Questions tagged [reporting]

Use this tag for detailed questions about how to create or manage reports.

Filter by
Sorted by
Tagged with
1 vote
2 answers
116 views

How do you measure progress for design works?

We are a software agency that adapts product approach because some of our clients need a discovery process before we actually dive into coding. This is a typical situation when a client comes to us ...
David Sojka's user avatar
0 votes
1 answer
32 views

How to represent time durations (e.g. time spent), in Excel, in hours-minutes-seconds?

Our platform has Excel reports with fields like Estimated Time or Actual Time spent on a task. These fields are not standardized - in some reports, time values are represented as 10.8 mins, 0.22mins, ...
Aveek Baruah's user avatar
0 votes
4 answers
149 views

Toggling the format of dates in MS Project

I often have to change the format of the date to check and "adjust" new sequences activities. It is very inconvenient to click always through the menu so I tried to find some VBA-macros for ...
Daniel's user avatar
  • 1
1 vote
2 answers
63 views

MS Project Dynamic Portfolio Reporting

I have a team creating projects in MS Project. I need them to share their projects with me (in sharepoint?) so I can pull individual reports in real time. I then need to take those dynamic projects ...
Lori's user avatar
  • 11
0 votes
1 answer
224 views

Finish Date not correct

I have one task that starts on 8/1/22 and ends on 1/23/23, but the duration is 2.5 days. The end date isn't calculating correctly. I have theses resources assigned to the task, total 27.2 baseline ...
jennifer halter's user avatar
5 votes
6 answers
2k views

How to handle stakeholders' different understanding of project requirements?

As a software tester/QA, how to handle when stakeholders (e.g Project Manager and Developer) have different understanding of project requirements? I understand that this communication breakdown ...
emeraldgold07's user avatar
1 vote
4 answers
658 views

What is the difference between "status report" and "variance report"?

Quoting Rita Mulcahy's book-: Status report-: This report describes where the project currently stands regarding the performance measurement baseline. Variance report-: A variance report compares ...
Team B.I's user avatar
  • 161
0 votes
1 answer
79 views

How to automate inclusion of confluence design docs in Requirement traceability report on Jira

If an organization is regulated, it has to pass the audit and show that it has implemented a "requirements traceability". This means it has documented the path from a specific requirement to ...
systemdebt's user avatar
0 votes
2 answers
100 views

QA phase reporting for SW development

In our project, we have a testbook with some test scenarios to be performed by a QA team. Each scenario must be tested on multiple device/OS/browser (in this particular case, just 3 combinations), and ...
Antonio's user avatar
  • 113
1 vote
3 answers
115 views

PM Control Charts using RAG

When using a RAG (Red, Amber, Green) scoring system on control charts for cost and schedule, would you score a variance from green to amber and then to red the further you move away from a zero ...
David Espina's user avatar
  • 37.1k
3 votes
2 answers
715 views

What is the most effective way to store and track impediments on multiple projects and having them up-to-date?

I am facing a problem of registering the impediments in one place from several projects that we are running at the company. What I have tried another Jira board for product owners to create issues ...
chullspen's user avatar
3 votes
3 answers
2k views

How do you filter project tags in Azure Devops?

The list of projects we've got in Azure DevOps is rapidly growing and growing. It makes it difficult to focus on areas that need attention across the department though, and is taking a lot of Admin ...
James's user avatar
  • 31
1 vote
1 answer
157 views

Dynamically updating filters in a dashboard

The team I'm on has a couple of JIRA dashboards for our projects tracking tickets that were completed. Our process is to create a filter for that weeks completed issues, and then create a new ...
midfield99's user avatar
2 votes
3 answers
161 views

Is there a report type to document a (Agile) project journey?

My main goals are to document our current methodology, share our team's story of changing and adapting, and share evaluations of our improvement. Ideally, I'd like to share this report with our ...
aliciasilhavy's user avatar
0 votes
1 answer
53 views

Manage activities of a group to make monthly reports

Recently I'm managing a group of people. It has 3 areas, with each area having an average of 7 people; there are 20+ people. To make a monthly report to my boss, I am faced with the following problems:...
Vrian7's user avatar
  • 101
3 votes
4 answers
3k views

Scrum Master role: Reporting?

Is the Scrum Master responsible for creating reporting on behalf of the development team to drive continuous improvement? I currently do this, and use that as a basis to improve processes. Other ...
bobo2000's user avatar
  • 3,892
0 votes
1 answer
248 views

Can I query for "date added to @currentiteration" in TFS?

