Questions tagged [pmp]

For questions about the Project Management Professional program, courses and the exam.

Filter by
Sorted by
Tagged with
0 votes
1 answer
96 views

Planned Value (PV): why amount of work is spread evenly on timeline?

I have a basic confusion on Planned value calculation. Example: BAC* : 1000 Time: 4 weeks after 2nd week, PV** should be 500 However, in my opinion, this sometimes does not hold true in an actual ...
Manish's user avatar
  • 101
2 votes
2 answers
87 views

How to Understand the Answer to this Question

A group has been working together for a month. During the daily meetings, one team member continues to report problems completing his/her tasks. What should a project manager do? A: Start discussions ...
user19775353's user avatar
1 vote
1 answer
143 views

What is the difference between "active listening" and the "sender-receiver model"?

I don't quite understand the difference between active listening and the sender-receiver model. active listening: The message receiver restates what’s been said to fully understand and confirm the ...
takanoha's user avatar
1 vote
5 answers
384 views

How to reject new requirement in project?

I am a PM for a waterfall methadology project. And I am going to ask a question that every PM faced I believe, but it is my first time to face such situation and would need your support and guidance. ...
amr007's user avatar
  • 33
1 vote
3 answers
401 views

Work Breakdown Structure - Help on identifiying deliverables, workpackages, etc.,

I'm seeking help for a project I'm involved with. I'm assigned to create a WBS for a project. I'm quite new to PMP and I'd like to ask for help or any advice in creating the WBS of the project we're ...
Ivan Villarosa's user avatar
1 vote
2 answers
88 views

Auditing vs. Inspection

I’m confused about the difference between audit and inspection. I know that they will have different meanings if used in different processes, but I think that inspection is about “deliverable or ...
Neptune's user avatar
  • 113
-1 votes
1 answer
43 views

PMP Stakeholder best level of engagement

In the PMBOK we have this different level of stakeholder engagement: Unaware Resistan Neutral Supportive Leading What is the best level that you should have? Because last month in a question i put ...
Neptune's user avatar
  • 113
0 votes
2 answers
542 views

Difference between: Change control system, change control tools, configuration management plan, configuration management system

I'm studying for the PMP exam and I have some understanding what these objects are and what the differences between them are. Can someone explain, maybe with some examples? Thanks. Change Control ...
Neptune's user avatar
  • 113
0 votes
1 answer
62 views

Do I have EVM Planned Value understood correctly?

I am struggling to get all the PMI EVM terminology sorted out. The last key for me was planned value (PV). Let say I have a task and my BAC is $100,000 and scheduled for 4 weeks. 2 weeks in I am done ...
Dan Tappin's user avatar
2 votes
1 answer
60 views

Planned / earned value for items outside of the project scope?

Getting my head wrapped around the PMP / PMI earned value methodology. Traditionally have tracked a project budget vs the actual spend on a simple basis with that being the variance etc. The scenario ...
Dan Tappin's user avatar
0 votes
1 answer
131 views

How to estimate amount of work/man hours for an unfamiliar task? This project is fixed bid project from customer

How to estimate amount of work/man hours for an unfamiliar task? This project is fixed bid project from customer. And most of our project is fixed bid project, for the past 3 - 4 project we are ...
Steven Pang's user avatar
2 votes
2 answers
271 views

Question regarding PMBOK (6th edition) definitions of project life cycles

I am currently studying for the PMI PMP exam and stumbled upon the following question in Kim Heldman's "Project Management Professional Practice Tests" book (correct answer boldened): A ...
barghest's user avatar
  • 123
0 votes
1 answer
903 views

EMV calculation for prototyping versus not prototyping

Good day, I'm currently studying for my PMP, and I'm confused about the following found in the Rita PMP prep book: A company is trying to determine if prototyping is worthwhile on a project. They ...
JeAnn Watson's user avatar
1 vote
1 answer
98 views

PMP application [closed]

I am in the process of writing my PMP application. I am a Program Manager at my work, however, I manage multiple similar projects in a year. Can I bundle up all similar projects and document them ...
Sonali's user avatar
  • 11
1 vote
2 answers
3k views

What to know about PMD Pro vs PMP

I am currently wondering about the differences between PMP and PMD Pro and what are the pros and cons of both certifications. If you can you help me here, then do it.
Joshua Espulgar's user avatar
0 votes
1 answer
75 views

Which are top three metrics one should look at as PM specially from IT industry perspective [closed]

I know its very subjective question, however in general I wanted to understand which are the top three metrics as PM, I should look at while working in a Software project
sumit's user avatar
  • 13
0 votes
3 answers
213 views

