Questions tagged [resource-planning]
Resource Planning is a method for the effective planning of all variety of company's resources. Such resources may be people, funds, equipment, etc. On this site, Resource Planning usually means workforce of the people assigned to a certain project.
196
questions
0
votes
0
answers
38
views
Three-Point estimating software (PERT?)
I'm looking for project management/planning software which makes it easy to work with the uncertainty in estimating effort for tasks. E.g., every task might have an optimistic, pessimistic, and ...
1
vote
2
answers
73
views
How to achieve substitutability if the team is not cross-functional (operation team)?
How to achieve substitutability if the team is not cross-functional (operation team)?
Currently in my Operation team, there are 3 sub-teams, each consisting of 2-3 people, which are handling different ...
0
votes
1
answer
59
views
Microsoft Project Does Not Sum The Work Total Of Resources Other Than The First Resource In The List
On the Default Resource Usage view, totals are displayed only for the first resource. Others are not added and displayed.
The zero total is also present in other reports. How can this be fixed?
0
votes
1
answer
38
views
Replacement for Project 2010 that lets multiple users edit at once?
We've been using Project 2010 and have a file saved to our network which we all enter data into and modify to track our projects. With licenses for Project 2010 no longer available, we were looking to ...
0
votes
2
answers
220
views
How we can calculate the free warranty time for a software application [closed]
I am a freelancer, and I am going to build a software application developed using SharePoint Online as the DataSource, Power Apps and Power Automate. The Project mainly includes automating 14 business ...
1
vote
1
answer
113
views
Is it possible to start with the amount of hours each person needs for each task and their availability, then drive the project schedule from that?
Following this question, I have a hierarchical list of tasks. I have asked my team members to tell me how much time they need for each task. I also know the interdependency between those tasks. take ...
1
vote
2
answers
132
views
Under what circumstances does resource levelling become necessary?
Sorry for the preamble here - but I think the context is important.
I'm responsible for tracking progress on a project which runs on a NEC3-ECC contract which requires that programmes (implemented in ...
0
votes
2
answers
158
views
MS Project: How to plan tasks that have no particular order?
I am involved in software development and I have a total of 35 features that need to be implemented in our software. Each feature has been estimated for the time it will take, and there are 5 ...
1
vote
1
answer
216
views
How can a generic resource be overallocated?
MS Project.
My understanding is that a generic resource is specifically of infinite availability. That's why it's generic.
So in the very early stages of our journey to implementing resource ...
1
vote
2
answers
65
views
Is it possible to have personal backlogs and planning according to the prioritization of the tasks?
Microsoft Project is ok for setting up for Gannt Chart and baseline but it is not possible to see individual plans and schedules. Is it possible to integrate all?
is it possible to have personal ...
0
votes
2
answers
657
views
Project Plans - MS Project Vs Atlassian BigPicture
I'm an engineering project manager, responsible for the delivery of development projects. We're currently using MS project for project for task and resource management and have been recently ...
1
vote
3
answers
211
views
How does the use of CI/CD make it easier to handle the loss or absence of key staff?
I'm working on a project that has no CI/CD. We have only one person who builds the code and deploys it to staging and production. In the past there have been discussions on implementing CI/CD, but to ...
2
votes
4
answers
169
views
How does project management manage people with differing abilities?
I once worked on an application programming project with three main tasks:
Build a system for analyzing a user situation
Integration with another piece of software
Organize the main architecture of ...
0
votes
1
answer
295
views
How to calculate a flexible team capacity and have the sprint capacity adapt to it?
I am planning a Program Increment of 3 Months and I have a team of people with a variety of skills.
Basically, we have 3 categories in which each developer is differently skilled: UI, Backend & ...
5
votes
4
answers
2k
views
What's the role of a Resource Manager in Agile?
The following exchange took place in the comments to an answer to another question How do I manage development with testing and get proper reporting in JIRA?, which seem to highlight a different ...
1
vote
1
answer
197
views
Estimate date based on number of resources allocated to project
Is there any way to determine an estimated project date by number of resources allocated? I have set up all my tasks to automatic and effort driven and identified critical tasks and dependencies, but ...
