Questions tagged [pm-software]

This tag is for questions regarding the USAGE of software directly related to project management. Questions about technical support or product selection are off-topic. You should already know what tool you plan to use and what process the tool will automate before writing your question. Use specific software tags (e.g. "ms-project", "jira") rather than this generic tag whenever possible.

11 questions with no upvoted or accepted answers
Filter by
Sorted by
Tagged with
2
votes
1answer
70 views

How do you filter project tags in Azure Devops?

The list of projects we've got in Azure DevOps is rapidly growing and growing. It makes it difficult to focus on areas that need attention across the department though, and is taking a lot of Admin ...
1
vote
1answer
133 views

MS-Projects -- Assigning a Resource group as resource

I am using MS Projects (desktop) and am wondering if it is possible to assign resources by the group they are designated under in the resource list. Essentially I would like to assign a team to a ...
1
vote
0answers
113 views

How to set dependencies in TeamWork app to cascade delays in one task into dates of other tasks?

Let's say I have multiple tasks that are supposed to be taken care of one after another. Each has its own date of completion. task 1 - will be completed on 15 march (1 day) task 2 - will be completed ...
1
vote
0answers
53 views

MS Project 2010 task calendar not working

I've created a task calendar for certain transports that can only occur on Wednesdays, with only Wednesdays marked as working time. But when I apply that calendar to the transport milestone items, MS ...
0
votes
0answers
15 views

Microsoft Project Duration Multipliers

In Microsoft Project, is it possible to have variables that can be used to set durations of tasks? For example my goal is to have a variable that could be set for 200 hours of work, the completion of ...
0
votes
0answers
20 views

Semantic Analysis tools to group and evaluate free text customer feedback

What tools would you recommend to run semantic analysis of large amounts of customer feedback in free text form. My Problem: I have tons of responses to a survey in which customers answered in free ...
0
votes
1answer
142 views

How to create a resource usage calendar across multiple Project Online projects

The division I work in has 3 PMs that share resources. We have a three fold need we're trying to engineer a solution for within the Microsoft Office ecosystem. We need to create a resource allocation ...
0
votes
0answers
277 views

In an Azure DevOps work item Excel file, how do I assign parent without having to see closed siblings?

I'm using the "Teams" tab provided by MS in Excel to add repeating Azure DevOps User Stories (US), i.e. work that needs to be done every sprint (don't ask). This seems to be the recommended approach ...
0
votes
0answers
66 views

Azure Boards Query: Rollover Cards

I am trying to put together a query that indicates cards that have 'rolled over' from one sprint to another. This should happen from time to time, but too much roll over is a flag that something is ...
-1
votes
1answer
153 views

In Jira-Domo integration, issues with more than 1 sprint show as closed in the first sprint

We set up DOMO to pull from our Jira issues. We noticed that the Velocity charts were not matching up. We realized that for issues that are rolled into more than one sprint - if they weren't complete ...
-1
votes
1answer
210 views

Support for Resource Overview in Omniplan

In Omniplan 2.3.5, Is there any way to create a Resource report similar to the report Microsoft Project offers? This report should include: how many hours does a resource work when do they start ...