Questions tagged [scrum]

For questions about using or implementing the Scrum framework.

Filter by
Sorted by
Tagged with
2
votes
4answers
98 views

Can an Epic span multiple versions / releases?

Is an Epic, containing multiple User Stories, allowed to span more than one version or release?
19
votes
2answers
14k views

How to deal with conflicting developers in Scrum team?

I'm a Scrum Master in a project. The development team was merged from two separate teams and now counts 8 people. John and Peter are previous teams leads - very experienced C++ developers, who know ...
7
votes
7answers
2k views

How to convert (volume of work, risk, complexity, uncertainty) to story points?

Disclaimer: I'm a developer, so I don't claim to be thoroughly knowledgeable of agile practices, thus I may not always use the correct words and terms. Please correct me if needed. Agile teams often ...
2
votes
4answers
688 views

Is it the product owner's responsibility to provide requirements around data mapping/transformation?

I'm a full stack software engineer. I have worked at many companies ranging from fortune 100 companies to startups and this issue is something i have heard different points of view on. This is the ...
6
votes
7answers
2k views

What does a QA team do during the development phase of a sprint in Agile Scrum?

I understand that, in theory, QA should be working with dev "collaborating" right from the day 1 of a sprint. But how does it actually work in real life? Let me present two scenarios - Scenario 1 ...
12
votes
6answers
2k views

How to incorporate UX/UI in sprint correctly when mockups are required to estimate a story?

Apologies if the question has already been asked, I couldn't really find the answer when looking around. I'm struggling to figure out a way to handle UX/UI in an agile way. I'd like to be "fully&...
7
votes
3answers
882 views

Are we allowed to move stories to future Sprints during a Sprint?

The Sprint Planning is done and, in the middle of the Sprint, the priority changed. Because of the priority change, the story needs to move to a future Sprint. This is not adding new stories, this is ...
14
votes
3answers
8k views

Why management is more concerned of JIRA hours than of following Scrum values?

As in many other projects, we are also using JIRA to manage tasks and user stories, and Scrum as the Agile methodology. At the end of each day, the ScrumMaster provides the burndown chart to the PMO ...
8
votes
3answers
19k views

User Story versus Task in Jira

I am learning about the agile/scrum process, and currently using it for a 6 month software project at my university. My team is using Jira. I am starting to get confused between the difference ...
-1
votes
3answers
166 views

Different methodologies for Project Management and Software Development

In my current company, they are using Waterfall methodology in defining the gateways for new project approval and developing detailed timeline with completion date (gantt chart). For the development ...
18
votes
11answers
7k views

In Scrum, do we really let people self-organize around their work?

This is what Scrum Guide says about the members of Scrum Team: They are also self-managing, meaning they internally decide who does what, when, and how. But we all know that very often if we would ...
-4
votes
1answer
111 views

Is it possible to be a Scrum Master without any technical experience?

I am an engineering (IT) graduate and right now I am pursuing masters in Computer Science & Engineering. I have teaching experience in computer and engineering fields, but now I am planning to ...
5
votes
5answers
2k views

How to foster more t-shaping within a Scrum team

As a Scrum Master and Agile Coach, how can I foster more t-shaping and elimination of silos within a single team. All the team members are open minded so I am sure they would let me try anything. One ...
7
votes
6answers
406 views

What does team's velocity measure?

Velocity is an average amount of estimated sizes of PBIs completed by Development Team in a Sprint. It's not an average amount of real PBI's sizes completed by Development Team in a Sprint. I don't ...
8
votes
7answers
3k views

Where does Scrum or Agile Manifesto say that we should avoid stages (development, then testing)?

It looks like neither Scrum nor the Agile Manifesto say that the practice when developers write code and then hand it over to testers should be avoided. Or do they?
3
votes
2answers
264 views

How to determine project complete date?

As a project manager, I've already worked on a few tech projects with newly assembled teams every time. The team is usually 2-3 team members doing the actual work. It is hard to determine velocity. We ...
5
votes
1answer
110 views

Are There Case Studies For Hardware and Software On Same Scrum Team?