1
vote
1
answer
587
views
MS Project chart for multiple projects
I am a project manager and I use MS Project to manage multiple projects. I use a shared resource pool. I have been playing with the charts feature, in the resource file to try to get a chart showing a ...
1
vote
3
answers
208
views
How to compete for resources with other project leaders
I handed over one of my projects to another project lead. Before that, I shared my resources more freely between my four projects, to ensure stress was bearable for all and milestones were met.
I ...
-1
votes
1
answer
82
views
How to manage time and resources efficiently? [closed]
I am new to resource management and I wanted to improve the time management of my team in handling tasks/projects. Do you have best practice to follow on giving out tasks or on planning the resources ...
-2
votes
1
answer
73
views
Project Management for Website Agency - Change of Industries [closed]
I have a couple of years experience of project management in a particular industry. Covid-19 restrictions have hit it hard and I have been out of a job for the last 6 months. There is not going to be ...
0
votes
2
answers
99
views
Project managment case on interview: Contingency resolution
I am getting ready for an interview for the role of project manager and came across an interesting case. How would you approach this case in an interview?
Your team supports Google's internal service ...
2
votes
1
answer
2k
views
MS-Projects -- Assigning a Resource group as resource
I am using MS Projects (desktop) and am wondering if it is possible to assign resources by the group they are designated under in the resource list. Essentially I would like to assign a team to a ...
1
vote
0
answers
430
views
Auto allocate resources
Is there any way to make MS project choose the resources for tasks between candidates that I've given to it? I mean there are several people who can do a task but how many of them and which ones are ...
1
vote
1
answer
241
views
Gantt chart with resource de-confliction
I like to use Gantt charts to model the time tasks will take and the dependencies of those tasks. For reference, I use GanttProject but I am not tied to it.
One issue I've had, however, is handling ...
0
votes
1
answer
360
views
Microsoft Project - Tasks do not split if a higher priority task "Leveling Can Split" is set to "No"
I have an issue where using "Priority, Standard" levelling that "Leveling Can Split" appears to stop lower priority tasks from splitting. I am trying to ensure that highest ...
2
votes
3
answers
235
views
Effect of front-loading tasks on project schedule
Customer wanted to re-prioritize activities and move them up the schedule. This will result in some tasks being carried out in parallel. To avoid over-allocating my resources, we have recommended to ...
0
votes
1
answer
1k
views
How to resolve the resource overallocation when the resource is allocated with 200%
I have a project with 650 days of effort with 2 resources to work with. For both resource it is 8 hours per day. When I assign resource with 200% of allocation for all the task the resource is ...
3
votes
2
answers
242
views
What is the standard approach to planning work that might or might not be needed based on certain circumstances?
I am wondering what the typical approach would be here:
In a project, we are renewing old machines and therefore the new ones will need to be integrated into an older system. That might or might not ...
0
votes
2
answers
146
views
How do you maintain proper resource leveling in MS Project after baseline since resource leveling shifts to maintain slack+leveling days?
Once you have created your schedule with all the known dependencies, leveled resource assignments, and proper baseline, how do you go about maintaining the leveling?
Task A is a driver to task B. Task ...
2
votes
2
answers
351
views
How to accurately communicate task priorities?
In my company, I am constantly struggling with how to accurately communicate the priorities of tasks. Some of the aspects of this are:
Some tasks need to be done before a deadline, however, sometimes ...
0
votes
1
answer
280
views
How to create a resource usage calendar across multiple Project Online projects
The division I work in has 3 PMs that share resources. We have a three fold need we're trying to engineer a solution for within the Microsoft Office ecosystem.
We need to create a resource allocation ...
1
vote
0
answers
95
views
How to cross project plan for enterprise resources, with leveling support in Microsoft Project Server
I'm using Microsoft Project Server on Sharepoint to manage project throughout the organization.
I have some enterprise (work) resources, that are simultaneously active on multiple projects.
The ...
6
votes
3
answers
304
views
Decision making between alternatives: methods and tools?
My company is in this situation:
low budget
few time
a lot of idea for new feature
So, we need to prioritize feature implementation, only some will be implemented now, some other will be next year, ...