I am trying to find a way to write a query in TFS to retrieve any PBIs or Work Items that were added to the @CurrentIteration after date X. Usually date X will be the iteration start, so if that is ...
BoomShaka's user avatar
  • 119
3 votes
1 answer
316 views

Create MS Project report which to return incomplete tasks per user with due date

I want to be able to produce a report I can share with resources on a project so that they have visibility on what outstanding tasks they have (overdue, current, future) and when they are due. ...
as_stack's user avatar
2 votes
5 answers
133 views

Best way to report impact of accepting additional work in scope?

Org I work in is trying to be agile, but often struggles with respecting the committed scope during a sprint and keeps forcing us to accept new work. This is coming at a cost; happiness and quality. ...
bobo2000's user avatar
  • 3,892
1 vote
1 answer
123 views

Report in MS Project (Hr/task/resource)

I am trying to find/create a report in MS Project 2013 in order to display hours done in a month by a certain group of resource or a resource only (they are already grouped in the Allocation tab) with ...
user34307's user avatar
0 votes
2 answers
183 views

Cost management without time tracking in Scrum

In my company I'm responsible for several software development teams. Lately our managers asked me to establish a time tracking system for our developers to have better overview over the actual costs ...
deviolog's user avatar
  • 109
1 vote
1 answer
40 views

Is it possible to sort JIRA tickets in the Reports area?

the question is very simple. Scenario is a Scrum Project. I would need to be able to sort tickets in the Reports are of a Scrum Project. Currently those tickets are separated per area, as Completed, ...
axel's user avatar
  • 379
1 vote
4 answers
1k views

What to do with control chart data?

I am running a kanban project, I am collecting cycle time data via control chart, what is the best way to use it?
bobo2000's user avatar
  • 3,892
0 votes
2 answers
589 views

Personal Time Tracking report using Atlassian Jira

I'm a software developer and I'm asked to log my time in Atlassian Jira for each of the subtasks we have in all the open stories. Sometimes we are in rush and I forget to log some time in the many ...
JeanValjean's user avatar
1 vote
1 answer
265 views

Can you extract issues from Jira on premise for reporting to management?

We have had a lot of success using JIRA for our risks, issues, decisions and milestones. What I want to do, though, is to have these queried and represented on a dashboard with Gantt charts, issue ...
aimon's user avatar
  • 11
0 votes
1 answer
380 views

Why does my Earned Value curve go back to zero

I managed to simulate a project in MS Project 2013. I created an initial planning, assigned ressources and put this in a baseline. Then I imagined two status for my project in two different dates. ...
Mohamed's user avatar
  • 113
5 votes
4 answers
681 views

Should I ask developers to report hours in daily reports or ask them to keep the task tracking tool we use with this level of detail?

I am the IT manager in a company having 30 people in the IT team. There are 3 major teams, each with 7 to 8 people, + few other smaller teams. Different locations, cultures and timezones. Having ...
Miloš's user avatar
  • 153
1 vote
1 answer
138 views

Milestone Reporting Format - Any ideas?

If I'm expecting the delivery of around 50 items from a contractor, each with their own forecast delivery dates and agreed need dates, what is the optimal way to track the forecast dates each time it'...
James Henderson's user avatar
2 votes
1 answer
173 views

Effective Status Reports - How to bring management attention?

How should I structure my weekly status report in such a fashion that I can have senior management attention to the issues being reported? Being objective, how to properly and effectively report ...
Friendly Sheep's user avatar
2 votes
1 answer
59 views

How to know when the project started in JIRA?

I am an admin for JIRA project following SCRUM approach. I am trying to report to my direct manager when the project was started. I went to Settingsand Timesheets.. and many places. And I cannot ...
Abdennour TOUMI's user avatar
2 votes
1 answer
3k views

How to generate a lead time report in JIRA without a plugin?

Has anyone compiled a lead time report (in any format) from JIRA without the use of a plug-in? If so, how did you do it? The native Control Chart tracks cycle time but not individual times for ...
Venture2099's user avatar
  • 4,065
1 vote
3 answers
5k views

How to create deliverables column in Gantt chart?

I’m taking Intro to Project Management online and the instructor has required us to produce Gantt charts with deliverables prominently in their own column on the far right. We can use any software we ...
Eric Hepperle - CodeSlayer2010's user avatar
2 votes
2 answers
551 views

Report to Show Work During Current Week Only

I need to create a work-ahead dashboard for my team, for weekly planning meetings. We have tasks that span several weeks, so a task may be needing work in the current week but not starting or ending ...
StackMonkey's user avatar
2 votes
1 answer
129 views

What process changes can I make to more accurately track both collaborative stories and individual time within Jira?

