Questions tagged [story-points]

For questions about applying or interpreting relative measures of work-effort, known as "story points," to user stories or project milestones.

Filter by
Sorted by
Tagged with
1
vote
4answers
72 views

Story acceptance vs. ability to have potentially deliverable SW ready at sprint end

for some time now the team, product owner and me (SM) have been busy with one task: the story acceptance and the ability to get potentially deliverable SW at the end of a sprint. What sounds simple ...
2
votes
2answers
31 views

When choosing the largest and smallest stories in a backlog for estimation how does it impact each sprint?

An article I came across suggested that we should pick the largest and smallest story in the prioritised backlog and relatively estimate the remaining stories. This makes sense. However, I was ...
11
votes
3answers
2k views

Is there any published research about story points vs time estimation?

We're getting started with Scrum and have had a few debates about whether we should estimate in story points or ideal hours. The team is pretty divided, so I'd like to know if any real studies have ...
6
votes
3answers
2k views

How can you estimate a spike story?

We are working on a technology of which the team is not sure how would it go.I would like to estimate and timebox this story.However,the scrum team has to goal or a shippable product at the end of ...
5
votes
2answers
226 views

What metrics can we generate from t-shirt sizes (rather than story points) when estimating user stories?

If I am using T-shirt sizing for my user story estimates, what metrics I can measure and report? We currently use a Sprint burn-down chart when using story points.
4
votes
2answers
84 views

Velocity calculation based on number of user stories completed in a sprint

In one of the projects, the velocity calculation is done based on the number of user stories that the team is delivering in each sprint. They are using story points to size but still the velocity is ...
1
vote
1answer
58 views

SCRUM - Sizing in sprint. Do I need to use story points in a sprint if the duration of the project phase itself is only 3-4 months?

In my current company, DSDM is being practiced. For a new project that we are starting, there are no backlogs yet and it is decided we will be executing the project in sprints. The duration of the ...
3
votes
2answers
238 views

Should story points be estimated according to team or assignee's abilities?

Say you have a team of 4. 1 junior, 2 mid-level and 1 senior. The senior engineer can get the story completed quickly (say 1 point). For the junior, the work is more complicated; he/she doesn't ...
4
votes
4answers
832 views

Story Points flaw?

Forgive me f this has been asked before, I read some similar questions (linked below), but didn't find the answer I was looking for. Our team is fairly new to them and trying to figure out how to ...
15
votes
6answers
3k views

In scrum should incomplete stories be re-estimated or does the original estimate get burned down when it's finally completed?

If I have a story that's been estimated at 10 story points and we don't manage to complete it in a sprint how do you handle estimates for the sprint in which it's next included (assuming it gets ...
3
votes
1answer
116 views

Carrying items over from one sprint to the next

Question: Carrying items over from one sprint to the next Answer: Yes Scenario: I am a new scrum master on a team and we have just completed our first sprint. I was not here when the team planned ...
2
votes
1answer
64 views

How to treat users stories which were almost completed at the previous sprint? [duplicate]

How to treat users stories which were almost completed at previous sprint but didn't meet Definition of Done due to testers were late for some reason. Suppose one of those stories was 5 story points, ...
9
votes
6answers
509 views

Is it okay to have a sprint where the team commits to zero story points?

Our two Scrum development teams are located in India. Our shared product owner is permanently relocating to the US, and we're just about to finish our first sprint. Him and the team suggested ...
6
votes
3answers
2k views

Changing backlog story point estimates mid way through a release

Background: We are mid-way through a development which was estimated for a customer on a fixed price contract. To come up with the estimate we built a backlog by trying to list all user stories and ...
7
votes
2answers
1k views

How can I effectively track story points with Trello?

I'm exploring Trello as a Kanban tool, and am hung up on how to track story points with it. This isn't something that Trello natively supports, so I've been re-purposing labels to carry this ...
23
votes
7answers
5k views

Why use both story points and hours?