We're in an automation market. All our projects are heavy on mechanical design, and many (but not all) of those projects include significant electrical and firmware components, with PC software being ...
1
vote
2answers
157 views

ScrumBut: "Developers don't do QA well."

Since arriving at my company, I've come to find that they specifically hire QA Analysts for QA work within sprints across multiple products. I'm aware that this goes against the Scrum Guide which ...
1
vote
2answers
101 views

Where would CI/CD project fit within Scrum?

A development team wants to automate deployment and testing. How would this be placed in the Sprint Backlog? And, how does this relate to Scrum Goal? e.g. CI/CD could be large enough that it could ...
20
votes
14answers
47k views

How do you name Sprints in Scrum?

I was wondering if it's a good idea to name Sprints with user-friendly names instead of using numerals like Sprint 1, Sprint 2, etc. Are there best practices or standards for naming the Sprint after ...
2
votes
7answers
188 views

How to ensure adherence to coding standards

We have a coding standards document that contains standards for SQL. In the last sprint, there were some standards that were missed by the Developer, and also missed by the Reviewer. We just had a ...
1
vote
3answers
193 views

How do you close out a Scrum Sprint in Azure Boards? Especially, what should you do with partially completed user stories and tasks?

I am new to Azure Boards and finding it can be very confusing when it comes to scrum sprint ends and planning the next sprint. What should you do with user stories and their tasks that are only ...
1
vote
1answer
72 views

How to split responsibility of a product page?

In our organisation, the responsibility is divided based on modules. Let's take an example of an auto portal product page where the product page consists of many different modules owned by different ...
6
votes
3answers
1k views

Are development and testing of a feature done at the same time in Scrum?

Let's suppose a Scrum team needs to implement a new feature. Do QA engineers write automated tests for the feature at the same time as developers write code for the feature? In other words, QA ...
0
votes
3answers
87 views

Usable or usefull increments in Scrum?

Two-week Product Increment can be usable, but not very usefull. So does PO need to attend every Sprint Demo? Let's say that a feature is mostly related to adding a new function to a backend. We need a ...
4
votes
2answers
316 views

Best practice: best place to track ad-hoc, ongoing work

I've recently taken over a project from another scrum master. In the backlog there is a 'Feature' called 'Support HW Team' (HW -> Hardware) that has a bunch of vague stories under it and basically ...
5
votes
7answers
205 views

Agile: Work on PBI Stories By Backlog Priority

We are working on an Agile Scrum team. They mention it is good practice to work on PBI tasks first by Sprint Backlog Priority in code development. Sometimes, When some of the first Priority stories ...
5
votes
1answer
83 views

In Scrum how do we maintain a small numer of end-to-end and UI tests (Test Pyramid)?

Scrum Teams often write automated tests for User Story's Acceptance Criteria. So every sprint the number of these tests increases. I suppose that many of these tests use browser testing frameworks ...
14
votes
7answers
46k views

How to calculate sprint capacity?

Let's say the team works 5 days, and there are 3 developers in the team, and they are working 8 hours per day. So actually it is easy to calculate: 5*3*8=120 hours of work per week. But there is ...
-2
votes
3answers
133 views

Question on temporarily allowing a team lead to pause project management to go faster?

Background In our organization, our Scrum Masters are also engineers, and 30% to 50% of their time is organizing the team, backlog, tickets, etc. The last 3-4 weeks we allowed one of these Scrum ...
9
votes
4answers
2k views

Lately discovered requirements in Scrum

If a requirement is discovered in the middle of a project or even later, then the cost of implementation of this requirement can be very high. The Scrum suggets that we should only refine the top PBIs ...
25
votes
6answers
4k views

Which is better: large feature branches or merging frequently? Which is better small work items vs large work items?

My team has problems pushing work items through all the stages in the Kanban board to done. The work items hit code review and pile up and stay there for a long time. The following stage (the QA stage)...
10
votes
4answers
1k views

How is refinement done in Scrum?

Scrum says: Product Backlog items that can be Done by the Scrum Team within one Sprint are deemed ready for selection in a Sprint Planning event. They usually acquire this degree of transparency ...
3
votes
1answer
375 views

Sprint planning, review: velocity,capacity, forecast and how this values relate?

