Stack Exchange Network

Stack Exchange network consists of 174 Q&A communities including Stack Overflow, the largest, most trusted online community for developers to learn, share their knowledge, and build their careers.

Visit Stack Exchange

Questions tagged [sprint-backlog]

The sprint backlog is the list of work the development team must address during the next sprint. It's commonly known with Scrum.

3
votes
2answers
53 views

Should we add more items to sprint backlog if there is items that are not completed

Question: Should we add more items in a sprint if there is items that are not completed but a developer is open. Scenario: Lets say we the development team are made up of 5 team members and we have ...
5
votes
3answers
101 views

Should User Stories be divided if they're not Done and the Sprint is almost over?

I have a user story for a login screen. It is in the active sprint. Part of it (andriod platform) cannot be done any time soon. The Sprint is almost over. What can I do? Should I divide the user ...
4
votes
3answers
94 views

Can the Scrum Master groom the Sprint Backlog?

Our company is migrating to Scrum. I've been thrust into the role of Scrum Master (with no formal training--but I'm working on that). Our team doesn't have a product owner due to the structure of our ...
3
votes
3answers
118 views

Should a technical person take part of the user stories prioritization process?

As a Tech Lead within a "Scrum" team, I am annoying regarding some laid rules. It is established that only Product Owner, Business Analyst and Scrum Master (and eventually Product Manager) take part ...
0
votes
3answers
69 views

Small story got bigger, what to do with the big bit?

Under Scrum, we have a story which was estimated to be quite short. Once the story was picked up by a developer, it turned out that a significant amount of technical preparation is required, and this ...
0
votes
1answer
105 views

Project manager dumps all tickets in sprint

I have a project manager who's managing a sizable project (8 developers, duration over 6 months) with rapidly and constantly changing requirements. The PM has started dumping hundreds of tickets into ...
5
votes
4answers
214 views

How to deal with tasks detalization in sprint planning?

I have a newbie question. Let's suppose that for a sprint backlog we choose one user story from product backlog: "As a photography junky I want to be able to make a collection of favorite photos". ...
0
votes
3answers
107 views

Scrum: Sprint backlog

I've an ongoing project with very tight deadline. I'm allowed to extend project deadline, if required. I've implemented Scrum (sprints) for day-to-day activities. Issue is - I've some backlog since ...
4
votes
4answers
733 views

Best (most agile) way to develop multiple products concurrently

I would like to restructure my development teams so that they can work in a more agile way, however each of those teams needs to develop changes for multiple products in their business area. I've ...
6
votes
2answers
798 views

T-Shirt Size and total estimation, how to manage them?

I'm working on a project and the Product Owner has to decide if and how many new game-features implement in a SmartPhone app. Those game-features have the goal of keep the user more active inside the ...
4
votes
3answers
562 views

How can we fix Sprint Planning meetings that are unproductive?

Currently, we have split "Sprint Planning Meeting" into two parts: SPM1 - This we do at the first day of the sprint. Product owner discusses the stories that have come into the current sprint from ...
-1
votes
4answers
276 views

What to do if a developer is waiting on a colleague to complete his side of the story during a sprint?

So today I was managing my team and they are in the middle of a sprint, I went over to my dev team just to find out how they are getting on. Turned out that one of my developers was waiting on his ...
1
vote
4answers
1k views

What to do if a member of a team finishes all his sprint tasks ahead of schedule?

I run 1 week sprints, lately my sprints are finishing ahead of schedule (one day before the end of the sprint) for one member of the team. I know that some PMs wait until the next sprint cycle, ...
0
votes
2answers
306 views

Who should attend Sprint Replanning?

It is clear that in Sprint Planning the Product Owner has to be present. However, since the Development Team is responsible for current sprint work, does the PO need to attend Replanning? Although the ...
10
votes
7answers
4k views

Who truly prioritizes the product backlog? The Product Owner or Team?

I keep reading that during Product Backlog Grooming the development team meets with the PM and the Product Owner and as a team prioritizes the features. Is it ultimately the Product Owner who decides ...
2
votes
3answers
1k views

Ineffective Backlog Grooming and Sprint Planning

I suspect that the problems on Scrum teams in my current organization supersede this one aspect, but wanted to focus the question more specifically to how Scrum can be done better than it is currently ...
7
votes
4answers
1k views

Should sprint backlog have MoSCoW prioritization applied?

Scrum states that the team should commit to delivering the stories in the sprint backlog. It is implied that once they have reached this limit, no more items are added to sprint backlog. Should the ...
2
votes
3answers
1k views

User Stories structure for architectural requirenments

Once all user stories are written down for functional requirements, we still need to define some other requirements as communication with a remote server or navigation. This whole process could be ...
0
votes
3answers
164 views

Making burndown chart with 4 sprint

We are in a group of 3 students in computer science, and we are making a website for our customer. First, we make a design for the website, and it took us 2 weeks to finish it. We converted it into ...
2
votes
5answers
2k views

Which strategies I can use to handle tickets during a scrum sprint?