I'm a new scrum master for a team that is using story point estimation and hours. We do story points first during grooming and then hours during planning. I always thought of story points as being ...
10
votes
3answers
625 views

How to use Story Points, if User Stories are completely different?

Story Points (SP) is a good measurement, that allows estimating User Stories. SP (in my understanding, it's an important note) is convenient because it is relative and not related with time. All ...
10
votes
3answers
2k views

How can story points be “non linear” in relative size

I've read in several places that story points are not necessarily linear. i.e., an "8 point" task is not the same as two 4 point tasks and so on. I totally get the argument about these being an ...
9
votes
4answers
4k views

When does a Scrum Team assign story points to the stories in the Scrum methodology?

I am in the process of learning Scrum. I got stuck with a question: on which stage does the Scrum Team assign story points to the user stories?
2
votes
3answers
82 views

How can I measure the effective team work per iteration?

I have a team of 4 developers and 1 QA. My workflow in Jira is: Backlog -> Analysis -> In Development -> QA Ready -> QA Complete -> Done Every sprint (1 week) all issues get into QA Ready stage (QA ...
12
votes
3answers
3k views

Can we have zero point stories?

Our Agile/Scrum team follows the Fibonacci sequence for story point estimation. However, it is not clear whether we should have any zero point stories at all. Even though a story may have minimal ...
2
votes
4answers
1k views

Should I estimate repeating tasks (besides Stories and Bugs)?

Besides User Stories and Bugs (no estimation) we have some repeating Tasks in our sprint, which have not much insecurity and a clear scope. For example such a task is "releasing our plugin" (building, ...
4
votes
1answer
461 views

Hot swapping stories

Is it acceptable to swap out stories from the current sprint to the backlog and replace them with stories of the same estimate size from the backlog, because of changing priorities in the business? ...
3
votes
4answers
524 views

How to break down an 8 point story into smaller stories in Scrum?

My team and I are struggling with breaking down a user story that we have estimated to be 8 points. The user story is : "A user can sign up to the app using a registration form so that he is ...
3
votes
4answers
511 views

Best measurable units for non cross-functional team estimation

I have a new development team and I want to use Story Points for high-level estimation. But I have two problems: My new team is not cross-functional (we are trying to solve this, but this is a slow ...
2
votes
2answers
78 views

When working closely with sales, does storypoints still make sense vs time estimations

The main idea behind using story points is to take away focus on the absolute time/cost of a task and look at the relative sizing vs the other tasks you have in front of you. This has worked well in ...
5
votes
1answer
200 views

Using the Stacey matrix to capture agile metrics

I recently encountered the Stacey matrix in an answer by Stephan Weinhold. After looking at the linked image provided & doing a bit more reading that describes it as a way to characterize ...
1
vote
1answer
140 views

If SAFe must be continuously calibrated and measured in ideal days, why does the framework say recalibration is unnecessary?

TL;DR SAFe says you don't need to recalibrate estimation, but requires estimates and other metrics to be normalized across one or more Agile Release Trains. Context, question rationale, and the ...
0
votes
3answers
75 views

How handle the change in baseline story

We follow Agile Scrum. We had identified a baseline story for story point estimation and used it for many sprints. We had a velocity calculated. After sometime, the team found that the baseline is not ...
8
votes
1answer
2k views

What are “Consumed Story Points” in Trello?

Some Scrum add-ons allow you to enter both estimated story points and consumed story points. What are consumed story points and how do you measure/estimate them?
5
votes
4answers
2k views

How to manage story points when several developers work on 1 story?

My team consists of 2 backend devs, 1 front end dev and designer. Lets pretend we have next user story: As a user I want to sign-in/sign-out to use the system Designer says that it is equal to 2 ...
1
vote
3answers
6k views

JIRA - Story Points & Time Tracking

I've read various questions and answers and I'm really struggling to setup up a Project/Sprint/Story/SubTask to get what we think we need. In terms of long term planning I've sold my team on the idea ...
82
votes
9answers
79k views

Why would teams use the Fibonacci sequence for story points?

