Questions tagged [scrum]

For questions about using or implementing the Scrum framework.

Filter by
Sorted by
Tagged with
30
votes
7answers
27k views

How do you schedule delivery dates in Scrum?

I've run into a constant issue. When a project starts, the client typically has a list of functionalities to be built in to the application. As a team we would like to follow Scrum. But the next thing ...
157
votes
19answers
92k views

Why use story points instead of hours for estimating?

After using hours to estimate our projects for a long time and rarely coming within 20% of actual "work-to-ship," I have been told by a handful of people that "points" work a lot better at gauging the ...
21
votes
6answers
4k views

In scrum should incomplete stories be re-estimated or does the original estimate get burned down when it's finally completed?

If I have a story that's been estimated at 10 story points and we don't manage to complete it in a sprint how do you handle estimates for the sprint in which it's next included (assuming it gets ...
19
votes
3answers
2k views

Handling bugs in the Scrum process?

I have recently gone live with a big project. To meet a tight deadline some technical debt was accumulated but the true extent only became apparent after go live. As this is intended to be a ...
64
votes
5answers
7k views

Is Scrum a status report meeting or a developer meeting?

I'm a developer and we started using Agile last year (October 2011). And, it has been rough to say the least. I was always taught Scrum was to discuss the following: What you did yesterday What you ...
27
votes
7answers
6k views

Why use both story points and hours?

I'm a new scrum master for a team that is using story point estimation and hours. We do story points first during grooming and then hours during planning. I always thought of story points as being ...
24
votes
3answers
11k views

In Scrum, how to estimate research stories?

In our Scrum team, when there is uncertainty about a story or the team is not sure about how to implement it, we take up a research story first. Based on the findings of this research story, we are ...
17
votes
4answers
4k views

Should velocity increase with time?

Some scrum masters are concerned with "bumping up" a team's velocity during a sprint, as if a higher velocity is better. But points are a relative measure of the work that a team needs to do for ...
1
vote
5answers
5k views

Why must we define a Sprint Goal for each Sprint?

As a Scrum Team, we are committed to deliver Product Backlog items per the Product Owner's priority. The team doesn't understand why we should define Sprint Goals. How does that help?
80
votes
11answers
27k views

Why can't the ScrumMaster and the project manager be the same person?

How a ScrumMaster does compare to a traditional project manager, and can either role coincide with the role of product manager or project sponsor / project owner?
34
votes
17answers
3k views

How to allow developers to get enough quality development time while keeping to support & maintenance obligations

I work for a small company of 6 multi-skilled developers where we have developed our own product which requires constant improvement but also maintenance and support, both for the current release from ...
11
votes
3answers
613 views

How should we plan work on support issues without a “battery”?

We are working on a very old project with a lot of legacy code. This means that we have around 3-5 unplanned issues every Sprint. We were handling that with "batteries": time set aside for ...
10
votes
7answers
3k views

Sprint Goal and Failure of a Sprint

My organisation is pushing for strictness on what they consider a Sprint Failure or not. They have decided that if there are any User Stories not fully completed (as per the DoD) at the end of the ...
75
votes
14answers
93k views

When to Use Waterfall, When to Use Scrum ?

Where I lecture, I was always taught to use waterfall to manage projects, but when I finished college, waterfall wasn't the only method that can be used for project management, and I am very ...
65
votes
7answers
21k views

How to deal with unavoidable on-demand tasks in Scrum? Or should we even try?

I was put in charge of implementing Scrum in my Development Team. Unfortunately, the company I work with has a rather stale structure that does not go well with this framework. The team works on a ...
27
votes
7answers
4k views

Scrum, Agile, Kanban looking for 'for dummies' type of information [closed]

I'm sure I'm not alone in this. I have heard and read a lot of snippets of information about this topic and I've formed my own understanding - probably not the best way to assess the value or try to ...
33
votes
4answers
71k views

Which Scrum certification provider is most widely recognized or accepted?

