Questions tagged [schedule-risk]
For questions about identifying, documenting, communicating, or mitigating risks to a project's schedule.
44
questions
0
votes
2
answers
42
views
Gantt Chart software for a monthly process with tasks/milestones based on business day of the month?
I am looking to create a Gantt chart for our Production process. This is a risk reporting process for a financial institution and it is run monthly. One key feature of most tasks and milestones is ...
5
votes
2
answers
644
views
Refactoring in Agile development
In an app development project, the full scope of the project was not considered in the app design. So, the frequent refactoring of codes to accommodate changes is negatively impacting the project ...
0
votes
2
answers
1k
views
Actual Duration Calculated by MS Project vs Actual Duration of the Project as of the Status Date
My project started in Jan 2020 and as of Jun 2020, we have spent a total of 80 working days ( minus weekends and public holiday). However, the actual duration given by the MS Project is over 90 ...
2
votes
3
answers
358
views
Task estimation and probable risks
Let's suppose we are estimating a task (not by the planning poker). We have discovered that there are a few possible problems (risks):
Risk 1 - with the probability p1, ..., risk N - with the ...
2
votes
2
answers
583
views
How to Handle a Funding Overrun on a Time and Materials (T&M) Contract
Here is the scenario: You are the PM of a new T&M contract that has a $800,000 budget at completion (BAC) and a price of $1,000,000 and a one-year period of performance (POP). Scope is fluid, ...
4
votes
4
answers
75
views
Scheduling for Calendar Time when availability is variable?
I have a few core team members who also look after daily support. It’s not uncommon for them to get stuck in some firefighting for a day or two which completely throws off a project schedule. How can ...
4
votes
4
answers
194
views
How to deal with a client who does not respect PM practices, yet wants a PM?
Simply put, I have a client who does not respect PM practices.
We have a large, high value, multi-stakeholder, multi-variable project. I estimate that if we are not 50% complete by end of February, ...
5
votes
5
answers
258
views
How to manage consulting resources to deliver ahead of delivery dates?
I am a PM for a large matrix enterprise organization that has internal development resources as well as contracted consulting groups. Depending on the project we may need to engage an application team ...
0
votes
3
answers
184
views
How to track and manage project progress & opportunities?
I am trying to manage project progress; what is the best way to track and manage project progress? As the project progresses, how does one recognize, anticipate and track alternative possibilities?
3
votes
2
answers
221
views
How can I produce more reliable estimates for technology refresh projects?
After running a few projects that refresh technology rather than add functionality, I've noticed a few recurring themes:
Technology refresh projects are more likely to go over budget/schedule; ...
2
votes
6
answers
1k
views
How to minimize scope creep?
Scope creep can easily transform a good project into a distressed one. What are the methods for minimizing continuous expansion of project requirements?
1
vote
5
answers
467
views
Managing scope changes and timelines for graphic design components of a project
Our team mostly does web application projects, working directly with our clients. For projects without a public-facing interface, design is rarely a major issue.
Nearly every project that involves a ...
2
votes
2
answers
2k
views
How can I plan for contingencies in Scrum?
Like any project, things happen. How can I plan for contingencies in a Scrum-based project?
My current practice is to have 10% contingency for the whole project, e.g. for a 10 sprint project, we will ...
4
votes
2
answers
2k
views
What does it mean to 'crash a project'?
'Crash the project' is a term is used frequently in PMP materials. What does it mean exactly?
How is it related to 'compressing the schedule', if at all?
2
votes
1
answer
155
views
Earned Schedule results versus Critical Path and Finish Variance results
I am monitoring a schedule right now for a project that is about 57% complete (duration). Looking at it at two different perspectives--Earned Schedule and Critical Path--I am finding results that ...
1
vote
6
answers
224
views
How can we prevent project professionals from sabotaging the project schedule?
I work with an organization that hires professionals with temporary contracts that last for the length of the particular projects they are working on. At the moment, these contracts are usually just a ...
7
votes
1
answer
113
views
How to deal with scheduling/control when task insertion (vs task duration) is primary risk
We're working on a project that has a considerable amount of task insertion risk (by which I mean either a) the insertion of new tasks into the WBS or b) the rearrangement of technical dependencies in ...
0
votes
2
answers
142
views
time management
After you determine the activity durations, you have a range associated to the it (duration +/- sigma). If you now want to determine the critical path in the network diagram what figure should you ...
1
vote
1
answer
778
views
How to calculate Critical Path including Std Dev for each activity estimate?
When estimating activity durations, you get a duration plus/minus a sigma (standard deviation) for each activity.
Afterwards, when you want to determine the critical path, what figure should you ...
4
votes
3
answers
166
views
What is the process of schedule management with clients who aren't very responsive?
Here's the scenario: The main point of contact was fairly active up until the project came close to the launch date. At that point, the client started to miss the dates for requirements that were ...
3
votes
3
answers
186
views
Documenting diversions or delays from a schedule?
This question is based on David Espina's answer: https://pm.stackexchange.com/a/14017
Specifically, the following portion:
On the other hand, deviation from a planned approach is sometimes required. ...
