Questions tagged [sprint]

A sprint is the basic unit of development in Scrum and Agile. Sprints last between one week and one month, and are a "timeboxed" (i.e. restricted to a specific duration) effort of a constant length.

Filter by
Sorted by
Tagged with
3
votes
2answers
777 views

Scheduling Sprint Reviews

I'm trying to find the right balance on how Sprint Reviews should be scheduled for my Team. Each member in my Team has their own project although everyone in the Scrum Team does attend a single Daily ...
-1
votes
3answers
93 views

Usable or usefull increments in Scrum?

Two-week Product Increment can be usable, but not very usefull. So does PO need to attend every Sprint Demo? Let's say that a feature is mostly related to adding a new function to a backend. We need a ...
2
votes
2answers
198 views

From a project planning perspective, is it wrong to have one sprint for the API and another sprint for the UI?

I am making an e-commerce project that has a dashboard module. Instead of having one sprint for the dashboard module, my advisor said I should split this module realization into two different sprints: ...
4
votes
1answer
115 views

How should large non-reducable tasks be handled in Scrum?

How are tasks that do not fit in a Sprint handled in Scrum? I see the benefit in delivering incremental value each Sprint, but I don't see how all tasks can be reduced to take no longer than a week or ...
4
votes
5answers
1k views

Why is it important to only have PBIs completable in a single Sprint?

In Scrum it is emphasized that the Sprint Goal is achieved and that the developers determine which work can be completed in the Sprint. I often get the following question: Why can't we start a story ...
14
votes
4answers
3k views

Artificial decomposition in Scrum

Scrum Guide says: Product Backlog items that can be Done by the Scrum Team within one Sprint are deemed ready for selection in a Sprint Planning event. They usually acquire this degree of ...
1
vote
2answers
155 views

Sprint Planning for Agencies

I'm looking for some help finding resources on sprint planning specifically for agencies, namely a web design and development firm focusing primarily on web apps. So a typical project would be a ...
0
votes
1answer
83 views

Creating a PaaS using scrum

If one were to build say a Windows Azure "clone", what would be considered an increment that is "potentially releasable"? e.g. Releasable vs shippable? I can not envision what ...
0
votes
3answers
111 views

Backlog grooming items planning

In a Scrum project if the team is from 4 developers, the sprint is two weeks long, Team Velocity is 40 SP/Sprint and the Focus Factor is 0.6. During the Backlog Grooming meeting, user stories with how ...
0
votes
0answers
103 views

Too much to test on the last day of the sprint [duplicate]

How can I avoid the issue where a lot of stories are moved to Under Testing on the last day of the sprint? The Under Testing column is manageable on most days but on the last day and there day before ...
7
votes
8answers
3k views

From a sprint planning perspective, is it wrong to build an entire user interface before the API?

I'm currently reading 'Agile Estimating and Planning' by Mike Cohn and it mentions to not split by tasks like 'build user interface' and 'build middle tier', and instead to focus on building something ...
1
vote
4answers
154 views

How to handle a Sprint completed ahead of time? [duplicate]

Let's say we have a sprint of 2 weeks. In that sprint, the IT team has to implement some issues or features. How can we handle the case where the team finishes all issues/features ahead of time? Do we ...
7
votes
4answers
802 views

How do you make the Teams Retrospective Actions visible and ensure they get attention throughout the Sprint?

After a Retro we usually have 2 or 3 Actions to address in the next Sprint. Some of these Actions are sometimes more of a reminder to Developers. Who do we ensure they are addressed in Sprint? We're ...
0
votes
7answers
723 views

Is it possible to give timelines in SCRUM?

Our team is currently using a very SCRUM near approach in planning and development. But I constantly face one issue with our management. The management is part of the backlog priority process and each ...
0
votes
2answers
68 views

Agile Development Practices in a Vendor-led App Development [closed]

As the product owner, what is the best approach to administering the scrum framework in vendor-led app development? And eliminate the difficulty of ensuring they build and deploy in line with a sprint ...
1
vote
4answers
190 views

Time management in a Sprint

During a sprint, producing frequent builds, conducting testing, and fixing bugs quickly during an iteration can become daunting, especially when the quality of the work done is not optimum. So how can ...
-1
votes
1answer
351 views

Adding New Requirement in the middle of the sprint [closed]

1 If you are in the middle of the sprint and the product owner has come with the one new requirement for the customer what do you do? What is the best way to handle it? How to evaluate the scrum team? ...
2
votes
3answers
206 views

How can I effectively differentiate the Sprint Goal from the Sprint Backlog?

