Questions tagged [pm-software]

This tag is for questions regarding the USAGE of software directly related to project management. Questions about technical support or product selection are off-topic. You should already know what tool you plan to use and what process the tool will automate before writing your question. Use specific software tags (e.g. "ms-project", "jira") rather than this generic tag whenever possible.

7 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
1 vote
1 answer
531 views

MS-Projects -- Assigning a Resource group as resource

I am using MS Projects (desktop) and am wondering if it is possible to assign resources by the group they are designated under in the resource list. Essentially I would like to assign a team to a ...
user avatar
  • 11
1 vote
0 answers
116 views

How to set dependencies in TeamWork app to cascade delays in one task into dates of other tasks?

Let's say I have multiple tasks that are supposed to be taken care of one after another. Each has its own date of completion. task 1 - will be completed on 15 march (1 day) task 2 - will be completed ...
user avatar
  • 111
1 vote
0 answers
55 views

MS Project 2010 task calendar not working

I've created a task calendar for certain transports that can only occur on Wednesdays, with only Wednesdays marked as working time. But when I apply that calendar to the transport milestone items, MS ...
user avatar
  • 11
0 votes
1 answer
196 views

How to create a resource usage calendar across multiple Project Online projects

The division I work in has 3 PMs that share resources. We have a three fold need we're trying to engineer a solution for within the Microsoft Office ecosystem. We need to create a resource allocation ...
user avatar
0 votes
0 answers
93 views

Azure Boards Query: Rollover Cards

I am trying to put together a query that indicates cards that have 'rolled over' from one sprint to another. This should happen from time to time, but too much roll over is a flag that something is ...
user avatar
-1 votes
1 answer
170 views

In Jira-Domo integration, issues with more than 1 sprint show as closed in the first sprint

We set up DOMO to pull from our Jira issues. We noticed that the Velocity charts were not matching up. We realized that for issues that are rolled into more than one sprint - if they weren't complete ...
user avatar
-1 votes
1 answer
212 views

Support for Resource Overview in Omniplan

In Omniplan 2.3.5, Is there any way to create a Resource report similar to the report Microsoft Project offers? This report should include: how many hours does a resource work when do they start ...
user avatar
  • 111