-2
votes
1
answer
277
views
Important Concepts In Project Management [closed]
What are the most important concepts that should be added (as notes on ms project)? for example: Defining the project scope, risk management .. what others?
0
votes
1
answer
187
views
What does a "Contingency" Plan involve? [closed]
For example, if lack of resource commitment is identified as an issue, then what would the contingency plan look like? does it have a specific structure? what key factors must I consider when ...
2
votes
1
answer
4k
views
How do you calculate extra costs incurred if a project overruns its schedule?
If a project doesn't meet its planned schedule, how do you calculate any losses per day incurred? Is there a graphing function in MS Project that I can use to depict losses per day?
17
votes
9
answers
4k
views
Should a Product Owner be asking developers to do QA to meet deadlines?
When the deadline is tight and when there are not enough QA people, the Product Owner asks developers to join in with QA to meet the deadline.
What should the developers do when this happens?
What'...
9
votes
4
answers
2k
views
When can a project's wrong estimates be justified?
This question is not about project estimation techniques, initial processes, etc. Assume everything was done correctly.
Recently, we gave an estimation for an Android application with development ...
3
votes
3
answers
16k
views
How to ask for more time if project misses a milestone and will be delayed?
I've been searching for management role for a long time and finally got myself hired into a new start up company as Project Manager. I'm managing a project (Multi Level Marketing Apps) Team. I ...
4
votes
3
answers
840
views
How to do risk profiling?
I've recently started working on a data center migration project for a large financial services client.
One of the tasks I'm accountable is risk profiling the migration based on the as-is and to-be ...
1
vote
4
answers
3k
views
How can I plan a project that has undefined scope associated with learning new skills?
The client has set (and we have agreed to) the deadline for a project. In order to complete the project, the team needs to master a new tool chain including Selenium and Java.
How do I establish a ...
3
votes
3
answers
431
views
How can we manage schedule risks brought into a project by 3rd party software?
Working in web-development, I face a common situation when clients want to use 3rd party software as a starting point of the project. That could be a CMS, an e-commerce site, or something else. ...
0
votes
4
answers
3k
views
How can I get inexperienced team members to meet project deadlines?
Recently, we have hired bunch of people who say they have little experience on technology. When I delegate jobs to them and ask for a timeline, they give unrealistic timelines of around 3-5 months.
I ...
4
votes
5
answers
594
views
Can story points remain constant between the initial estimate and later planning sessions?
Background
We have a bunch of epic stories.
We have a fixed term to do the project.
We have to get approval from a project board.
We don't know the velocity of the project team yet.
The project ...
3
votes
5
answers
7k
views
Who decides how much work should be included in each Sprint?
Once we have groomed the backlog and have a relatively clear direction of what should be done in short and long term, how do we decide what to include in each Sprint? Who makes that decision?
It ...
2
votes
2
answers
828
views
How should a drastic deviation in overall design be managed in Scrum?
We are starting a Sprint today, first day of a 3-week Sprint. Our requirements from the client are still evolving, so remaining hours are estimated on some unclear values.
How should a deviation in ...
4
votes
4
answers
392
views
Schedule Control
Here's the scenario: You are building a schedule for a project that has a planned duration about three months. You are not concerned about project costs so you will not be doing EV. You are ...
3
votes
4
answers
907
views
What is a good way to set control limits on a schedule?
I want to try to track project progress using Earned Value Management approaches, mainly for my own education rather than out of a pressing need. The metric used to define planned value (PV) and ...
11
votes
3
answers
730
views
How should we plan work on support issues without a "battery"?
We are working on a very old project with a lot of legacy code. This means that we have around 3-5 unplanned issues every Sprint.
We were handling that with "batteries": time set aside for ...
9
votes
16
answers
2k
views
Is planning software necessary? [closed]
Is planning software necessary? Can you plan your project without one?
3
votes
2
answers
184
views
How to deal with inhouse technical group manager?
Regarding to management of a multi-task IT project;
How to deal with technical group manager who risks the completion of the project in time by not respecting weekly work-schedule?
3
votes
2
answers
260
views
Early stage risk/cost/time estimaties when working with unstable/beta software integration
What is the usual way to estimate costs in the first weeks of this kind of high risk projects where there is no specialist knowledge of the technologies you need to use in a development team?
In my ...
11
votes
8
answers
580
views
How can a PM prevent a train wreck in progress?
Our mid-size development team is doing a multi-year project. We always had major technical concerns that were never resolved. Now we find ourselves part of the way over a cliff: the architecture ...
3
votes
4
answers
350
views
Would this be a good way of reporting?
I do not know whether I am reinventing the wheel, but I have never come across the following reporting method.
I imagine that if I was to choose a single metric to report to upper management about a ...
1
vote
2
answers
189
views
What is the Procedure For Handling High Risk Involving Another Team's Conflicting Goals?
I am working on an ongoing project which spans over the course of several years. The project has moved to the stage where the product we're building has customers.
Our management structure is the ...
7
votes
5
answers
11k
views
How to calculate budget margin?
Say a work package (containing several tasks) is estimated to take between 320 (Most likely) and 480 (Worst case) hours of work (not duration) to complete. Because of some dependencies and the ...