Questions tagged [sprint-backlog]

The sprint backlog is the list of work the development team must address during the next sprint. It's commonly known with Scrum.

Filter by
Sorted by
Tagged with
0 votes
0 answers
14 views

One Item Type per One Sprint Backlog

Does more than one items of dissimilar type (but related to production i.e. To carry out event successfully here) be worked during one sprint backlog? Or one items (of one type) can only be worked ...
user avatar
0 votes
2 answers
49 views

Estimating values in Sprint Backlog

How is value (in a scale of 1-10) assigned in Estimate of Value calculated (For instance as shown in figure below) in Product Backlog in Scrum Process?
user avatar
0 votes
0 answers
39 views

Planning an event program using scrum process

Scrum process consists following steps for product development: (1)Product Backlog (2) Sprint Backlog (3) Sprint review & (4) Scrum Retrospective. The sprint backlog tables for product development ...
user avatar
  • 1
0 votes
2 answers
86 views

How to properly add or manage a repeated User Story in Auzre DevOps's backlog?

A user story needs to happen each sprint, and I want it to handle it properly - whatever that may mean - within Azure DevOps. I am used to adding user stories for single-issue tickets but have never ...
user avatar
0 votes
2 answers
63 views

Review of sprint board during the sprint session?

What is the name of the session that the scrum master and PO during the sprint review the sprint board to see and the progress, update the status of the tickets and sometimes include some team members ...
user avatar
  • 131
1 vote
1 answer
62 views

Showing interdependency of items in backlog

In cases where we have two stories dependent on the same task, is there a way to show the dependency besides adding a comment in the stories? Additionally, in cases with multiple dependencies that are ...
user avatar
  • 131
2 votes
5 answers
217 views

Should user stories be delivered orally?

I have studied software engineering and learned a decent amount about requirements engineering. I also took a course in Scrum. I've now worked at several different companies, and so far, I haven't ...
user avatar
  • 23
1 vote
3 answers
113 views

Should we re-estime (reduce) story points of a task that we started but didn't finish last sprint? [duplicate]

I need an advice and it's about the best option to choose in an agile project, here is the situation : A sprint backlog contains between 15 and 20 user stories A the last day of the sprint, we ...
user avatar
  • 111
0 votes
2 answers
101 views

Acceptance Criteria, Given/When/Then format demote readability of user story?

I'm creating Acceptance Criteria for user stories. Since it seems to be the main way to do it in my current company. I feel that Given/When/Then always demote user story's readability and increase ...
user avatar
  • 153
1 vote
7 answers
714 views

Are User Stories from Sprint Backlog assigned to individual developers?

Let's suppose the development team is planning the next Sprint. What does it technically mean that a User Story is added to the Sprint Backlog? Is it assigned to a developer or to the whole team? (If ...
user avatar
  • 2,701
2 votes
5 answers
292 views

Backlog Grooming

I have a question regarding backlog grooming. I have completed product prioritization using MoSCOW method. I have it prioritized it as follows. I have rationalized it working with client and gathering ...
user avatar
  • 81
0 votes
1 answer
90 views

When should be done Backlog Refinement Meeting? [closed]

I am a new PO so please help me or guide to understand this better. Per Scrum Guide, I do Sprint planning, my o/p is sprint goal and sprint backlog. I already come to the meeting with PBs and user ...
user avatar
  • 81
3 votes
3 answers
991 views

Can a story be put on hold within a Sprint?

The team is working with a user story and they are stuck on some technical issues and unable to resolve them. This story is committed for the current Sprint. Shall I put this story on hold after ...
user avatar
  • 321
0 votes
1 answer
442 views

Some of the epics are shown on the active Sprint view, I'm not able to remove them

For some reason some of the epics are displayed as swimlanes on active Sprint view. Board filter, sorting config are fine. Any ideas?
user avatar
  • 1
8 votes
2 answers
508 views

In Scrum, what should we do with partly-completed work started at the end of a Sprint?

