Questions tagged [sprint-planning]

The tag has no usage guidance.

Filter by
Sorted by
Tagged with
15
votes
6answers
9k views

Is it really necessary to have a four hour meeting in Sprint planning?

According to Wikipedia, it is recommended that there should be a four hour meeting in a two-week sprint planning (pro-rata for other sprint durations). Is it necessary? Why?
12
votes
4answers
2k views

What should we do if there are not enough PBIs to fill a final Sprint in Scrum?

Background Scenario At the end of a project, there aren't enough story points to fill a two-week Sprint based on the velocity of the team. Capacity & Backlog The average velocity of the ...
11
votes
3answers
1k views

Selecting user stories during sprint planning

When selecting user stories from the prioritized product backlog during sprint planning, is it more important to make sure that we end up with our predicted velocity in story points or that we choose ...
8
votes
4answers
2k views

Planning a sprint after reduced team strength

We have seven people team and their running velocity is ~50 points(2 weeks sprint). Now due to change in business focus, we have to reduce team size from 7 to 4. How do we plan current sprint? ...
6
votes
5answers
2k views

How do I convince a team to follow the Scrum Guide?

I have recently joined a new team in a new organization that is supposedly using Scrum. This Sprint, the BA/Scrum Master has decided it would be best to do the planning session for 1 hour on ...
6
votes
3answers
2k views

How can you estimate a spike story?

We are working on a technology of which the team is not sure how would it go.I would like to estimate and timebox this story.However,the scrum team has to goal or a shippable product at the end of ...
6
votes
2answers
1k views

Should all team members be assigned user stories?

This is a very basic question but I don't see any answers on it yet. Scenario: We did sprint planning and I noticed some one saying Not all developers have a task to do. We need to add more tasks ...
5
votes
3answers
1k views

How to manage technical conflict between Product Owner and developers?

Imagine you are a Product Owner. And you have planned a sprint, prepared every detail, broken down the epics into stories and already presented your roadmap to management and promised the releases ...
5
votes
3answers
2k views

Sprints Starting Mid-Week in Scrum

When people discuss Sprints that start or stop mid-week, they seem to agree that this should be done on a Tuesday or Wednesday. Why is that? Also, how do week-long Sprints with mid-week starts and ...
5
votes
1answer
216 views

How to handle when planned work is blocked and a developer has capacity to take on a new user story that may be too big

Assume the following situation. All but one user story planned in a sprint is completed. The remaining user story is blocked. A developer would like to take on work in the highest priority work ...
5
votes
1answer
108 views

Sprint board critique

We are a DevOps software team with dependencies upon a release process which often requires us to wait before releasing some code to production for up to 5 times longer than our sprint length. This ...
4
votes
2answers
195 views

Slicing User Stories

I have few queries on how granular we need to go on splitting stories. We have a story where clicking the phone no in the system should dial cisco or skype or any other telephony systems based on the ...
4
votes
4answers
999 views

Story Points flaw?

Forgive me f this has been asked before, I read some similar questions (linked below), but didn't find the answer I was looking for. Our team is fairly new to them and trying to figure out how to ...
4
votes
2answers
92 views

Architecture task as sprint issues

I understand spikes as being investigation tasks when there is an uncertainty about how a story should be done but my question is more about how to include a software architecture task in a Sprint. ...
4
votes
1answer
514 views

Hot swapping stories

Is it acceptable to swap out stories from the current sprint to the backlog and replace them with stories of the same estimate size from the backlog, because of changing priorities in the business? ...
4
votes
2answers
309 views

Why is sprint planning so long if your backlog is ready and prioritized

Sprint Planning is time-boxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter. According to the scrum guide it sounds like the meeting has two ...
3
votes
4answers
279 views

Reducing Spill Overs

The scrum team performs following tasks Development -- Dev Team Testing -- Test team Merging -- Senior Team [BOTTLE NECK] Acceptance Testing -- PO/BA [BOTTLE NECK] The Dev and Test team finishes ...
3
votes
2answers
272 views

How should the Scrum Team proceed if the PO is sick and can't attend the Sprint Planning meeting?

What should we do if the PO is unable to attend the Sprint Planning meeting? Is there a workaround for it?
2
votes
3answers
143 views

Capacity Driven Sprint Planning

I have recently taken over as Scrum Master for a team. I plan on implementing capacity driven sprint planning. The challenge is, we have several User Stories (that should've been classified as Tasks ...
2
votes
1answer
250 views

Scrum PSM I Practice Assessment (3rd Party) Trick Questions?

I took the PSM I Practice Assessment here, and came across two questions that appear to be incorrect, or at least trick questions. Question 1: https://www.scrumguides.org/scrum-guide.html#team-dev ...
2
votes
2answers
78 views

What should I learn to become a software project manager? [closed]

I am a newbie mediocre developer/freelancer working with Angular-NodeJS/MongoDB projects. What I want to do is create a team and work on bigger and better projects, but my problem is that I don't ...
1
vote
1answer
103 views

Need help for sprint planning when tasks are not done in previous sprint

In our team we don't have dedicated Scrum Master so one of the developer is playing the role of SM. I know this is wrong but it can't be changed. In out system, we assign story points to all the ...
0
votes
2answers
109 views

Sprint planning

I am a new PM/PO in a software firm in California. I am working with offshore team in India. As a new PM/PO I need to do Sprint Planning. As I understand, Sprint Planning is also known as Sprint 0 as ...