Stack Exchange Network

Stack Exchange network consists of 175 Q&A communities including Stack Overflow, the largest, most trusted online community for developers to learn, share their knowledge, and build their careers.

Visit Stack Exchange

Questions tagged [sprint-planning]

The tag has no usage guidance.

11
votes
3answers
1k views

Selecting user stories during sprint planning

When selecting user stories from the prioritized product backlog during sprint planning, is it more important to make sure that we end up with our predicted velocity in story points or that we choose ...
1
vote
1answer
65 views

Need help for sprint planning when tasks are not done in previous sprint

In our team we don't have dedicated Scrum Master so one of the developer is playing the role of SM. I know this is wrong but it can't be changed. In out system, we assign story points to all the ...
4
votes
2answers
138 views

Slicing User Stories

I have few queries on how granular we need to go on splitting stories. We have a story where clicking the phone no in the system should dial cisco or skype or any other telephony systems based on the ...
4
votes
4answers
786 views

Story Points flaw?

Forgive me f this has been asked before, I read some similar questions (linked below), but didn't find the answer I was looking for. Our team is fairly new to them and trying to figure out how to ...
5
votes
2answers
232 views

Should all team members be assigned user stories?

This is a very basic question but I don't see any answers on it yet. Scenario: We did sprint planning and I noticed some one saying Not all developers have a task to do. We need to add more tasks ...
5
votes
1answer
98 views

Sprint board critique

We are a DevOps software team with dependencies upon a release process which often requires us to wait before releasing some code to production for up to 5 times longer than our sprint length. This ...
4
votes
1answer
61 views

How to handle when planned work is blocked and a developer has capacity to take on a new user story that may be too big

Assume the following situation. All but one user story planned in a sprint is completed. The remaining user story is blocked. A developer would like to take on work in the highest priority work ...
3
votes
3answers
165 views

Sprints Starting Mid-Week in Scrum

When people discuss Sprints that start or stop mid-week, they seem to agree that this should be done on a Tuesday or Wednesday. Why is that? Also, how do week-long Sprints with mid-week starts and ...
3
votes
2answers
76 views

Architecture task as sprint issues

I understand spikes as being investigation tasks when there is an uncertainty about how a story should be done but my question is more about how to include a software architecture task in a Sprint. ...
8
votes
4answers
2k views

Planning a sprint after reduced team strength

We have seven people team and their running velocity is ~50 points(2 weeks sprint). Now due to change in business focus, we have to reduce team size from 7 to 4. How do we plan current sprint? ...
4
votes
1answer
449 views

Hot swapping stories

Is it acceptable to swap out stories from the current sprint to the backlog and replace them with stories of the same estimate size from the backlog, because of changing priorities in the business? ...
3
votes
3answers
279 views

How to manage technical conflict between Product Owner and developers?

Imagine you are a Product Owner. And you have planned a sprint, prepared every detail, broken down the epics into stories and already presented your roadmap to management and promised the releases ...
11
votes
4answers
2k views

What should we do if there are not enough PBIs to fill a final Sprint in Scrum?

Background Scenario At the end of a project, there aren't enough story points to fill a two-week Sprint based on the velocity of the team. Capacity & Backlog The average velocity of the ...