I get most of Scrum. However, I can't get my head around what to do with work in progress at the end of a Sprint. If we are working in a swarm, we can defer the end of a Sprint, or bring it forward ...
user avatar
1 vote
1 answer
80 views

How to structure backlog and ceremonies around a team with separate skillsets working from a backlog which is not directly connected

I have a team of engineers who are building a data intelligence capability for the organisation. As such the team members are I-shaped and the work is I-shaped i.e. 1 team member can only work from 1 ...
user avatar
  • 2,291
3 votes
3 answers
866 views

User Story breakdown - Technical Task + User Feature

My team is building a web application that has the following high-level user story: As a user, I would like the ability to bulk exclude components from a given country. The work breaks down into ...
user avatar
2 votes
1 answer
279 views

Sprint demo feedback

Sprint demos are done at the end of each sprint to the clients. This helps to identify the issues and collect feedback from the clients. I have a question about implementing the demo feedback. Should ...
user avatar
5 votes
2 answers
311 views

Should we add more items to sprint backlog if there is items that are not completed

Question: Should we add more items in a sprint if there is items that are not completed but a developer is open. Scenario: Lets say we the development team are made up of 5 team members and we have ...
user avatar
  • 784
5 votes
3 answers
267 views

Should User Stories be divided if they're not Done and the Sprint is almost over?

I have a user story for a login screen. It is in the active sprint. Part of it (andriod platform) cannot be done any time soon. The Sprint is almost over. What can I do? Should I divide the user ...
user avatar
5 votes
3 answers
452 views

Can the Scrum Master groom the Sprint Backlog?

Our company is migrating to Scrum. I've been thrust into the role of Scrum Master (with no formal training--but I'm working on that). Our team doesn't have a product owner due to the structure of our ...
user avatar
3 votes
3 answers
240 views

Should a technical person take part of the user stories prioritization process?

As a Tech Lead within a "Scrum" team, I am annoying regarding some laid rules. It is established that only Product Owner, Business Analyst and Scrum Master (and eventually Product Manager) take part ...
user avatar
  • 271
0 votes
3 answers
102 views

Small story got bigger, what to do with the big bit?

Under Scrum, we have a story which was estimated to be quite short. Once the story was picked up by a developer, it turned out that a significant amount of technical preparation is required, and this ...
user avatar
  • 905
1 vote
1 answer
156 views

Project manager dumps all tickets in sprint

I have a project manager who's managing a sizable project (8 developers, duration over 6 months) with rapidly and constantly changing requirements. The PM has started dumping hundreds of tickets into ...
user avatar
  • 113
4 votes
4 answers
918 views

How to deal with tasks detalization in sprint planning?

I have a newbie question. Let's suppose that for a sprint backlog we choose one user story from product backlog: "As a photography junky I want to be able to make a collection of favorite photos". ...
user avatar
  • 143
1 vote
3 answers
187 views

Sprint backlog before going further with project

I've an ongoing project with very tight deadline. I'm allowed to extend project deadline, if required. I've implemented Scrum (sprints). Issue is - I've some backlog since one weeks, that I couldn't ...
user avatar
  • 549
6 votes
4 answers
4k views

Best (most agile) way to develop multiple products concurrently

I would like to restructure my development teams so that they can work in a more agile way, however each of those teams needs to develop changes for multiple products in their business area. I've ...
user avatar
5 votes
2 answers
2k views

T-Shirt Size and total estimation, how to manage them?

I'm working on a project and the Product Owner has to decide if and how many new game-features implement in a SmartPhone app. Those game-features have the goal of keep the user more active inside the ...
user avatar
  • 379
3 votes
3 answers
1k views

How can we fix Sprint Planning meetings that are unproductive?

Currently, we have split "Sprint Planning Meeting" into two parts: SPM1 - This we do at the first day of the sprint. Product owner discusses the stories that have come into the current sprint from ...
user avatar
  • 248
-1 votes
4 answers
850 views

What to do if a developer is waiting on a colleague to complete his side of the story during a sprint?

So today I was managing my team and they are in the middle of a sprint, I went over to my dev team just to find out how they are getting on. Turned out that one of my developers was waiting on his ...
user avatar
  • 3,858
1 vote
4 answers
3k views

What to do if a member of a team finishes all his sprint tasks ahead of schedule?

I run 1 week sprints, lately my sprints are finishing ahead of schedule (one day before the end of the sprint) for one member of the team. I know that some PMs wait until the next sprint cycle, ...
user avatar
  • 3,858
0 votes
2 answers
745 views

Who should attend Sprint Replanning?

It is clear that in Sprint Planning the Product Owner has to be present. However, since the Development Team is responsible for current sprint work, does the PO need to attend Replanning? Although the ...
user avatar
13 votes
7 answers
13k views

Who truly prioritizes the product backlog? The Product Owner or Team?

