Stack Exchange Network

Stack Exchange network consists of 175 Q&A communities including Stack Overflow, the largest, most trusted online community for developers to learn, share their knowledge, and build their careers.

Visit Stack Exchange

Questions tagged [scrum]

For questions about using or implementing the Scrum framework.

0
votes
0answers
5 views

Do bugs from previous Sprints need to be estimated?

For example: in Sprint 2, on story, A Tester raises 4 bugs. 2 bugs got fixed in the same Sprint. The remaining 2 were pushed to the Product Backlog. At Sprint 6, we are picking those 2 bugs of story A ...
0
votes
1answer
31 views

Sprint demo feedback

Sprint demos are done at the end of each sprint to the clients. This helps to identify the issues and collect feedback from the clients. I have a question on implementing the demo feedback. Should we ...
1
vote
2answers
47 views

Large group retrospective format

I would like to run a retrospective for a huge amount of people involved in a cross-departmental project. The problem is there are 50 people involved. I was thinking of doing the data gathering, ...
2
votes
1answer
84 views

Does every Scrum story need to be completed at the end of the sprint?

I have worked on teams which, while using Scrum, have fallen either side of this opinion: every story must be complete by the end of the sprint. What is the "official" definition/requirement? I ...
0
votes
1answer
39 views

how to differentiate between epic and story for an already existing software? [duplicate]

How to decide that a requirement will be my epic or user story.I have a few enhancements from the client which cannot be grouped into something.As for example my request is adding a few informative ...
3
votes
3answers
699 views

How to include front end developers and QA into the estimation process?

We are team of 3 Back-end developers, 3 Ios developers, 1 QA, 1 Product Owner and 1 SM, working on a Social App. We are interested to do this using the agile methodology with the Scrum framework. We ...
3
votes
2answers
69 views

User Story versus Task in Jira

I am learning about the agile/scrum process, and currently using it for a 6 month software project at my university. My team is using Jira. I am starting to get confused between the difference ...
4
votes
4answers
833 views

What to do with work not on the board?

TL;DR: At some point, someone on the team will have work which can justifiably not go on the board. How is this handled in a sprint team when it is a long running thing? Our team's technical leader ...
1
vote
1answer
74 views

Scrum Team delivery without hitting commitment

Hi looking for some ideas.... One of my scrum teams is performing and releasing, we have regular deployments but the planning and board does not reflect the work they have done. I'm not sure what ...
2
votes
2answers
71 views

In Scrum, how to handle a functionality that could be used by more than one feature?

Is there a principle in Scrum for packaging the different views of the project into different owners' perspectives, or do I just need to get more practice in picking the pieces I need out of the ...
21
votes
4answers
4k views

Task estimation for PMs who are not developers

While working Agile, how can a PM estimate a task when he/she is not a developer?
2
votes
1answer
31 views

Writing stories for SAP

Perhaps this will get criticised for being technical, but SO seems the wrong place for it. If you are running/involved in a project with SAP developers, how do you/they write stories for it? What do ...
1
vote
2answers
52 views

I'm looking for the name of a spiral chart type used in Scrum

I'm looking for the name of a chart type that (I think) is used in Scrum. It's a spiral where each revolution represents a sprint and the radius at any given point is the amount of work remaining. ...
3
votes
1answer
109 views

Advice on Agile team structure

I’m looking for a little advice…. let me start at the beginning…. My Organisation is very traditional and our organisation structure a little strange. Our web team are part of the marketing ...
5
votes
2answers
201 views

Should all team members be assigned user stories?

This is a very basic question but I don't see any answers on it yet. Scenario: We did sprint planning and I noticed some one saying Not all developers have a task to do. We need to add more tasks ...
2
votes
1answer
70 views

Is Scrum framework or methodology?

As per my understanding, Scrum is a Framework. Following is my view of the Scrum Framework and I would like to hear your ideas as well. The methodology is a set of principles and practices which can ...
4
votes
2answers
689 views

Scrum for SDK development - split stories horizontally?