I'm facing a situation where I have to explain with an example the difference between a Sprint Goal and a Sprint Backlog. Here's how I understand it: The Sprint Goal is an objective that needs to be ...
5
votes
3answers
719 views

Does a 30 days Sprint include weekends?

I am still learning more about Scrum and I have a question. If people say the duration of the Sprint is 30 days, is the actual work 22 days (30 days - (2 weekend days * 4 weeks in a month)) or is it ...
5
votes
6answers
196 views

What is the proper use case for an Iteration 0?

When starting a new software version and/or embarking on a new product, what is the purpose of, and what are the crucial pieces of an "Iteration 0?"
2
votes
2answers
79 views

Agile Storyboarding impact on a Business Quarter

a) We have total 6 Sprints constituting a business quarter. b) We are releasing every 2 Sprints (or earlier) by means of CI/CD. c) We have to deliver a new feature in the next quarter for which we ...
1
vote
4answers
187 views

Team velocity declined after legacy declaration

I am the manager and I am struggling with a declined velocity. I have tried to discuss with the team what is going on, and they say they got better at story point estimation. But I suspect they are ...
3
votes
6answers
290 views

Team consistently not making sprints

So I know that this question has been asked before, but since I haven't really seen anything that benefited my problem, I thought I would give it a chance. So first things first, in a perfect world ...
6
votes
5answers
816 views

We have a velocity of zero

I am a Scrum Master for a small development team of 7 developers and 3 testers with 2 week sprints. The product we are working on is large with a lot of modules. The breakdown of the modules is ...
6
votes
2answers
654 views

How to deal with recurring tasks in a sprint?

We are working on a software product which by now requires about 40% of our capacity maintenance work like e.g. manually checking data per day. What would be the recommended way on dealing with those ...
0
votes
2answers
174 views

How do you plan a sprint with disproportionate Devs/QA members ratio?

How do we plan a sprint in which we have 5 developers constantly coding and only 1 QA to test the output? Basically QA ends up to be the bottleneck in every sprint. One option is hire more Was but ...
7
votes
4answers
1k views

Does it make sense to use Scrum when the dates for sprints constantly change?

Does it make sense to use Scrum when the dates for sprints constantly change? Our team uses Azure DevOps with Scrum. We have multiple codebases to maintain. However, since things are usually rather ...
3
votes
2answers
794 views

Why is Scrum iteration called a Sprint?

I'd say that a sprint implies commitment, hard working, willingness to finish all the tasks taken into the sprint by the end of the sprint. On the other hand Scrum doesn't require a team to complete ...
2
votes
5answers
604 views

What to do when there's not enough work related to the Sprint Goal?

We have enough work to do to fill two weeks (our Sprint length) for the Team. We have a Sprint Goal. We do not have enough work to do for the Sprint Goal to fill two weeks for the Team. As a result,...
1
vote
1answer
50 views

New Sprint planning when no history data is available [duplicate]

What is the technique to be used when you are starting a new sprint (in a new project) when no history data exists. Thanks, Shiva
0
votes
1answer
88 views

When should be done Backlog Refinement Meeting? [closed]

I am a new PO so please help me or guide to understand this better. Per Scrum Guide, I do Sprint planning, my o/p is sprint goal and sprint backlog. I already come to the meeting with PBs and user ...
0
votes
2answers
143 views

Sprint planning

I am a new PM/PO in a software firm in California. I am working with offshore team in India. As a new PM/PO I need to do Sprint Planning. As I understand, Sprint Planning is also known as Sprint 0 as ...
2
votes
2answers
940 views

How to balance the QA load during the Sprint?