PMP certification without having served in a management position

I am looking to get certified in project management , however in my 20 year job history I have never held a "Manager" title. I have served in an "software developer" , "system analyst" and "...
JavaHead's user avatar
  • 111
2 votes
1 answer
124 views

Putting zero hours under a process for a PMI application

As you all know, project descriptions are limited to 550 characters in the PMI application. In two projects in my list, I decided to highlight tasks I did in the planning and the monitoring processes ...
The Last Word's user avatar
2 votes
2 answers
230 views

2000 hrs a year as project management experience in application

I find conflicting information on how many hours I can claim a year as project management experience with some experts suggesting that I claim just 1500 hrs while others suggest claiming the full 2000 ...
The Last Word's user avatar
1 vote
1 answer
289 views

PMP application but did only one project as a lead and one solo project

I am a biology researcher and I have been part of many research projects over the years. I have also played a minor role in a firm as part of a project trying to find franchisees for the firm. I have ...
The Last Word's user avatar
2 votes
2 answers
2k views

Does Project Charter change when the Project manager changes?

What if the project manager changes all of a sudden during the project at any phase (Due to resignation / Personal reasons / Accident). Does the Project charter also change with it? If so, Who does ...
Prakash's user avatar
  • 121
4 votes
1 answer
484 views

Is a company with Tech Leads a matrix organization?

Employees of my company are grouped into pools depending on technical skills (e.g. front-end devs, back-end devs, QA engineers, etc). For each pool there's a Tech Lead who doesn't manage projects (or ...
franz.fonta's user avatar
3 votes
1 answer
73 views

Can organizational trainings (Classroom and Web-based) be considered for Continuing Certification Requirements (CCR) of PMP?

Can organizational trainings on Project Management (Classroom and Web-based) be considered for Continuing Certification Requirements (CCR) of PMP? For example I recently attended a few trainings on ...
Manuj's user avatar
  • 43
0 votes
2 answers
274 views

A PMI/PMP Requirements Questions [closed]

I have searched and searched online for an answer to my specific question, but haven't found it yet. Can't find the solution on PMI.org either. Maybe you can help. I have more than 4,500 hours for ...
Tomster's user avatar
  • 11
0 votes
1 answer
100 views

Should workarounds pass by the Perform Integrated Change Control process?

If an unanticipated problem occurs (unknown-unknown), should the devised workaround need to pass by the Perform Integrated Change Control process before it is allowed to be implemented?
Bougret's user avatar
  • 111
1 vote
3 answers
643 views

What is the difference between ITIL and PMP?

It seems I'm dragging you along with me in the IT field, believe me, it's not premeditated. My question - a little broad that I admit - is: when is ITIL used and when is the PMP used? and why rather ...
AED's user avatar
  • 211
1 vote
1 answer
495 views

How to determine hours spent on a project if didn't record them at the time?

How can I produce an accurate determination of hours spent on projects in the past when I didn't record the time spent at the time? I used to own my own business putting on concerts in the Seattle ...
Zack Lyons's user avatar
0 votes
1 answer
84 views

Project Management courses [closed]

I have just completed my three years in project management role. I have contributed five projects towards successful delivary and achieved targets on time. I have been told to pursue management ...
Vinayak Sabnis's user avatar
2 votes
2 answers
4k views

Can running my own business be counted towards PMI experience requirements?

I started a retail business from scratch. I imported ready-made garments. I was the CEO for three years, managed everything, and worked in my stores full time. I had employees as well. The ...
Shadi Sweilem's user avatar
-1 votes
1 answer
221 views

PMP question bank [closed]

I am looking for a way to practice for PMP. A question bank for PMP would be nice. There are lots of sample questions in web. But I do not know which one to select. What can be the criteria to select? ...
lamostreta's user avatar
4 votes
1 answer
828 views

ETC calculation including SPI

PMBok (page 221) mentions two formulas for estimation ETC based on previous project performance. These are: (1) ETC = (BAC-EV) / CPI (2) ETC = (BAC-EV) / (CPI * SPI) While (1) is completly clear ...
BerndGit's user avatar
-1 votes
2 answers
410 views

How long will be 5th edition of PMBOK be basis for PMP certification

As far as I know the PMBBOK 5th edition will be soon be replaced by a new edition. When it is expected that the content of the 6th edition is mandatory for PMP certification?
BerndGit's user avatar
0 votes
1 answer
80 views

Degree completed 2 years back but have PM experience for more than 5 years

I have been performing Project Management for more than 5 years now. I have completed my Degree in Distance Education program. Can I use this degree to qualify for 4500 hour in last 36 months? I am ...
Rajesh Jaganatha's user avatar
0 votes
1 answer
270 views

PMP hours documentation

I understand PMP documentation is 4500 hours with a degree and that the hours covered must not overlap. I also understand that the hours you spend studying, can only cover a 36 month period. My ...
Eric's user avatar
  • 11
0 votes
1 answer
170 views

PMP certification experience hours for each PM phase [closed]

I am filling out my application for PMP cert, but a very small percentage of my hours are allocated to the 'Initial' phase. Would this a deal-breaker?
sotn's user avatar
  • 111
0 votes
2 answers
292 views

Does the current PMP exam ask about human motivational theory?