Our product is moving more and more in the direction of a software development kit (SDK) which can be used by other developers. This brings up quite some challenges to our agile processes, though ...
8
votes
4answers
114 views

How to write a user story involving artistic work?

Using Scrum, what would be the way to define, structure and estimate a user story, containing work for an artist? The main problem that I'm interested here is that an artistic story can take a long ...
4
votes
2answers
273 views

Adding test cases to user stories (Backlog items) before the sizing session

Scenario: I was asked by management if it is a good idea to add test cases to user stories before the sizing session. This will involve investigating the item, writing test cases, speaking to ...
3
votes
2answers
64 views

How to warn if blocking tickets are not in a sprint

We had a recent problem that I would have thought Jira could handle but I can't see where this would work. We are using Jira with scrum/agile. While defining stories we had two stories one larger one ...
5
votes
1answer
96 views

Sprint board critique

We are a DevOps software team with dependencies upon a release process which often requires us to wait before releasing some code to production for up to 5 times longer than our sprint length. This ...
2
votes
2answers
65 views

Is a mid sprint check-in/catch-up a good idea

Scenario: With scrum teams doing a daily stand-up to inform team of progress (yesterday and today) and any impediments. I wonder sometimes do they actually bring up impediments, concerns or issues. ...
3
votes
1answer
76 views

Carrying items over from one sprint to the next

Question: Carrying items over from one sprint to the next Answer: Yes Scenario: I am a new scrum master on a team and we have just completed our first sprint. I was not here when the team planned ...
4
votes
1answer
52 views

How to handle when planned work is blocked and a developer has capacity to take on a new user story that may be too big

Assume the following situation. All but one user story planned in a sprint is completed. The remaining user story is blocked. A developer would like to take on work in the highest priority work ...
2
votes
1answer
35 views

Reflecting external dependencies

We use ServiceNow story boards and one element of this tool is that it provides little coloured dots for representing attributes of stories or spikes. These dots are very limited in number, but our ...
1
vote
2answers
45 views

Advisable scrum columns for software projects

Our software team has essentially these storyboard columns: Backlog To Do Develop Test Done Unfortunately, people inside and outside the team often attempt to affect the board to represent pre- and ...
1
vote
2answers
57 views

What's the name of Knowledge sharing activity within scrum metodology

Suppose you work by scrum and set up special meetings to let developers share their knowledge about technologies / experience of the current project parts / enhance collective code ownership. What is ...
10
votes
4answers
976 views

Demo in Sprint Review

Currently we are following one week Sprint, Post refinement sometimes we encounter few stories which may take more than 1 week time to complete development, integration & Test. This means to ...
3
votes
3answers
126 views

Sprints Starting Mid-Week in Scrum

When people discuss Sprints that start or stop mid-week, they seem to agree that this should be done on a Tuesday or Wednesday. Why is that? Also, how do week-long Sprints with mid-week starts and ...
2
votes
1answer
41 views

How to treat users stories which were almost completed at the previous sprint? [duplicate]

How to treat users stories which were almost completed at previous sprint but didn't meet Definition of Done due to testers were late for some reason. Suppose one of those stories was 5 story points, ...
4
votes
2answers
99 views

Is QA stage mandatory to be included into user story cycle?

The problem I came across: A 2-week Sprint is close to the end (let's say 80% of the time has passed by) A particular user story has just been completed (and has unit tests) What next? Testing takes ...
3
votes
2answers
83 views

Should we add more items to sprint backlog if there is items that are not completed

Question: Should we add more items in a sprint if there is items that are not completed but a developer is open. Scenario: Lets say we the development team are made up of 5 team members and we have ...
2
votes
1answer
59 views

SCRUM and Nexus Frameworks - 1 Team with multiple projects

I work essentially for 3 companies. A development team consisting of members from the 3 different companies will be formed to build 1 related product (w/ several versions). The complex part is that, ...
5
votes
6answers
3k views

Should a Product Owner start testing while an item is in code review

We have a Product Owner (PO) who starts testing while an item is in code review and gives feedback to developers. I see, from the point of view of the PO, that this allows for quicker feedback. ...
1
vote
0answers
25 views

Azure Board (DevOps) Reports

I am looking for out of the box "Scrum" reports (velocity, burn-down, sprint report) that use story points, in the tool Azure Boards/DevOps (formerly known as VSTS). I played with "Analytics Views" ...
2
votes
4answers
151 views

Kanban or Scrum for tough deadline project?

