Skip to main content

Questions tagged [risk-management]

This tag is about documenting risk, handling risk, risk estimations, cross-team project risk, and any other risk that may affect the outcome of a project.

Filter by
Sorted by
Tagged with
1 vote
2 answers
108 views

Time & Material project contract - how to handle blockers during project execution

Imagine you are a consulting company and you have T&M contract based project. You aligned with the customer to provide consultants to work on a 4days/week schedule. The project is facing an issue ...
Marcin Sanecki's user avatar
0 votes
2 answers
51 views

Gantt Chart software for a monthly process with tasks/milestones based on business day of the month? [closed]

I am looking to create a Gantt chart for our Production process. This is a risk reporting process for a financial institution and it is run monthly. One key feature of most tasks and milestones is ...
finrisk_01's user avatar
2 votes
1 answer
175 views

ISO Requirement for Risk Acceptance

ISO seems to suggest that there needs to be a risk initial/residual exposure threshold where, if exceeded, there needs to be evidence of "acceptance" by someone with approved authority. The ...
David Espina's user avatar
  • 37.1k
1 vote
2 answers
330 views

How do you calculate acceptable risk on your project?

I am trying to find some information on the following: how do I determine the acceptable risk (risk appetite) for my project, what is the usual practice/approach? Is it percentage of profit, for ...
ProwlingBeast's user avatar
1 vote
3 answers
516 views

How do we mitigate by reducing the impact of risk(Risk response planning)?

Risk mitigation is a strategy for reducing the probability or impact of risks. I understand by what reducing the probability of risk means. For eg-: Consider a risk of theft while working in an area ...
Team B.I's user avatar
  • 161
1 vote
1 answer
244 views

Risk triangular distribution: percentile sensitivity

When modelling risks, usually a triangular distribution based on three time estimates (optimistic, likehood and pessimistic time estimates - a, c, and b respectively) is used to evaluate the planning ...
Upax's user avatar
  • 158
0 votes
3 answers
150 views

Hired a mid level consultant who is producing junior level work. We're 2 weeks in. Should I recommend letting her go or giving her time to ramp up?

Things to consider: She's getting paid at a level that implies that she is a very experienced mid level consultant She doesn't ask questions, even though I very clearly make it known that I'm ...
inadilemma's user avatar
1 vote
3 answers
457 views

Do I calculate the Earned Value with BAC or PV?

I'm a little confused on how to calculate the EV. There are two formulas that I found: EV = %completion x BAC EV = %completion x PV When do I use which formula?
nmq's user avatar
  • 11
0 votes
1 answer
149 views

What are the risks and mitigation strategy for SAAS solutions?

I am suggesting a software solution POS for a small retail store to manage his business operations effectively. I am just trying to identify the risks and its mitigation strategy for SAAS solutions. I ...
I Love Stackoverflow's user avatar
13 votes
5 answers
5k views

Scrum teams and the risk of a member getting sick

Scrum suggests small teams as far as I'm aware. This means that we often have single frontend developer, single backend developer, single QA engineer, etc. Doesn't it negatively affect the project ...
Daniel's user avatar
  • 2,739
6 votes
4 answers
1k views

How to formulate risks well for risk analysis?

If I have to formulate goals for a project there's the well established S.M.A.R.T. paradigm. It helps to have goals at the end, from which necessary actions can be easily deduced. It prevents from ...
Ariser's user avatar
  • 161
-2 votes
2 answers
101 views

In Agile project management, do you keep everything in Jira or maintain some documents? [closed]

I'd like to know about agile project management practices - do you keep everything in Jira or do you create and maintain any external documents (Requirements, Project schedule, Definition of done, ...
Chris Brettini's user avatar
0 votes
1 answer
108 views

How to identify risks in a given case study? [closed]

I am working on a case study which is like below : Economic inequality is a huge issue. A recent study found that the world's 80 wealthiest individuals own as much as the entire world's poorest 3.5 ...
I Love Stackoverflow's user avatar
5 votes
3 answers
760 views

Dev went on vacation leaving his work unfinished. How to manage this without informing the customer?

I would like to discuss and hear some advice from you about a pretty common situation. We develop the functionality that has huge business value for the customer’s project and thus the customer is ...
Artem's user avatar
  • 153
0 votes
1 answer
5k views

Good RAID Log examples & usage

I was hoping for any good examples of how anyone has effectively presented RAID logs (or the individual lists of Risks/Assumptions/Issues/Dependencies) in their projects. In particular for Agile/Scrum ...
Dave Hollows's user avatar
0 votes
1 answer
77 views

Which are top three metrics one should look at as PM specially from IT industry perspective [closed]

I know its very subjective question, however in general I wanted to understand which are the top three metrics as PM, I should look at while working in a Software project
sumit's user avatar
  • 13
0 votes
1 answer
114 views

How do you agree with a client for a deliverable version (definition of done) on a big project

My company sells an ERP software in a very specific niche. The process is turnkey and every bit of data is entered for the client before launch. Since a lot of our customers have different needs, we ...
phadaphunk's user avatar
6 votes
4 answers
2k views

What could be my risk mitigation strategies if my client wants to contract UAT?