1
vote
0
answers
87
views
MS Project, Resource Availability, Task Usage work hours
I've been using other tools for awhile and have to jump back into MS Project.
I started a high level plan with tasks and resources, however, I'm having trouble remembering the specifics around Task ...
1
vote
1
answer
228
views
How to assign 1 resource to a fixed work task where the resource has 50% availability for the first 2 days and then 100% availability after that?
I have a project that I am trying to schedule and am having a little difficulty. I am a MS project novice and will try to explain the problem in a simple example.
I have 1 task which is fixed work. ...
1
vote
2
answers
113
views
How can I calculate duration and price for the development of SW product?
How can I calculate the duration and price for the development of the C# software? Does exist any pattern or tools for that? I think the duration of the project can be about the 6 months, for one ...
0
votes
1
answer
70
views
What is the report called that tells you whether a business venture is worth pursuing?
This report would be distinct from a market research report which helps a business understand something central or auxiliary component of their existing business. I'm referring to a report that helps ...
0
votes
2
answers
326
views
How to allocate a manager to many tasks that overlap
I have a project with a lot of work going on in different domains. Say one domain is Business Process. Each domain has a single manager, for example the Business Process manager. There are lots of ...
1
vote
0
answers
165
views
Auto Scheduling in Microsoft Project Planning 2016 is not working as expected
I scheduled many tasks in the AUTO schedule, However, it is not taking/changing the dates once I link all the tasks. Due to that, I selected the start date manually which is resulting in a different ...
13
votes
10
answers
6k
views
How to execute a project with two resources where you need three resources?
Recently, I participated in a Project Manager interview and the following question were raised. What would be the correct answer for that?
A software development project is needed three resources to ...
0
votes
3
answers
189
views
How can I plan resources for maintenance after project?
My managers are asking, before green-lighting a new project, how much people (resources) will it take after the project is done, to maintain it. Ie: fix bugs, deploy new features on demand, adapt to ...
1
vote
3
answers
2k
views
MS Project Configuration - 80% allocation to project, max of 50% per task per day
I'm a newbie to MS Project here, so I was wondering if someone could point me in the right direction, or tell me if I'm barking up the wrong tree.
Is there a way to constrain a resource in MS Project ...
2
votes
1
answer
1k
views
MS Project resource graph across multiple projects
I am using MS Project to create Gantt charts for multiple projects. Each project consists of different resources but these resources are shared across all of these projects.
Currently these resources ...
3
votes
1
answer
119
views
How to divide a generic resource?
I am still new at using ms project Professional. My project has already assigned resources.
For instance, let's take developers who together have a maximum effort of 200%, which means I have 2 ...
0
votes
1
answer
499
views
ms project - delay a task due to unaviability of 1 resource
I want to schedule tasks using multiple resources. The work task is fixed and multiple resources are allocated to the tasks.
I want to auto-schedule the tasks, however, when 1 resource is ...
4
votes
2
answers
68
views
Is focusing on one project beneficial even when project priorities can't be quantified?
Small internal IT department that assists all of a company's departments.
Each department has projects that each are 'priority 1' - the departments and executive team are unwilling to strictly ...
3
votes
1
answer
162
views
Duration vs Work...Resource Overallocation Errors
I am fairly new to project so apologies up front...I have several tasks in my project plan which have a set duration; i.e. start and end dates/due dates, but the actual amount of time required for ...
4
votes
2
answers
291
views
Determine to which task a resource is allocated on a particular day
Using a shared resource pool for several project plans (each plan is contained in a separate file), what is the simplest way of working out to which task a given resource is allocated on a particular ...
6
votes
4
answers
2k
views
About the claim that adding more developers to a team does not make delivery faster
Over the years, I have heard many times that adding more developers to a team does not make things faster. My opinion is that it's a question of management. If you can allocate one complex screen of a ...
1
vote
1
answer
232
views
MS Project - Multi-year Inflation
I am managing a 3 year project in a country where the average annual inflation rate is 12%. Instead of going through every item and entering "+12%" into the cost rate table for each item, is there a ...