Skip to main content

Questions tagged [planning]

This tag is for questions that involve planning a project schedule or planning tasks for the team.

5 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
1 vote
1 answer
125 views

Is multi-project management possible in OpenProject?

Can I track multiple projects at the same time by using OpenProject?
alfonso's user avatar
  • 121
1 vote
0 answers
159 views

Auto Scheduling in Microsoft Project Planning 2016 is not working as expected

I scheduled many tasks in the AUTO schedule, However, it is not taking/changing the dates once I link all the tasks. Due to that, I selected the start date manually which is resulting in a different ...
kapilddit's user avatar
  • 111
0 votes
0 answers
58 views

MS project status update with % complete AND actual work

I have created a new MS Project project with a task in it. This task has a "Work" of 360 hours and is assigned to two resources. The task is scheduled with "Fixed units" and "...
dude's user avatar
  • 101
0 votes
0 answers
33 views

Show timebased plan and the people involved at each activity

Disclaimer: I am not a project manager, just a software developer, so I may need some help wording this to make it acceptable. I was talking to a company who want me to do some consulting work, ...
Mawg's user avatar
  • 121
-2 votes
2 answers
161 views

Is it difficult or time-wasting for developers to adjust page design based on component design changes?

I have been curious about that how much effort developers have to make to adjust components to accommodate changes in UI design. Sometimes I think a design from UX is good and there's no problem for ...
Chris Ma's user avatar