My client wants to squeeze UAT into 6 working days from originally planned 10 working days. This is because they want to go live because of an impending business reason. As a risk mitigation strategy ...
Jarvis's user avatar
  • 193
4 votes
2 answers
106 views

I Need Help Quantifying Risk of Behavioral Variables

BLUF I need advice on how to capture cultural or behavioral risks in an organization (Cost, Duration, Scope) to a project in a fashion that can quantify and express those risks and mitigation options ...
Shelix's user avatar
  • 41
3 votes
2 answers
60 views

Which risks to expect when managing different vendors on a client assignment?

My next role is of a Program Manager managing interdependencies between multiple projects. It involves daily program management until the program cycle ends. Each project is being delivered by a ...
Jarvis's user avatar
  • 193
2 votes
3 answers
145 views

importance of long list of risks

Can anybody explain the importance of having long list of risks in managing the project? i know we should cover maximum of all possible one but what really significant importance to have a long list ...
Mian Almas's user avatar
14 votes
5 answers
3k views

Product Owner is requesting a "confidence check" for reaching the MVP - How to in a Scrum project?

We're in a quite complex software engineering project with lots of unknowns due to new technologies involved that the Team has never applied nor have comparable experience. Due to these risks the ...
Andre Meier's user avatar
0 votes
1 answer
5k views

Risk register vs risk report

Risk documents normally are documents in possession of the Project Manager with the discretion to show only to Project Team and Sponsor. Risk register is a document that contains all the work ...
Maximus Decimus's user avatar
2 votes
2 answers
193 views

When should I raise risk with stakeholder [closed]

Should I raise risks immediately when I see one or should I try to resolve the risk first and then raise it. How long should I try before raising one.
rsapru's user avatar
  • 123
1 vote
4 answers
372 views

How is a countermeasure influencing the total risk score?

I'm just setting up a risk management for a project, and I have to admit, that I'm not used to it. That's my table so far. ----------------------------------------------------------------------------...
Herr Derb's user avatar
  • 111
2 votes
1 answer
92 views

How is consensus and accountability achieved in large software development projects?

I'm studying how distributed software is managed (Linux, Wikipedia etc) and am trying to figure out if there is any pattern for consensus and accountability. Ideally I could visualize the inputs and ...
makerofthings7's user avatar
2 votes
2 answers
168 views

How to explain to management that taking over an external project is a big risk?

Management thinks that it would be lucrative to take over a fairly complex solution from a startup founder. Apparently the client has fired the tech company that had built it due to "poor quality". It ...
Jessica's user avatar
  • 21
3 votes
2 answers
132 views

Distributed Risk Register and Facilitation of Risk-Based / -Aware Thinking

Over here, it was aksed how to overcome reticence to use RAID logs (with A referring to actions, not assumptions). The general approach, already suggested by the OP, would be to rid the (in this case ...
loom with a crew's user avatar
-1 votes
2 answers
362 views

How do I facilitate a project risk assessment?

Let's say I wanted to asses the risks in a project like the one in this link: https://github.com/tanay-bits/baxter_skeletonteleop, where I am tele-operating a robot using a vision sensor. How can I ...
king rogers's user avatar
8 votes
5 answers
2k views

How to deal with constantly (~daily) changing requirements?

I see a number of similar links, but none seem to have a solution, mostly "they shouldn't be doing that"'s. I agree, but please, read on: Scenario: 800K pages of documents, narrative(e.g. emails)/...
Gryph's user avatar
  • 304
0 votes
3 answers
697 views

Do you show your RAID log to stakeholders?

So I have started documented all risk related issues in a RAID log. I am showing my stakeholder it weekly, so that he is aware of all product related risks, but not sure if there is much value in ...
bobo2000's user avatar
  • 3,892
-1 votes
1 answer
310 views

RAID logs - What is the best way to organise them?

First time using RAID logs as part of project delivery. I have found a template where Risks is separate from Issues done in Excel. I am using it the following way: 1) RISKS - I specify all potential ...
bobo2000's user avatar
  • 3,892
3 votes
4 answers
1k views

Development buffers and risk factors

How do you plan on risks when working on the project detailed plan? I assume you add to the plan vacation days for each resource (even though they may not have requested leave at this point), you plan ...
Diana's user avatar
  • 89
0 votes
3 answers
194 views

How to track and manage project progress & opportunities?

