Questions tagged [sprint]

A sprint is the basic unit of development in Scrum and Agile. Sprints last between one week and one month, and are a "timeboxed" (i.e. restricted to a specific duration) effort of a constant length.

Filter by
Sorted by
Tagged with
5
votes
1answer
249 views

How to handle when planned work is blocked and a developer has capacity to take on a new user story that may be too big

Assume the following situation. All but one user story planned in a sprint is completed. The remaining user story is blocked. A developer would like to take on work in the highest priority work ...
5
votes
3answers
3k views

Sprints Starting Mid-Week in Scrum

When people discuss Sprints that start or stop mid-week, they seem to agree that this should be done on a Tuesday or Wednesday. Why is that? Also, how do week-long Sprints with mid-week starts and ...
4
votes
1answer
87 views

How to treat users stories which were almost completed at the previous sprint? [duplicate]

How to treat users stories which were almost completed at previous sprint but didn't meet Definition of Done due to testers were late for some reason. Suppose one of those stories was 5 story points, ...
4
votes
2answers
222 views

Should we add more items to sprint backlog if there is items that are not completed

Question: Should we add more items in a sprint if there is items that are not completed but a developer is open. Scenario: Lets say we the development team are made up of 5 team members and we have ...
4
votes
3answers
237 views

How to deal with non negotiable change

One of the issues my organisation has is where change requests are requested during a sprint cycle in a particular high volume worksteam. The development team are often forced to accept these change ...
5
votes
5answers
971 views

Should we demo bug fixes in sprint demos?

We have been asked to demo almost all bugs in our sprint demo, except the bugs which were raised for the stories of the sprint. Some teams only demo critical bug fixes, probably to reassure others ...
13
votes
4answers
2k views

How can story points be “non linear” in relative size

I've read in several places that story points are not necessarily linear. i.e., an "8 point" task is not the same as two 4 point tasks and so on. I totally get the argument about these being an ...
3
votes
2answers
133 views

How to correctly define tasks in a user story? And can you split the tasks between sprints?

I'm fairly new to Scrum and I'm working with a group of colleagues on a project to learn more about it. Long story short our project is simply creating a website for tourists of our country where they ...
4
votes
4answers
1k views

Moving backlog items into Sprint

In Agile, who's the person responsible of moving tickets in Jira (e.g. moving backlog items into Sprint). Is this a Scrum Master's responsibility or Product Owner?
4
votes
2answers
94 views

Architecture task as sprint issues

I understand spikes as being investigation tasks when there is an uncertainty about how a story should be done but my question is more about how to include a software architecture task in a Sprint. ...
4
votes
2answers
347 views

How to handle real world sprint failures?

Example: I have a project where I want to import raw data into a new database. sprint 1: clean up/validate raw data sprint 2: import raw data to new database If sprint 1 fails, what is the SCRUM ...
0
votes
1answer
87 views

What is the proper way to add/represent development tasks (like refacturing) to a sprint?

We coded something which works but is quite terrible. We have planned the refactoring of that piece of code in this sprint but since it doesn't really fit in a user story, how do we add or represent ...
5
votes
2answers
262 views

How to utilize resources effectively in cross-functional scrum teams?

I agree on an idea of making teams cross-functional. However, I doubt that resources may not utilize effectively when the nature of the work varying sprint to sprint. For example, There are database ...
8
votes
3answers
373 views

Is it possible to be agile with a highly technical project?

I'm working on a small (4-6) team on a project that involves creating a machine learning model to predict the outcome of sports matches real-time. This also involves scraping the data and storing it ...
2
votes
2answers
1k views

Business days calculation for the sprint

Our team is new to agile. We are in the phase of defining the rules for sprint planning. To start, we are keeping our Sprints at 2 weeks (10 business days). Let's say there is a public holiday in a ...
4
votes
1answer
115 views

Is it fine to pick stories in the current sprint which have external dependency?