I'm fairly new to Scrum and its sprint planning/retro (etc), our team today was trying to calculate velocity, capacity and forecast for the following sprint, but we just realised that no one actually ...
1
vote
1answer
57 views

Professional Scrum Master I (PSM)

everyone. I just gained the PMP certification, where I already learn something on agile, and now I want to get a certification specialized in agile. I want to start with the Professional Scrum Master ...
2
votes
3answers
72 views

Should we re-estime (reduce) story points of a task that we started but didn't finish last sprint? [duplicate]

I need an advice and it's about the best option to choose in an agile project, here is the situation : A sprint backlog contains between 15 and 20 user stories A the last day of the sprint, we ...
1
vote
1answer
68 views

Can Scrum be used in combination with Step-Wise project planning?

I'm currently reading up on project management and therefore the Step-Wise framework, and I was wondering, Can Scrum be used in combination with Step-Wise project planning? I know that you generally ...
5
votes
5answers
4k views

What are the pros and cons of using Daily Standups?

What are the pros and cons of using Daily Stand-ups? Positive sides of the Daily Scrum I see, but I can't find negatives.
3
votes
2answers
184 views

From a project planning perspective, is it wrong to have one sprint for the API and another sprint for the UI?

I am making an e-commerce project that has a dashboard module. Instead of having one sprint for the dashboard module, my advisor said I should split this module realization into two different sprints: ...
4
votes
4answers
2k views

Calculating project forecasts in Jira

As a Scrum Master, I want to help my Product Owner to make an educated guess of when features in a project will be implemented, in order to communicate with stakeholders so that they can manage Scope. ...
4
votes
2answers
90 views

Planning Poker with differents roles in video game Studio [duplicate]

I work in a video game studio, and I´m running Scrum. The question here is: using Story points, how do the team estimate the Story, if I have a 2d artist, a Game designer and programmers? As you can ...
4
votes
3answers
143 views

Is Task always decomposed from User Story?

I've heard many times that tasks are basically subsets of user stories and they are derived from User Stories, so on the scale of amount of work that is needed to finish them, a Task is always smaller ...
56
votes
7answers
18k views

Why aren't you supposed to report status in standups?

My team has a new scrum master. The old SM always said that standups were about coordination between the team members and not a report to him. Urging us to help each other if one of us ran into ...
6
votes
3answers
2k views

Is a mid sprint check-in/catch-up a good idea

Scenario: With scrum teams doing a daily stand-up to inform team of progress (yesterday and today) and any impediments. I wonder sometimes do they actually bring up impediments, concerns or issues. ...
9
votes
7answers
777 views

When "taking it to the team" should we seek consensus?

Is consensus required for a self-organising team to make a decision? How do we know that a decision is made? When we as Agile Coaches and Scrum Masters servant lead teams and help them make decisions,...
4
votes
3answers
218 views

How to implement unit testing with a small Scrum team without spending half the Sprint unit-testing stories?

We are a very small team (1 front-end developer, 1 back-end developer/solution architect, 1 PM/UX) working in Scrum with 2 weeks Sprints. Up until now, we were mostly working on prototype projects not ...
1
vote
1answer
49 views

How to do Large-Scale Scrum LeSS or Nexus with remote teams?

Disclaimer: I am new to the scaled agile topic. I researched a bit about how to scale scrum -> Scaled scrum/agile frameworks (SAFe vs. Nexus vs. LeSS) comparison and I like the comparably lean ...
8
votes
10answers
2k views

Agile in a reactive organisation?

I am working in an organization as a Scrum Master that is extremely reactive by nature, where the ‘agile’ teams are being given extremely aggressive ‘non-negotiable’ deadlines by senior executives, ...
1
vote
4answers
102 views

The relation between a project and a contract

Let's suppose we're talking about companies that perform some work for customers. This work is usually considered to be a project and is done on a contract basis. It's natural to assume that any ...
3
votes
3answers
6k views

During a Sprint Retrospective, the Development team proposes moving the Daily scrum to only occur specific days. Not daily

I had a question during PSM1 assessment: During a Sprint Retrospective, the Development team proposes moving the Daily scrum to only occur on Specific days of week. Not daily. Which two are the ...

1
2 3 4 5
31