I am trying to manage project progress; what is the best way to track and manage project progress? As the project progresses, how does one recognize, anticipate and track alternative possibilities?
Krishna Datt Shukla's user avatar
-1 votes
4 answers
132 views

Is it normal to find managing remote teams/subcontractors harder?

Typical problems I have found that there is: a delay in communication, even after using project planning tools. More delays. Remote worker not having the self discipline to work structured hours and ...
bobo2000's user avatar
  • 3,892
1 vote
2 answers
207 views

Are retrospectives and daily stand ups replacement of risk management

Currently we are following a lot of the Scrum routines like stand ups, refinements, planning 1/2, demo, retro... The past few months we were heading downwards showing poor performance and delivering ...
Leron's user avatar
  • 179
1 vote
3 answers
1k views

Is lack of knowledge/experience in the dev team a risk according to the risk management theory

Our team has 1 BA, 3 devs and 1 QA. We are trying to follow SCRUM as much as possible and since recently the term Risk management was not a part of our dictionary. However the past few months our ...
Leron's user avatar
  • 179
2 votes
6 answers
1k views

How to minimize scope creep?

Scope creep can easily transform a good project into a distressed one. What are the methods for minimizing continuous expansion of project requirements?
Ruslan Doronichev's user avatar
1 vote
1 answer
164 views

Finding out whether a decision made has been risk-taking or risk-averse

I want to do an empirical study on risk management by translation trainees for my MA thesis. Translation is an act full of decision-makings for rendering risky parts of the text. I want to interpret ...
m2004's user avatar
  • 163
1 vote
2 answers
173 views

What risk analysis model shall I use if I know the areas (sources) of risk?

I know the areas of risk in a group of companies based on a Risk Breakdown System. With what model shall I analyze them afterwards? Is FMEA good for this purpose? If yes, how should I apply it?
m2004's user avatar
  • 163
3 votes
1 answer
53 views

How exactly one can find out the influence of each risk component in Fault Tree Model? Is that possible at all?

How exactly one can find out the influence of each risk component in Fault Tree Model? Is that possible at all with model?
m2004's user avatar
  • 163
1 vote
2 answers
849 views

FTA (Fault Tree Analysis) or FMEA (Failure mode and effects analysis): how they are different from each other?

I have decided to work on risk analysis for my MA thesis, but I am stuck with choosing the theoretical framework for that. I am not studying MBA or other Management fields, and that makes my job hard. ...
m2004's user avatar
  • 163
1 vote
3 answers
156 views

Having trouble managing a sub contractor

I am project managing on an on going bases an e-commerce site for a client. I have only one resource working on it, a sub contractor due to a lack of resources. He is working remotely. I am having ...
bobo2000's user avatar
  • 3,892
1 vote
1 answer
83 views

Identify risks from 100 case studies [closed]

I want to identify risks from 100 case studies of past construction projects. What the most relevant documents that I need to consider that would save my time. Thank you in advance, Mustafa
Mustafa M. AL-Shammaa's user avatar
2 votes
2 answers
2k views

Who is responsible for risk management in Agile-style deliveries?

I have a lot of experience of waterfall-style deliveries (or more accurately, incremental waterfall since I don't know of anyone who still does actual rigid waterfall any more), but none whatsoever in ...
Marv Mills's user avatar
  • 4,414
3 votes
3 answers
118 views

What qualifies as a trackable risk?

When creating a Risk Analysis document, what qualifies as a reasonable risk? As a rule of thumb we expect 5 risks to be tracked. Is it reasonable to include risks such as the building burning down or ...
Danny Schoemann's user avatar
14 votes
8 answers
2k views

How to motivate my team members to start documenting their work

I just started a new job as a technical project manager. It's more or less my first experience, as I have just run teams of two students before, and now I am managing a project of 10 engineers, some ...
user2536125's user avatar
1 vote
2 answers
91 views

Using probability to assess issues

In risk management within projects, probability is used as a way to understand how likely risks are to happen in the future. This is obviously a well-established area. Presumably there is nothing ...
Curious_analyst's user avatar
1 vote
6 answers
164 views

Product launch failure [closed]

Background I'm currently working on a product (external facing) and we are on the verge of launch of the product. I want to gear myself up with facing the worst situations since this is the first ...
psteelk's user avatar
  • 171
5 votes
4 answers
199 views

Project constantly running into problems, so how does a PM manage the consistent budget impacts?

With a certain project, I reconcile on a weekly basis to determine its performance, i.e. if estimates are being adhered to or not. Issue: Every week, the team faces a new issue that wasn't accounted ...
Ray's user avatar
  • 247