I'm currently working with an organization that is using the Jira Tempo Timesheets plugin to track developer time, but the way that Jira stories and tasks are being used fails to capture overhead ...
Todd A. Jacobs's user avatar
  • 50.1k
2 votes
1 answer
125 views

Gantt charts with ranged estimates?

I'd like to create Gantt charts with ranged estimates (for reporting to non-technical execs) but don't want to use a web service (LiquidPlanner). How can I get Gantt charts with range estimates?
Display Name's user avatar
1 vote
5 answers
134 views

Executive Summary Repetition

This might be an intuitive question but it seems that not much people knows it. Should I repeat information from last report's executive summary or should I only write what happened the week before ...
OOzy Pal's user avatar
  • 141
3 votes
1 answer
83 views

Consulting and separating internal and external tickets

So, I'm helping an agile software consulting company to create a workflow between themselves and their customers. The goal is to provide the customer with an Agile way of approving features (stories) ...
JMarsch's user avatar
  • 173
3 votes
1 answer
5k views

Is there a way to use your customized fields in reports created in MS project 2013?

I have some customized fields that I've created. I really need to find a way to use them while I'm creating customized reports in MS project, but I just see the built-in fields when I want to create ...
Tina's user avatar
  • 31
-2 votes
3 answers
94 views

How should I classifying my daily project activities into tags?

In the company where I work, I need to fill out a timesheet specifying how I spent my working hours for each project. I need to put the amount of time spent, and also a comment about how I spent that ...
zeferino's user avatar
5 votes
1 answer
1k views

In TaskJuggler, how to manage multiple projects running in parallel

I manage three different projects with TaskJuggler. These project share some of the resources. I follow these suggestions and created three different .tjp files. I'm fine for my individual reports, ...
Christian Lemer's user avatar
0 votes
0 answers
262 views

How to draw stacked column chart with custom text fields?

I am working on a report on MS Project 2013. In this report there is chart. The chart is based : NumberOftasks (Y-axis) which is a custom field of type number. Localization (X-axis) which is done by ...
user avatar
3 votes
2 answers
2k views

Displaying a resource's tasks across multiple subprojects

I am having a bit of an issue getting the kind of report that I want from MS Project 2010. To get some background on my project, I am creating a master scheduled using multiple templates. The ...
Seth39195's user avatar
3 votes
2 answers
407 views

What is the quarterly report called after fourth quarter?

First of all, I apologize for such a minor question. I am not sure if this is a suitable platform for this. I am responsible for submitting quarterly reports for a project. I am doing this since last ...
sylvia's user avatar
  • 31
1 vote
2 answers
242 views

No Checkpoint Reports

I am running a Prince2/Waterfall project that is currently about 1/4 of the way through a 8 month timeline. I have been having trouble with Work Package owners not providing me with Checkpoint reports/...
JS-'s user avatar
  • 135
3 votes
3 answers
514 views

EVM in Research and Technology

Earned Value Management (EMV) sounds like a great and objective method for reporting. Precondition for applying EVM is that tasks or results are well defined and well distributed during the project. ...
Tob's user avatar
  • 1,767
0 votes
1 answer
4k views

MS Project Professional 2013 Email Notifications

I am attempting to use MS Project Professional 2013 to send out automated outlook e-mails the week before a task is due among other automated e-mail tasks. Is this possible with the desktop program or ...
Eamon's user avatar
  • 3
1 vote
1 answer
482 views

What is the 'life-cycle' of an issue or exception report

What is the 'life-cycle' of an issue and exception report. I've seen the reports, and it looks like only one sheet that needs to filled out once. Of course, it may not be filled out completely at the ...
Ramonster's user avatar
  • 133
4 votes
1 answer
312 views

Work statistics report for resources

I have a master file with several sub-projects and resources assigned to them. Is there a way to make a bar chart in Project Pro report that shows the work hours for resources based on the sub-...
Millie T's user avatar
2 votes
1 answer
798 views

MS Project 2013 Reports: ACWP in Timephased Line Chart does not match ACWP in Column Chart or Table

Version: Microsoft Project 2013 Standard (15.0.4420.1017) Hello - I am creating a report in MS Project 2013. When I create a time-phased line chart containing ACWP, the ACWP shown in the chart for ...
Bill Cary's user avatar
3 votes
3 answers
399 views

Is reporting project progress in % to supervisors acceptable?

Currently I am working as a Project Manager in a big software project. Currently my supervisors require me to report each week to report the project's progress in percentage form, as in the example: ...
Placeholder's user avatar