I am planning to go for Scrum Master certification, and while researching the certification providers, I could not clearly make up my mind about which one was most widely accepted. There are two ...
4
votes
2answers
9k views

What to do when mid-sprint, you realize some stories won't be done?

On the seventh day of a two weeks Sprint, we realize that 20 percent of the stories cannot be completed. What is the best action to take? Is it possible/recommended to cancel the iteration on start ...
5
votes
8answers
911 views

What does a QA team do during the development phase of a sprint in Agile Scrum?

I understand that, in theory, QA should be working with dev "collaborating" right from the day 1 of a sprint. But how does it actually work in real life? Let me present two scenarios - Scenario 1 ...
18
votes
9answers
11k views

Managing scope creep in Agile

I often get asked this question in the interview, and no matter what I answer the interviewers do not seem to get satisfied. So, they start with asking how to manage scope creep in Project Management?...
36
votes
9answers
3k views

Strict or pragmatic Scrum?

Do you practice Scrum strictly after its rules or are you going a more pragmatic way, picking out the bits that suit you/your environment best, maybe mixing it up with other methodologies ? In other ...
11
votes
3answers
16k views

Can we add more user stories to the Sprint Backlog if the requirements change during a sprint?

We are currently working on a project where we receive a lot of change requests, and the client insists that we should deliver the changes in the current sprint! Can I add the new work to the sprint ...
4
votes
4answers
4k views

Agile “user story” for a user-less project

Disclaimer: I'm a total agile newbee. As a project manager for a pilot agile project, I am trying to create a rough sketch of my project using agile methodologies, but somehow I am not sure how to do ...
5
votes
3answers
974 views

How to handle tasks from previous Sprint on current Sprint Burn down chart

Let's say a project has 2 or more Sprints and for each sprint you are using a burn down chart to track the Sprint progress. If at the end of the first Sprint there are tasks that have been started but ...
7
votes
3answers
1k views

What are the right conclusions to draw from the success or failure of a Sprint?

I recently encountered the opinion that, if a Sprint is successful due to statistical reasons (e.g. the team made big mistakes during planning but the team delivered its stories anyway), then that's ...
5
votes
3answers
431 views

How do we deal with bugs in scrum environment

We recently began working on Scrum with one of our products. Prior to that we worked with a Waterfall methodology. We have created stories for the new feature and also included the bugs for the next ...
4
votes
3answers
700 views

Is there a relationship between technical debt and velocity?

Per my understanding, velocity is just a metric used to forecast work for future sprints, therefore it has no significance other than for planning purposes. Even if technical debt exists, my ...
8
votes
4answers
11k views

Scrum on maintenance. Is it possible?

God bless, I never had a lot of deal with maintenance. But I am curious, is it possible to customize Scrum for maintenance? If yes, how to guarantee SLA (if developers have a fixed Sprints), for ...
25
votes
4answers
9k views

How do handle adhoc work during a sprint from pressing customers

I intend to introduce sprints to my company, fairly new to it myself. Not sure if it's appropriate for my current situation, we have several on going projects, all of them are ERP scale size and most ...
24
votes
5answers
19k views

How to make Scrum of Scrums meetings more productive?

At my job, we're having a Scrum of Scrums meeting where all the Scrum Masters get together. This meeting is turning into a boring meeting where everyone gives their status update. I'm trying to make ...
33
votes
7answers
6k views

Advice for dealing with a cowboy programmer in an agile team

We have a cowboy coder in our team i.e. he likes to take advantage developing some new features or tools that are not always requested nor useful. We use scrum/kanban for development, and it is quite ...
17
votes
5answers
12k views

How to timebox Spikes using story points?

My original question was raised here: In Scrum, how to estimate research stories? and as suggested by @CodeGnome I created a separate question. In my opinion Spikes should be time-boxed as there is ...
14
votes
4answers
3k views

Tracking external dependency stories

Say you have three projects. Two of these projects are end-user facing products (Project A and B). The third is an infrastructure project (Project I) where all the work will never be directly ...
18
votes
2answers
16k views

What does “Architectural Spike” mean?