We have a separate Scrum (front-end) Team to handle UI requirements. Sometimes, due to urgency, we end up picking stories in the current Sprint which depend on the front-end Team. Whenever ...
4
votes
1answer
64 views

Change of business focus after a sprint has started

If we start a sprint with a specific goal and the user stories to support that goal, then the business changes their immediate requirements during that sprint. This may be because of a client ...
3
votes
1answer
197 views

Is it necessary for the whole team to participate in the Sprint Review in Scrum?

Scenario Before changing to Scrum, we usually performed some type of review with the Project Manager (now Product Owner), the Project Lead of the development team and the stakeholders. Our ...
3
votes
2answers
2k views

Is it possible to remove Stories during a Sprint in Scrum?

Scenario In our organization, we use velocity to forecast the amount of possible work in a Sprint. Sometimes, based on the Team's average velocity, we add extra features not related to the Sprint ...
1
vote
3answers
217 views

Should we start a sprint review with no business value stories in Scrum?

Scenario In some cases, specially at the beginning of a new product, we have a sprint entirely with architectural user stories with no business value but necesary to the product to be sucessful. We ...
4
votes
1answer
514 views

Hot swapping stories

Is it acceptable to swap out stories from the current sprint to the backlog and replace them with stories of the same estimate size from the backlog, because of changing priorities in the business? ...
5
votes
5answers
1k views

Can you change the end date of a sprint?

Ideally we commit to work being completed and releasable by the time the sprint finishes. However sometimes things happen or estimating is a little bit out. If we are approaching the end date of a ...
5
votes
6answers
417 views

Is it fine to correct an estimation of a story during execution?

During execution of sprint, should team allowed to change estimation of a story in following scenarios. During execution When a story is finished Re-estimate in absence of Product Owner(PO)
14
votes
4answers
2k views

Are all the scrum ceremonies included in the sprint timebox in Scrum?

We know the daily meeting and the backlog refinement is inevitable to have out from in the sprint timebox, but we don't know, for example in a two-week sprint, if the sprint planning, review and ...
4
votes
2answers
253 views

Is a good Scrum practice to meassure the developer team by the story points completed at the end of the sprint?

We have new teams working on scrum and they estimates all the points of a several ammount of stories. But, at the beggining, they have no reference of how ammount of points could be delivered in two-...
12
votes
4answers
2k views

What should we do if there are not enough PBIs to fill a final Sprint in Scrum?

Background Scenario At the end of a project, there aren't enough story points to fill a two-week Sprint based on the velocity of the team. Capacity & Backlog The average velocity of the ...
18
votes
4answers
3k views

How to deal with hotfixes keeping the scrum methodology

My team works with scrum methodology. However, during some sprints we have hotfixes that have to be developed as soon as possible, so we treat them in the current sprint, and consequently we have an ...
1
vote
2answers
3k views

Schedule for a 10 day Sprint in Scrum

We have been doing 1 week Sprints and the development team is quite reluctant to go ahead with continuing 1 week sprints. various reasons include Team is feeling stressed in getting things done in a ...
4
votes
3answers
262 views

During a Sprint, a DevTeam determines that it will not be able to finish the complete forecast. Who should review and adjust the Sprint work selected?

During Sprints' executions, I used to encounter a problem: the planned Sprint would not be able to finish as forecasted. Then in that case, who is responsible to review and adjust the Sprint work ...
2
votes
4answers
180 views

Good approach to group different project stories in same sprints

Would you consider is it good approach to group different user stories from different projects into one sprint? Have you ever detected pros/cons? Let's say 1. Project A (Start 2017-01-05 Estimate ...
2
votes
2answers
461 views

How do you deal with external customers in agile projects

You are starting an agile project. As a scrum master you are facilitator and you assist the product owner with the backlog in creation as also in its maintance. You also coordinate with external ...
9
votes
4answers
4k views

QA Code freeze and setting the expected delivery timeline

We are in the healthcare industry, where bugs can have an impact on people health. As a result, we started having a code freeze on the staging environment to have the QA test each build. In addition: ...
2
votes
4answers
471 views

Regarding best practices of Scrum are there any “best weekday” to start/end Sprints?

From my experience I always worked at companies in which the Sprints started on Mondays and ended on Fridays (regardless of the sprint size, obviously). Is there any good practice that says this is ...
0
votes
3answers
449 views

Can one developer work on two different projects (and in effect, two different backlogs) in a single Sprint? Any Agile recommendations on this?