My 4 man team directly handle most technical tickets, with a SLA from 8 hours to 24 office hours, means that during a sprint we must add these tickets in top of our current sprint backlog. We have one ...
4
votes
2answers
370 views

Who plans the items for an iteration/sprint?

In DAD (Disciplined Agile Delivery), who is responsible when for moving work items from the release backlog to the iteration/sprint backlog? I'd say that this is done by the scrum master during the ...
1
vote
3answers
284 views

What to do with the Sprint backlog tasks that we have decided are not needed any more

Can anybody answer my question here? I have estimated for 5 to 6 tasks like analysis (4 hrs), design (3 hrs), logical review (1 hr), peer review (1 hr), unit testing (1 hr), coding (2 hrs) and release ...
4
votes
3answers
642 views

Committing the Product Owner to a sprint backlog with a contract

A short introduction to the question: I'm a Scrum Master in a small web development organization (10 employees) and we do a lot of projects that'll last for 3 or 4 sprints, with an average duration of ...
1
vote
4answers
166 views

When to consider multiple PBIs when determining the HOW?

Consider that we have 10 Product Backlog Items (PBIs) that have been estimated and, if all goes well, will make it into our next sprint, after Sprint Planning. At what point would it be appropriate ...
1
vote
3answers
341 views

Defining user story in Scrum: how specific must they be? [duplicate]

As the title suggests: for example, the following user story too generic? "A registered user wants to login in order to use the site's services" Or, should I use more detailed user stories, like ...
4
votes
4answers
5k views

Can we use only one Scrum board for a team with multiple projects?

I am doing research for school. My research is covering how we could have one Scrum board for one team that works on multiple projects simultaneously. Scrum methodology is not just for working on one ...
3
votes
2answers
695 views

Which guidelines are applicable for a single Scrum Team managing multiple backlogs?

Does the Agile community have recommended processes for a single Scrum Team managing tasks coming in from multiple backlogs? Context and Problem One Scrum Team One Scrum Master Delivering value to ...
0
votes
2answers
188 views

In Jira where to login hours for tasks that is not part of sprint [closed]

There are some subtasks and their hours need to be tracked. They are not directly related to Sprint work but indirectly related to Sprint. There are not related to particular story so they cannot be ...
1
vote
6answers
1k views

Estimate hours of work for every user story

In Scrum, is it mandatory to estimate the amount of hours needed to finish every user story before putting it in the Sprint? Or should we use planning poker and use points instead of hours?
3
votes
2answers
2k views

How is sprint backlog prioritized?

I've read some articles and questions, but didn't come up with an answer. There's a number of different opinions about it. Some say, development team should make a decision on this matter to achieve ...
2
votes
1answer
2k views

In JIRA, is it possible to have items show up in a project backlog but not show up in a sprint's column?

I've set up workflows, workflow schemes, issue type schemes, and everything else required to get a project through my customized steps from new idea to live release. The default behavior of "Agile" ...
8
votes
3answers
12k views

Can we add more user stories to the Sprint Backlog if the requirements change during a sprint?

We are currently working on a project where we receive a lot of change requests, and the client insists that we should deliver the changes in the current sprint! Can I add the new work to the sprint ...
2
votes
2answers
201 views

Should we take a photo of our Sprint Board every day for a remote manager?

A new manager just came on board in another region and asked us to take a photo of our Sprint board and post it to our wiki every day. The question is: should we do this? If yes, by the Team, Scrum ...
4
votes
2answers
428 views

Can a sprint be composed of vertical slices of functionality across multiple 'projects'?

Our company is doing some Scrum experimentation, and I have a quick question about what exactly a sprint should be composed of. After the sprint planning meeting, we settled on three different ...
5
votes
2answers
5k views

Is it accepted practice to group user stories by epics in the sprint backlog?

I have a sprint backlog with about 50 user stories that can be broken down into 7 epics. However, each epic is only partially represented in the current sprint. For example, one of the epics is ...
18
votes
3answers
36k views

Sprint Backlog vs Product Backlog

I was always under impression that Sprint Backlog is part of Product Backlog -> it's impossible to add anything into Sprint Backlog without affecting Product Backlog However, according to one of the ...
12
votes
4answers
1k views

Managing a Product Owner in a not-yet-agile organization

When my company was acquired, my 20-person development team gained a Product Owner who is energetic, engaged, and extremely idealistic. While many of the programmers on our team are familiar with ...
4
votes
4answers
8k views

How should the Product Owner prioritize the backlog?

Should the Product Owner prioritize the backlog side-by-side with the customer? Must this step be done during the Sprint Planning Meeting, or could it be done before the meeting? Is the meeting ...