What does Architectural Spike mean? I know, that this is investigation activity for unknown and unestimated tasks. But I want know more details. When we should do it: during Sprint or between them? ...
8
votes
4answers
2k views

Aren't stakeholder expected to adopt an agile mindset when working in a Scrum framework?

What is expected of the stakeholders when it comes to being agile? Since collaboration is at the heart of agile, shouldn't the adoption of agile values be present on both sides? As per my ...
6
votes
5answers
12k views

How to estimate accurate velocity when team members are on leave

I am a Scrum Master of a team with 12 members. I know that the size of the team is large at this point, but as we grow further we will divide the team into multiple Scrum Teams. Our estimations for ...
19
votes
7answers
10k views

What are developers expected to do during testing in the latter half of each Sprint?

When you are using the Scrum framework, a Sprint cycle involves development and QA. At the end of the Sprint the tasks worked upon and tested are showcased and released. Typically, for a team of 3 to ...
14
votes
6answers
6k views

Should a Scrum Master also perform a functional manager role?

We're trying to plan for agile transformation soon, and one of the main sticking points in this is organizational structure. Management's expectation is to have a Scrum Master perform all normal ...
12
votes
3answers
3k views

In our Agile/Scrum team, should we move or split incomplete stories?

Our Agile/Scrum teams are getting better at taking on manageable workload and completing them fully. However, sometimes for a variety of good reasons, some of the stories are not fully done at the end ...
8
votes
2answers
308 views

In Scrum, what should we do with partly-completed work started at the end of a Sprint?

I get most of Scrum. However, I can't get my head around what to do with work in progress at the end of a Sprint. If we are working in a swarm, we can defer the end of a Sprint, or bring it forward ...
6
votes
3answers
752 views

What we should do with tasks which estimated time bigger than sprint?

I know, we need to separate this task to several subtasks. But what we should do, if further division of this task have no sense? What if all of resulting subtasks will have no business value until ...
11
votes
5answers
2k views

Where does documentation like business and software requirement spec docs fit in an agile project?

We are implementing scrum in our company. The problem we faced is our traditional thinking, which always requires physical document. Management is constantly asking for documents like Business ...
7
votes
1answer
282 views

Aligning story points' value

We've ended up with non-linear weighing of our points. I worry this makes reporting velocity data erroneous. Background: A fairly traditional deck is used: ?, 0, ½, 1, 2, 3, 5, 8, 13, 20, 40, 100, ...
7
votes
4answers
7k views

What is an impediment, and how to handle them and internal improvments in Scrum?

What exactly is an impediment? I know that Scrum say that and impediment is something that stop the team from performing the best it can. So basically it can be everything? But where goes the magical ...
5
votes
5answers
1k views

Can you change the end date of a sprint?

Ideally we commit to work being completed and releasable by the time the sprint finishes. However sometimes things happen or estimating is a little bit out. If we are approaching the end date of a ...
2
votes
3answers
1k views

How do I capture details in a user story?

Suppose I have a user story like: As a customer, I am able to browse products by specifying a category. If the Product Owner wishes to list the types of categories available such as books, ...
0
votes
1answer
204 views

how to execute sprint effectively?

How to execute sprint effectively? If my story is developed , tested i.e. unit + acceptance + regression, all the bugs are resolved i.e. even low bugs then only developer take on another story? Or we ...
50
votes
14answers
81k views

Where to Find a Desktop Kanban board application? [closed]

I have been looking for a week now, all over the net for a simple desktop based kanban management system. I work in a distributed team, but my company won't accept to use an exterior webapp like ...
42
votes
14answers
24k views

Should bugs be treated as stories or as tasks?

If you're using scrum you should know that there is a clear difference between tasks and stories. A story is something that is valuable to user. A task is a step to produce that value to user. So, ...
23
votes
6answers
15k views

Where should design be incorporated in an agile process?

We use a scrum-based agile development process. But where should design get incorporated? Separate user stories? Tasks on stories? We currently think of design as a separate task and break it out as ...

1
2 3 4 5