There is an iterative development (let's call it “Scrum - with reservations” for simplicity) of a team of 12 people: 3 back-end developers, 3 front-end developers, 1 technical writer and 5 testers (4 ...
4
votes
3answers
110 views

Scrum based High-tech Product Development with a very mixed Group (Seniors & Novices)

I'm already a (certified) Scrum Master of a software Development Team and I'm going to/have to establish an agile product development process (Scrum is favored) with another group with four engineers. ...
3
votes
2answers
76 views

Develop user stories in the previous sprint, if sprint commitments met?

If your developers have completed their Sprint commitments (QA is ongoing - and any issues found by them are fixed in the same Sprint), what are the possible issues with developers picking up items ...
2
votes
4answers
213 views

Sprint Review: How to prevent every single type of story from being "reviewed"

The team decided to make every work item into a sprint story. This means that along with development stories that result in a product increment, a sprint also contains stories for integration testing, ...
1
vote
3answers
11k views

What is prerequisite for starting a Sprint?

What are the mandatory prerequisites to start a Sprint? The Product Owner makes decision to start the Sprint; what are the Scrum Master's/Development Team's roles in making the decision? Does the ...
15
votes
6answers
9k views

Is it really necessary to have a four hour meeting in Sprint planning?

According to Wikipedia, it is recommended that there should be a four hour meeting in a two-week sprint planning (pro-rata for other sprint durations). Is it necessary? Why?
4
votes
5answers
564 views

"Dead horse" topics banned at sprint retrospectives, is this good practice - why or why not?

I'm asking as a member of an Agile (Scrum) team, not as the PM/PO/Scrum Master. On this project there are a handful of well-known impediments / problems / things that didn't go well, which are a ...
3
votes
1answer
68 views

How to take out dependancies among tasks within a scrum sprint?

Suppose, a user story has further divided into multiple tasks; if the tasks are having dependancies among themselves then how to make sure that productivity stays stable? I have read that we have to ...
4
votes
3answers
414 views

breaking down a feature into stories and avoiding dependencies

I run a team with a few iOS developers and a few backend developers. Over the last couple of months, we've been experimenting with different ways of structuring users stories for sprints and have ...
0
votes
2answers
85 views

Tasks during sprint planning

For the next sprint, Jira displays the total number of story points in the backlog, calling it "Estimate.". This number leaves out tasks, which are estimated in hours, not story points. This makes it ...
3
votes
3answers
762 views

Can a story be put on hold within a Sprint?

The team is working with a user story and they are stuck on some technical issues and unable to resolve them. This story is committed for the current Sprint. Shall I put this story on hold after ...
0
votes
3answers
607 views

When requirement changes comes during the sprint, who takes the final decision to include or not

If change request is pushed by the client during the sprint aggressively, who takes the final decision if it needs to be included or not
0
votes
2answers
81 views

How can we decide if a story is a feature or just an internal change?

We have a story where we want to have uniformity across our product suite by using a same jar file across three products. Consider it as an add-on to the original product, and as of today we have ...
2
votes
2answers
63 views

When choosing the largest and smallest stories in a backlog for estimation how does it impact each sprint?

An article I came across suggested that we should pick the largest and smallest story in the prioritised backlog and relatively estimate the remaining stories. This makes sense. However, I was ...
3
votes
2answers
176 views

Should single user story contain estimations for each involved guild in full-stack development team

Problem We're working in a full-stack development team composed of three guilds (backend, frontend, QA), so as a team we share a single sprint board. User stories we take into our sprints are written ...
1
vote
3answers
433 views

How far should you vertically slice?

We are a small team of 4 software developers trying to use Scrum. We have a large project to start from scratch and we've hit a roadblock regarding slicing the project. The project is a distributed ...
41
votes
7answers
11k views

Why do all the teams that I have worked with always finish a sprint without completion of all the stories?

I am developer, I have worked with three Agile teams for the last eight years, with different organisations. The organisations have had a mix of Scrum, Kanban & Lean Startup Mindsets. I have ...
1
vote
1answer
159 views

An agile approach with a waterfall delivery and the QA impact

My customer signed off on a major enhancement to an existing application. The enhancement will be delivered as a single new release and I can't change this. However, how we get to this final release ...

1
2 3 4 5