Questions tagged [scheduling]

This is for task scheduling or resource allocation questions.

Filter by
Sorted by
Tagged with
0
votes
1answer
357 views

Finish variance in Hours

How can I show the Finish variance column in hours and not days? I am working in MS project Pro 2010. Thank you for your help.
1
vote
2answers
1k views

Is there a theory of management that supports backward/reverse planning?

I have found that project managers/project leaders use this common sense approach to planning. Namely, they already have a deadline, then they set milestones in a backwards order. They apply the same ...
0
votes
1answer
757 views

How can Critical Chain scheduling be undertaken with Microsoft Project 2010?

How can Critical Chain as a scheduling approach be applied using only Microsoft Project 2010 with no add-ins or additional software? What settings and options need to be used, and what task types.
-2
votes
1answer
266 views

Important Concepts In Project Management [closed]

What are the most important concepts that should be added (as notes on ms project)? for example: Defining the project scope, risk management .. what others?
1
vote
2answers
427 views

Adding requirements gathering to the project plan - time phased budget baseline (PMB)

I'm preparing a time phased budget - basically my project schedule with all resources and cost allocated. When its reviewed, I will need to baseline it for calculating variance (tracking) in future. ...
1
vote
3answers
774 views

breaking down WBS in a project plan into activities

I understand that a project plan (schedule) is much more than a WBS task list. It depends on how you organize your project schedule - may be into phases, may be modules. Phases might have overlapping ...
1
vote
2answers
415 views

Actual Start Date in MS Project

I have a problem: I have a schedule that is baselined, constructed using horizontal and vertical logic, constraint free, fixed duration. I have a work package / task that has a FS dependency. The ...
1
vote
2answers
27k views

Activity-on-arrow (AoA) diagram review

so I don't completely understand dummy activities(arrows) in AoA diagrams, so I decided to do some practice questions related to it. I was wondering if anyone have a look at my solution and tell me if ...
0
votes
1answer
212 views

PERT adjust most likely time with probability and duration time

I don't know if the name of the question is clear what I would like to do is: I need to adjust the most likely time for an activity of my project in purpose of the probability of any path through the ...
2
votes
1answer
620 views

Schedule Logic, Use of Leads and Lags

I was recently told that you shouldn't have or minimize the use of leads and lags in your schedule as it somehow affects the calculation of critical path. I do not know if this guidance is limited to ...
1
vote
2answers
3k views

Let MS Project adjust previous dependent tasks' schedule based on last task's due date

I want to tet MS Project adjust previous dependent tasks' schedule based on last task's due date. I'll try to tell my requirement via image below: last row is a milestone (final report) and has a due ...
0
votes
2answers
2k views

What does (Normal time-Crash time=0) implies?

In Crashing a project, if for an activity [Normal time - Crash time = 0], what does it mean? Since Crash cost per day = |(Crash cost-Normal cost)/(Normal Time- Crash time)| The Crash cost per day ...
1
vote
2answers
1k views

Is there any of Special way of showing Tentative Tasks in a Gantt graph using Project Libre?

I'm documenting a Software Web Application Project Plan. The customers have sent us: 1) snapshots of the various Web pages, and 2) Change Request Snapshots of some existing Web pages that we already ...
3
votes
2answers
123 views

What to do when the same project needs to generate two specific products - and product build is not aligned?

We work in a project where we have to build the same game for both Android and iOS platforms. The requirements are the same, but each result in specific products. We use SCRUM in order to keep our ...
1
vote
1answer
133 views

What's the practice to include new subtasks in a project chart?

I am new to project managment. I am trying to apply a task chart for different activities for my personal life as a "project". The chart has different areas, goals, taks, and schedule. Pherhaps you ...
5
votes
1answer
1k views

Linear Programming and PERT charts

I've studyed some Operations Research (maths), as well as some Project Management (for engineers) at Uni. It is fairly well known that directed Graph with weighted edged (such as a PERT Chart, and ...
1
vote
1answer
76 views

How to represent changes on efforts % for a specific resource over different tasks?