Can a single developer work on two different projects/backlogs completely independent in two Sprints (One Sprint is for one project/one sprint for the other) in the same timeline.
3
votes
3answers
668 views

How to complete many development phases within 2-week Sprints

I work in a tech company, a few weeks ago we moved from traditional project management to Scrum multidisciplinary Teams. Our sprints' length is two weeks and the experiment is not working well for ...
1
vote
2answers
94 views

Dedicating one day for support work per sprint

I would like to receive thoughts and possible feedback on anyone's previous experience of allocating a dedicated day to support jobs within a sprint. Our percentage of support jobs per sprint is ...
2
votes
2answers
246 views

Can Fixed Scope/Variable Timescale be Agile?

I have an ongoing argument - our delivery manager tried to introduce a "release after 3 sprints" pattern into our teams. Unfortunately, like many businesses, the actual work can be x number of ...
-1
votes
3answers
1k views

Should bugs be estimated in story points?

Should bugs be estimated in story points according to the Scrum methodology? In particular, what if a bug appears to be a quite complicated task, which in fact is a some missed functionality which ...
3
votes
4answers
158 views

How to account for new work items while implementing a story without affecting the sprint scope?

During a sprint in scrum, the scope of the sprint should not change. However, I often find that after the sprint starts and I begin working on a story, I discover new stories that must be done. For ...
1
vote
5answers
5k views

Why must we define a Sprint Goal for each Sprint?

As a Scrum Team, we are committed to deliver Product Backlog items per the Product Owner's priority. The team doesn't understand why we should define Sprint Goals. How does that help?
3
votes
7answers
15k views

Scrum vs. Sprint

I'm new to Agile methodology and I have some very basic questions. Sprint -> It is the iterative process (One development life cycle from Requirement to user acceptance testing) in Scrum. So, while ...
3
votes
3answers
264 views

Is it ok to make developer responsible for one of sprint goals?

Currently in our project the situation is that we can have several goals. And it works fine for us to make a team member responsible for acheiving a particular goal. But recently I tried to pass "...
0
votes
3answers
113 views

How to handle issues that are part of the backlog, solved in the weekend and are not part of current Sprint in Scrum?

There are two issues on the backlog that I want to solve this weekend, that are not part of the current sprint. According to me it is fine to work on this issues as I solve them in my spare time and ...
2
votes
4answers
644 views

How should be the pricing using agile?

How should be the pricing using agile? Is it fixed per sprint?
3
votes
6answers
2k views

For a two-week Sprint, can I adjust the meeting dates when there is a holiday in our country?

Sprint 1 starts November 5th and is supposed to end on November 16th, but there is a government holiday November 13-15. Can I change the Sprint 1 schedule to be November 5th to November 21st?
2
votes
5answers
289 views

What happens when the PBI in a sprint are done but the sprint timebox hasn't expired?

I know that if PBI's cannot be completed within a sprint they can be re negotiated with the product owner Now again a sprint cannot be shorted or lengthened then the agreed time box unless the ...
4
votes
4answers
778 views

How to deal with tasks detalization in sprint planning?

I have a newbie question. Let's suppose that for a sprint backlog we choose one user story from product backlog: "As a photography junky I want to be able to make a collection of favorite photos". ...
1
vote
3answers
171 views

Sprint backlog before going further with project

I've an ongoing project with very tight deadline. I'm allowed to extend project deadline, if required. I've implemented Scrum (sprints). Issue is - I've some backlog since one weeks, that I couldn't ...
2
votes
1answer
132 views

How to explain to a product owner that inviting their team to sprint planning is a bad idea?

I have a product owner for one of my sprits who likes to involve people outside the sprint in sprint tasks. I've attempted several times to explain how this isn't ideal, and in fact slows down the ...
1
vote
3answers
793 views

How to determine the story points to commit for the next sprint

I'm a software QA that has limited knowledge of the agile methodology due to my sparse time with Agile teams in the past. Currently I'm exploring using Story points for my team instead of estimated ...