I have already completed my class for the 35 hours of coursework, and am working through my second full read through the PMBOK 5th edition. I have also been looking online for test prep exams and ...
Shawn's user avatar
  • 256
-2 votes
1 answer
324 views

What is unique about application development projects? [closed]

I'd like to understand the difference, from a project-management perspective, between application development and other, non-application development.
Shamil Bhatti's user avatar
0 votes
2 answers
76 views

Types of audits in service IT industry [closed]

I have seen many job descriptions for project managers in which organizations want the candidate should have been worked on different audits and audit reporting. I have 2 questions: Kindly explain ...
shams's user avatar
  • 5
3 votes
5 answers
48k views

Can I go for PMP certification without having any project management experience?

I have 4 years of work experience as Network consultant. I have worked in a team and also led a team of 3. However, I have never worked as a Project Manager. Can I go for the PMP certification or not?
Prachi Bansal's user avatar
2 votes
1 answer
1k views

Why can't the Crash Time be greater or equal to Normal Time?

Scenario Activity | Normal Cost | Normal Time | Crash Cost | Crash Time | Weekly Crash Cost A 5,000 4 5,000 4 0 B 8,000 4 ...
fufusaki's user avatar
0 votes
1 answer
679 views

Can I use the PMP Exam book to prep for a CAPM exam? [closed]

I purchased Rita Mulcahy's PMP Exam Prep(8th Edition) and I have already finished the first eight chapters. However, I have realised that this book is only for experienced PMP attendants not for CAPM. ...
Ozge B. Duff's user avatar
0 votes
1 answer
154 views

Logical Loop: PMBOK 5th Ed

I am hoping someone can clear up my misunderstanding of the sequence for developing a project plan according to PMBOK 5th Ed. We see that creating a project plan inputs into it's subsidiary plans (...
JSolano's user avatar
  • 13
-1 votes
2 answers
1k views

PMP experience requirement

PMP experience requirement-I'm scrounging for hours! 1. On a parenting leave of absence from the workforce I started up a small business, went on training courses, incorporated the business, ran it ...
I Mayer's user avatar
  • 11
3 votes
3 answers
925 views

Requirements for PMI's PMP course

I am interested in working towards my PMP certification. I have a 3 year BSc degree from someplace in Canada which I got back in the mid 1980s. As I read the requirements, they specify a 4 year ...
Stephen Simpson's user avatar
0 votes
1 answer
252 views

Master degree business administration vs. Project Management Professional (PMP) to become project manager in Programming Inc. and why

I want to be project manager; now my job is .net/web developer . What is the best way to become a project manager and what are the minimum years of experience needed? pmp
Ibrahim Alsurkhi's user avatar
0 votes
2 answers
538 views

Anyone studying for PMP exam or have passed PMP? [closed]

Is there anyone here who is studying for PMP exam or someone who has passed the exam already ? I have two questions for those who have passed: Q1. Let's say I have read the book and understood the ...
qw008's user avatar
  • 1
2 votes
2 answers
1k views

Things to consider before Project Initiation

What are the things to consider before project initiation. I believe a lot goes on before the charter can be produced and PMBOk 5 is a bit silent on that point.
Michael Effanga's user avatar
4 votes
2 answers
3k views

What does it mean to 'crash a project'?

'Crash the project' is a term is used frequently in PMP materials. What does it mean exactly? How is it related to 'compressing the schedule', if at all?
getglad's user avatar
  • 187
4 votes
4 answers
143 views

Faulty piece of software discovered, next steps for a Project Manager to take

Consider the following scenario, which is straight out of a PMP exam prep book: The project manager of a large software implementation project just finished a project status meeting. In the ...
Josh's user avatar
  • 159
5 votes
4 answers
844 views

How can I write a project charter prior to collecting requirements, defining scope, estimating and so on?

I am trying to set my mind on the PMI rails, but absolutely can't get the order in which a project manager asked to prepare a project charter prior to steps in the planning process group like ...
Tural Mamedov's user avatar