Why do some teams use numbers from the Fibonacci sequence as story points? Is it just a preference, or is there something more to it?
4
votes
6answers
1k views

Alternatives to estimating in hours/story points

We are looking to change our approach on estimates. Now we estimate in hours/days, but we would like to change this and make our process more flexible. We are working based on Scrum, where stories are ...
0
votes
3answers
86 views

What could be potential harm of giving points to chores or technical debts?

Recently our team has decided to give points to the chores. They had an argument that: Velocity defines team's capacity to deliver the work and if chores are not counted in velocity it won't reflect ...
-1
votes
3answers
88 views

Should we break each smallest possible thing as a separate story?

We have a requirement where we need to analyze all the analytics placed on our website. We have total 4 pages on our website where we need to do this. The story is simple: As a developer, I want to ...
145
votes
18answers
88k views

Why use story points instead of hours for estimating?

After using hours to estimate our projects for a long time and rarely coming within 20% of actual "work-to-ship," I have been told by a handful of people that "points" work a lot better at gauging the ...
2
votes
5answers
257 views

What approach of story points suit our team

We are distributed development team in three locations. In each location we have between 2 to 5 developers. We conduct daily standup via Skype. However, we have not been using story points. We just ...
1
vote
3answers
120 views

How do you write completable “stories” when all members of a team have a specialty?

From a user perspective our stories seem clear. From a engineering perspective our stories are a bit too broad and need to be broken up into sub-tasks. This is OK, but each member of the team has a ...
1
vote
3answers
124 views

What should you do with story points which aren't completed in sprint?

Within Scrum/Agile, if I have a story which is 90% completed, and the sprint ends, what should be done with this story? The logical decision seems to be to move this into the next sprint, however if ...
4
votes
4answers
232 views

Do we need to update time estimates when we estimate based on story points?

We estimate the issues based on story points/planning poker. My questions are: Do we need to update original/remaining time estimates when we estimate based on the story points? If we estimate based ...
6
votes
5answers
5k views

Jira story points versus sub task estimation

We are using Jira for agile PM, but are having problems working with both story points and sub task hours estimation. Articles like this and this just don't seem to help. The second article has a ...
4
votes
4answers
5k views

How to factor in story points/tasks for non sprint related items?

I understand that in general you create stories with story point complexity, and then define tasks and subtasks in which to mark time against, but how does this translate into items that are outside ...
13
votes
4answers
4k views

Should a burndown chart be based on stories or tasks completed?

TL;DR; As the title reads: do you base your burndown chart on stories completed, or on tasks completed? Some background on why I'm asking this: I currently work in a software development team of 4 ...
3
votes
3answers
206 views

Are story points achieved a good individual quarterly goal?

Our company is starting to set quarterly goals at a more individual level. For many engineers on the team, these goals will include product impact, automation and code coverage, new responsibilities, ...
3
votes
2answers
364 views

How to get team agreement about what story points mean to said team

Mike Cohn suggests having workshop and estimating 2 dozen stories. I was thinking of adapting this idea for one team. The objective is to get the team agreeing/understanding about what 1, 2, 3 and 5 ...
5
votes
5answers
412 views

Should I trade points when adding a new story mid sprint?

Suppose a task shows up mid sprint that is high priority. It must go into the current sprint and take top priority. Suppose the task is estimated by the development team to be a 3 point task. When ...
3
votes
3answers
321 views

How (and in what units) to measure the product scope?

Short version: How and in which units is it better to measure the product scope (volume of incoming requirements / amount of business functionality) if different parts of product (different ...
13
votes
4answers
3k views

Should velocity increase with time?

Some scrum masters are concerned with "bumping up" a team's velocity during a sprint, as if a higher velocity is better. But points are a relative measure of the work that a team needs to do for ...
4
votes
1answer
367 views

Why measure in story points (being a relative measure is not an acceptable answer)

When I read about story points it is always mentioned that they should be used because they are a relative measure with examples like: It takes me 60 minutes to run a trail while you only take 30 ...