Sorry in advance if my question looks silly, but it's bothered me for quite a long time and haven't found the answer to it yet. I work in an IT outsource company and due to specifics of my job I ...
0
votes
1answer
37 views

Web development project management through Jira Software [closed]

I worked as a software developer and recently I became the manager of some web development projects for clients. Can you please recommended some useful tutorials for web development project management ...
3
votes
3answers
118 views

How to deal with non negotiable change

One of the issues my organisation has is where change requests are requested during a sprint cycle in a particular high volume worksteam. The development team are often forced to accept these change ...
4
votes
5answers
133 views

Should we demo bug fixes in sprint demos?

We have been asked to demo almost all bugs in our sprint demo, except the bugs which were raised for the stories of the sprint. Some teams only demo critical bug fixes, probably to reassure others ...
35
votes
7answers
8k views

Daily standup vs. Micro-management

Why isn't the daily scrum considered to be micromanagement? Under any other circumstances expecting to get a daily update from developers would be considered micromanagement. Maybe even pico-...
5
votes
2answers
102 views

Product Owner in different time zone from scrum team

I am a product owner for a remote scrum team. I am on the east coast of the US. The scrum team is in India. This is a 10.5 hour time difference. I have been participating in their daily scrum at 6:...
4
votes
3answers
191 views

Daily Scrum development member taking too much time

A team member is taking too much time at Daily Scrums. What is the best way to resolve this issue as a Scrum Master? Can I intervene at the Scrum?
3
votes
2answers
73 views

Please advise on my experience for the final month of a project closing

I would like to bring up my story for a closing project to have a discussion on practice as a Scrum Master. At that time I am working as a member in the Development Team roled as a support Engineer ...
4
votes
2answers
97 views

Specifications in spreadsheets vs. stories in JIRA

I think this is a very common issue a lot of companies fight with. So I would like to ask for your input. Product Owners often prefer to keep specifications in Google spreadsheet. And then write user ...
0
votes
1answer
63 views

What magnets for a glass whiteboard? [closed]

What design and strength of magnets are best for a glass whiteboard, used to hold our story cards for daily stand-ups? We have a glass whiteboard, and many magnets fail to stick through the glass, or ...
4
votes
2answers
154 views

Can the Definition of Done be overriden or changed?

Does the Definition of Done come before everything else, almost like a programming interface? And can it be changed if later on, once it’s realized that it was designed poorly? By overriden, I mean ...
1
vote
4answers
122 views

Agile (“Scrum”) “Metrics” Question

My team has recently transitioned from essentially zero project management (other than the "put out fires as they happen while trying to stay on top of current workload") to something more Agile with ...
9
votes
3answers
2k views

How can story points be “non linear” in relative size

I've read in several places that story points are not necessarily linear. i.e., an "8 point" task is not the same as two 4 point tasks and so on. I totally get the argument about these being an ...
2
votes
2answers
60 views

How to correctly define tasks in a user story? And can you split the tasks between sprints?

I'm fairly new to Scrum and I'm working with a group of colleagues on a project to learn more about it. Long story short our project is simply creating a website for tourists of our country where they ...
0
votes
1answer
32 views

Enterprise Mobile-first multi-team-product organization

I am the mobile product owner (PO) at a firm with a dozen or so scrum teams each managing their own web products. My team builds mobile versions of the above web products. I work with each product ...