Scenario: John Doe is 100% allocated to the task 'vacations' from 01/Dec to 01/Feb. He's doing great (a lot of efforts to wake up at 11AM!), but during 20/Dec to 30/Jan John needs to be 50% '...
5
votes
3answers
137 views

Schedule & Customer Blame

Here are work we are having some difficulty with, well, difficult customers during the implementation phase of a semi-custom SaaS product. Standard story, I guess, ship deliverable's and then nothing ...
5
votes
1answer
7k views

Unable to schedule a 4-hour task completed over 2 days in Gantt Chart

I'm trying to create a detailed Gantt chart, using MS Project 2013, for a project in one of my courses. Being a student, I'm not working the same number of hours every day. For example, I may have a ...
1
vote
1answer
786 views

Scheduling tasks to start today

I have a plan that's broke up into a few stages. I want to schedule the first couple tasks in stage 2 to start as soon as possible, there are no predecessors for these tasks. My tasks in the middle of ...
1
vote
2answers
4k views

Update project plan, rescheduling and dates

I'm trying to understand the update function in MS Project 2010 and I hope you can help. Let's say I have a road-project where I have divided a task in to several activities based on where the task ...
1
vote
5answers
3k views

How can we effectively manage a master project schedule alongside Asana?

Background My team uses Asana for all of our project communications and task management. We're very agile and lean focused and therefore our project plans are changing all the time. We love the ...
2
votes
3answers
2k views

What is the best way to develop a project baseline?

I am conflicted on how to create a baseline for a project. Which of the following scenarios would be considered a "best practice" for creating a project baseline in which to measure progress and get ...
2
votes
2answers
669 views

Early and Late Start

A statement "a plan curve that will be created based on 40% late, 60% early" - does it mean a 40% chances of starting late and a 60% chances of starting early . . . please help me clarify a plan ...
10
votes
4answers
3k views

Participants of sprint planning meeting - Is it essential to involve part-time team members

I'm currently in the process of getting my team in a position to start using Scrum and Sprints within the next couple of weeks - I intend on taking on the role of Scrum Master as long as everyone on ...
1
vote
3answers
4k views

How to not count the duration of non-working days of a calendar in Microsoft Project?

I have a plan in MS Project. I have a resource that can't work 5 days per week, so I have negotiated with him to work just 3 days per week. In the plan, I changed his calendar for Thursday and Friday ...
4
votes
2answers
1k views

For every hour cutting code, how many project hours are spent doing something else?

I work on a large line-of-business legacy application, my projects are very much NOT green field. The dev teams are small, usually 2 developers, 1 system tester, plus part-time PM and BA resources. ...
2
votes
2answers
467 views

Project scheduling based on use cases or technical tasks

We have a web project going on and there are several use cases and we're now busy scheduling the development of the project. We're wondering what the best practices are about scheduling a project. ...
0
votes
1answer
258 views

How can new project managers avoid the pressure of creating schedules that meet deadlines but are not realistic?

I can see some project managers who worked as engineers and programmers in the past suddenly device impractical and insane plans when they become managers. Do they lose sanity even after worked so ...
3
votes
3answers
321 views

Timetabling solution for small tutorial college

I am currently working as a maths teacher at a small tutorial college, which offers one-on-one tuition. There are around a dozen tutors and a dozen students at any one time. Currently timetabling is ...
0
votes
3answers
206 views

What is the effective procedure or process to get the esimate of the Project Managers time on the projects ? [duplicate]

When you estimate for project management i.e PM's role time, do you take a certain % of the total estimate? Can you provide me the process or procedure used in general and how accurate it is?
4
votes
5answers
455 views

Can story points remain constant between the initial estimate and later planning sessions?

Background We have a bunch of epic stories. We have a fixed term to do the project. We have to get approval from a project board. We don't know the velocity of the project team yet. The project ...
1
vote
4answers
255 views

Optimizing scheduling of developers: “who works on what, and when”?