I keep reading that during Product Backlog Grooming the development team meets with the PM and the Product Owner and as a team prioritizes the features. Is it ultimately the Product Owner who decides ...
user avatar
  • 407
3 votes
3 answers
2k views

Ineffective Backlog Grooming and Sprint Planning

I suspect that the problems on Scrum teams in my current organization supersede this one aspect, but wanted to focus the question more specifically to how Scrum can be done better than it is currently ...
user avatar
7 votes
4 answers
3k views

Should sprint backlog have MoSCoW prioritization applied?

Scrum states that the team should commit to delivering the stories in the sprint backlog. It is implied that once they have reached this limit, no more items are added to sprint backlog. Should the ...
user avatar
2 votes
3 answers
4k views

User Stories structure for architectural requirenments

Once all user stories are written down for functional requirements, we still need to define some other requirements as communication with a remote server or navigation. This whole process could be ...
user avatar
1 vote
3 answers
206 views

Making burndown chart with 4 sprint

We are in a group of 3 students in computer science, and we are making a website for our customer. First, we make a design for the website, and it took us 2 weeks to finish it. We converted it into ...
user avatar
3 votes
5 answers
4k views

Which strategies I can use to handle tickets during a scrum sprint?

My 4 man team directly handle most technical tickets, with a SLA from 8 hours to 24 office hours, means that during a sprint we must add these tickets in top of our current sprint backlog. We have one ...
user avatar
  • 133
4 votes
2 answers
751 views

Who plans the items for an iteration/sprint?

In DAD (Disciplined Agile Delivery), who is responsible when for moving work items from the release backlog to the iteration/sprint backlog? I'd say that this is done by the scrum master during the ...
user avatar
  • 259
1 vote
3 answers
378 views

What to do with the Sprint backlog tasks that we have decided are not needed any more

Can anybody answer my question here? I have estimated for 5 to 6 tasks like analysis (4 hrs), design (3 hrs), logical review (1 hr), peer review (1 hr), unit testing (1 hr), coding (2 hrs) and release ...
user avatar
5 votes
3 answers
850 views

Committing the Product Owner to a sprint backlog with a contract

A short introduction to the question: I'm a Scrum Master in a small web development organization (10 employees) and we do a lot of projects that'll last for 3 or 4 sprints, with an average duration of ...
user avatar
2 votes
4 answers
209 views

When to consider multiple PBIs when determining the HOW?

Consider that we have 10 Product Backlog Items (PBIs) that have been estimated and, if all goes well, will make it into our next sprint, after Sprint Planning. At what point would it be appropriate ...
user avatar
1 vote
3 answers
617 views

Defining user story in Scrum: how specific must they be? [duplicate]

As the title suggests: for example, the following user story too generic? "A registered user wants to login in order to use the site's services" Or, should I use more detailed user stories, like ...
user avatar
  • 277
5 votes
4 answers
8k views

Can we use only one Scrum board for a team with multiple projects?

I am doing research for school. My research is covering how we could have one Scrum board for one team that works on multiple projects simultaneously. Scrum methodology is not just for working on one ...
user avatar
  • 193
4 votes
2 answers
1k views

Which guidelines are applicable for a single Scrum Team managing multiple backlogs?

Does the Agile community have recommended processes for a single Scrum Team managing tasks coming in from multiple backlogs? Context and Problem One Scrum Team One Scrum Master Delivering value to an ...
user avatar
  • 4,046
0 votes
2 answers
200 views

In Jira where to login hours for tasks that is not part of sprint [closed]

There are some subtasks and their hours need to be tracked. They are not directly related to Sprint work but indirectly related to Sprint. There are not related to particular story so they cannot be ...
user avatar
3 votes
6 answers
2k views

Estimate hours of work for every user story

In Scrum, is it mandatory to estimate the amount of hours needed to finish every user story before putting it in the Sprint? Or should we use planning poker and use points instead of hours?
user avatar
  • 277
3 votes
2 answers
4k views

How is sprint backlog prioritized?

I've read some articles and questions, but didn't come up with an answer. There's a number of different opinions about it. Some say, development team should make a decision on this matter to achieve ...
user avatar
  • 133
3 votes
1 answer
2k views

In JIRA, is it possible to have items show up in a project backlog but not show up in a sprint's column?

I've set up workflows, workflow schemes, issue type schemes, and everything else required to get a project through my customized steps from new idea to live release. The default behavior of "Agile" ...
user avatar
  • 163
12 votes
5 answers
21k views

Can we add more user stories to the Sprint Backlog if the requirements change during a sprint?

We are currently working on a project where we receive a lot of change requests, and the client insists that we should deliver the changes in the current sprint! Can I add the new work to the sprint ...
user avatar
  • 251