Questions tagged [schedule-risk]

For questions about identifying, documenting, communicating, or mitigating risks to a project's schedule.

Filter by
Sorted by
Tagged with
10
votes
3answers
580 views

How should we plan work on support issues without a “battery”?

We are working on a very old project with a lot of legacy code. This means that we have around 3-5 unplanned issues every Sprint. We were handling that with "batteries": time set aside for ...
3
votes
4answers
728 views

What is a good way to set control limits on a schedule?

I want to try to track project progress using Earned Value Management approaches, mainly for my own education rather than out of a pressing need. The metric used to define planned value (PV) and ...
7
votes
5answers
9k views

How to calculate budget margin?

Say a work package (containing several tasks) is estimated to take between 320 (Most likely) and 480 (Worst case) hours of work (not duration) to complete. Because of some dependencies and the ...
0
votes
4answers
2k views

How can I get inexperienced team members to meet project deadlines?

Recently, we have hired bunch of people who say they have little experience on technology. When I delegate jobs to them and ask for a timeline, they give unrealistic timelines of around 3-5 months. I ...
2
votes
6answers
886 views

How to minimize scope creep?

Scope creep can easily transform a good project into a distressed one. What are the methods for minimizing continuous expansion of project requirements?
2
votes
2answers
489 views

How should a drastic deviation in overall design be managed in Scrum?

We are starting a Sprint today, first day of a 3-week Sprint. Our requirements from the client are still evolving, so remaining hours are estimated on some unclear values. How should a deviation in ...
1
vote
1answer
477 views

How to calculate Critical Path including Std Dev for each activity estimate?

When estimating activity durations, you get a duration plus/minus a sigma (standard deviation) for each activity. Afterwards, when you want to determine the critical path, what figure should you ...