I'm trying to plan the next 9-12 months of development using a Gantt chart. I've input all the tasks, their durations, and their dependencies, and all is well. However, as I assign developers to ...
5
votes
4answers
1k views

How to start my first project?

I'm going to manage my first project that is really a small stream of an even greater project, and my boss said that I could make my own schedule and plans etc. I have a couple of questions, I need ...
12
votes
4answers
9k views

How can I schedule resources across multiple projects?

Drawing from the body and comments of a previous question, what is the best way to schedule simultaneous projects and resources to those projects? For example, in a group of 16 staff, each working on ...
4
votes
4answers
379 views

Schedule Control

Here's the scenario: You are building a schedule for a project that has a planned duration about three months. You are not concerned about project costs so you will not be doing EV. You are ...
4
votes
5answers
991 views

How to determine which project should execute first?

Assuming we have 3 projects for three different clients within an industry. The Concept papers are already approved and will be funded by senior managements. So it's rather in the next step of ...
24
votes
3answers
12k views

In Scrum, how to estimate research stories?

In our Scrum team, when there is uncertainty about a story or the team is not sure about how to implement it, we take up a research story first. Based on the findings of this research story, we are ...
16
votes
4answers
22k views

What is the typical ratio of PM/EM hours to “work” hours in a project?

What is the rule-of-thumb ratio of Project Manager/Engagement Manager time to overall project time (e.g. man-hours for work products) in a project? I'm especially interested in an answer within the ...
12
votes
6answers
2k views

Is there a clear benefit to separating “issues” from “tasks” when working in larger teams?

Is there a clear benefit to separating issue from task when working in larger teams? When working with sizable teams of developers in addition to a number of external clients, QA, and any other form ...
18
votes
5answers
485 views

How should I account for non-coding time when estimating duration of a coding task?

I was wondering whether this approach I am doing to scheduling dev work on a day to day basis is correct. In which I assume that instead that a developer has 8 hours a day to do coding, they actually ...
17
votes
5answers
508 views

How to schedule a team during a time of many holidays, on a project with a tight deadline?

You are assigned a three month duration project at the end of the calendar year that has legal obligation of a finish by Jan 1. The schedule is very aggressive with higher odds missing that date than ...
11
votes
4answers
1k views

Agile/scrum - tracking time spent in current iteration towards stories from the next iteration if all current stories are done

Our team has been slowly trying to go towards agile, and like many other teams, up to this point, the question of "what do we do when we actually finish all commitments?" is fairly new and foreign to ...
12
votes
4answers
691 views

How can I improve a project schedule on a project I took over and complete it on time?

I just took over a project from a Project Engineer and just saw a revised project schedule. The revised schedule shows the project will be delayed by 3 months. I am trying to complete it within the ...
1
vote
1answer
145 views

Canned project breakdown suitable for training interns in scheduling

I'm looking for a project with a well-constrained breakdown that would suitable for training interns in scheduling projects. (The desired context is actually software project scheduling, but I'm ...
24
votes
14answers
4k views

Are 40 hour work-weeks (no overtime) acceptable for development teams?

No matter what our current conditions are, it seems like my team is always working 40 hour work-weeks. Under normal work conditions this would be fine, but as we approach a deadline on a major ...
4
votes
1answer
2k views

How to manage a project schedule based on Late Start dates?

We finished planning a project a month ago and since then have had four formal changes pushing out start dates to the latest possible. Scope change isn't a factor, rather the root cause appears to be ...
10
votes
2answers
2k views

How can I track team member utilization across a range of projects?

I have a fixed-sized team (with fixed-hours) and products, more than the team can handle. At any given time, while my resources are working on one product, requests keep flowing in about work on other ...
3
votes
2answers
119 views

How can an EV be calculated when there are different versions of a project plan?

There is a project manager who is trying to come up with a way to calculate EV under a specific situation where there is a project management system which allows different versions of project plans. ...
9
votes
4answers
394 views

Resources used by multiple PMs

I am the Infrastructure PM on a large project, working as part of a team of PMs with different responsibilities. These include Development, Testing, Environment Support, and Implementation. My remit ...