answers
190 views

How to get Project to _not_ auto-update

I have been tasked to use Microsoft project in a group assignment to help manage it, but I'm having trouble getting the durations and dates to not auto update. I basically would like to have the ...
1
vote
1answer
237 views

Plot CVI and SVI in EVA graphical report

I am using Project 2007 to perform the calculation related to the EVA methodology. Everything works as expected, and when I generate the earned value over time graphical report I have the correct ...
0
votes
1answer
972 views

How to show critical path INCLUDING completed tasks (in MS Project 2010)

My project is 75% complete and I have no problem getting a nice view in MS Project showing the remaining critical path. However, I want a view that shows how we got to this point, in other words I ...
-1
votes
1answer
149 views

MS Project compatibility and Office 365

I have two questions for the experts on MS Project I have heard that Microsoft will now be releasing updates (from Sept 2018) for O365 without testing them for MS Project 2010. Is this True? Also, ...
1
vote
1answer
718 views

How to turn off auto duration calculation is MS project 2010?

I tried File -> option -> Schedule -> Calculation after edit -> Off And Task mode -> manual scheduled I want to set start date at 12/01/09 and end date at 03/03/09 but I want to set the duration to ...
-1
votes
2answers
207 views

Scheduling: Remaining Work

Let's say I have a task that I've know is going to take 12 hours to do. But when I schedule resources, I only scheduled 6 hours of resources. How could I show that the resources are under-scheduled? ...
2
votes
3answers
547 views

Calculate Cost Deviation

How to calculate Deviation of work and cost of each task on MS project 2010. There is any option for finding the report of Standard deviation. How to find "Cost Deviation" in MS project 2010. Is it ...
1
vote
1answer
62 views

Set Undo Level by the use of VBA in MS Project 2010

How to set Undo Level of MS project 2010 by the help of Visual Basic. I set by option> Advanced>Undo Level but it's not working properly. How to find VB code window for set the undo level in MS ...
0
votes
1answer
749 views

how to distribute the work of an activity between specific number of individuals of a kind from a work resource

I have added a work resource entry "Laborers" with Max. Units 10000% in the Resource Sheet. The resource calendar for this resource is standard and all the units are available. Now I want the work of ...
0
votes
1answer
1k views

How to assign a resource with two units to the task?

I want to assign a resource -Excavator- to a task -Task#1 : duration = 4 month- : 2 units in first 2 months and 5 units in second 2 months.
1
vote
2answers
428 views

Ms Project - Assign resource for fixed duration

Suppose we have two tasks T1 and T2 taking respectively 3 days and 10 days to complete, and two resources R1 and his best friend, R2. T1 starts on Nov 1rst and is supposed to finish on Nov 3rd, while ...
1
vote
2answers
2k views

I want to link one task as successor to multiple task in MS project

I want to link one task as successor to multiple task in MS project. How it can be done quickly? There is one successor and 50 predecessors.