Questions tagged [tasks]

Questions relating to the management of individual tasks in a project or within project management software.

Filter by
Sorted by
Tagged with
6
votes
5answers
6k views

How to factor in story points/tasks for non sprint related items?

I understand that in general you create stories with story point complexity, and then define tasks and subtasks in which to mark time against, but how does this translate into items that are outside ...
5
votes
6answers
2k views

What is smaller than a user story but bigger than a task?

We have a "heavy" story that cannot be decomposed into smaller stories. It will span several sprints. We can decompose the story into tasks all right, but tasks seem to be abstractions that are only ...
0
votes
1answer
3k views

Is it possible to show the percentage of completed task in the Timeline in MS Project?

I am using Microsoft Project 2013. I would like to visualize in the Timeline the percentage of completed task, for example 33%... Is this possible ?
1
vote
0answers
23 views

MS Project, Resource Availability, Task Usage work hours

I've been using other tools for awhile and have to jump back into MS Project. I started a high level plan with tasks and resources, however, I'm having trouble remembering the specifics around Task ...
1
vote
1answer
26 views

Can I link or have formulas between task times?

Is it possible to use a formula to get information from "TASK A" as an input "work" in task B? Example: Task A is fixed duration of 2 weeks. I have assigned some resources and the total work they do ...
0
votes
1answer
194 views

MS Project - how to set a task to finish before else start after a set period

I'm trying to set a task to either be wholly complete by 1st Dec, if not then start after 1st Jan (i.e. don't start at all if it can't be completed by 1st Dec). I don't want to split the task. Is ...
-2
votes
1answer
75 views

task/workflow management best practice [closed]

I know this is not a specific question and I could rephrase it as such if necessary. I am seeking recommendations on how to manage an individual (my own) task list or how best to create a work ...
1
vote
1answer
55 views

Milestone behavior in MS Project

I am working in MS Project with a project someone else set up. This project contains 29 activities which are auto scheduled, has a minimum start date constraint on an activity, and two milestones. The ...
5
votes
5answers
360 views

What are the benefits of queuing tasks as opposed to assigning them?

When something needs to be done, be it a new task or getting help with an existing one, a knee-jerk reaction I've often seen in the wild is finding a person to do it. Here are some random examples of ...
21
votes
23answers
56k views

“Start to finish” dependency example?

Can you give me an example of a Start to Finish dependency? Wikipedia describes it like this: Start to finish (SF) A SF B = B can't finish before A starts
1
vote
1answer
189 views

Microsoft Project 2019 - problem allocating resources to tasks outside their calendar working hours

We have a standard calendar work week. (Monday to Friday with weekends off) Our resources have "standard" calendar - so scheduling as standard for them is a normal work week. However, we have ...
1
vote
2answers
80 views

How to reconcile WIP limits with tasks done in parallel by one dev?

Let's say we have five Stories, A, B, C, D, and E. However, while D and E are clearly separate business requirements and should be tested/documented separately, the technical requirements are related/...
0
votes
1answer
48 views

Parallel task with single person poject in microsoft project

I am making plan for my personal project.I have deadline for top level task(Project Planning- 31 days). I have rough idea of how I can divide these 31 days among sub-tasks. For example, Problem ...
5
votes
2answers
221 views

Small Projects: Asking the right questions

I'm a data analyst. I get assigned small projects. The projects usually take anywhere from 1 day to 2 weeks to complete. An example would be: Create a system/query that will generate a list of roads ...
2
votes
8answers
6k views

Adding new tasks to the current baseline

I would like to ask what the best approach would be in the following scenario. I have a project with all the tasks. I've created the baseline but my boss comes and says: I need you to add these other ...
3
votes
4answers
208 views

How to arrive at a project plan for migrating a legacy web application to ReactJS based application

I need to come-up with a project plan for migrating a legacy web application to a ReactJS based application. The legacy web application is written in Vanilla JS, HTML, CSS and there are approximately ...
0
votes
2answers
62 views

Tasks during sprint planning

For the next sprint, Jira displays the total number of story points in the backlog, calling it "Estimate.". This number leaves out tasks, which are estimated in hours, not story points. This makes it ...
4
votes
1answer
3k views

How do you calculate the number of days between two tasks in Microsoft Project?

I've created an event planning project that explains all of the relevant tasks before, during, and after a given event in MS Project 2003. I would like to calculate the number of days between a given ...
0
votes
1answer
36 views

MS Project: Sub-tasks causing unexpected 'Late Start'

I'm attempting to build a schedule and use MS Project to calculate dates and flow, based on constraints and task linking, but am unable to overcome an apparent issue with how the 'Late Start' is ...
2
votes
1answer
748 views

How can the Backlog Item's Effort field be auto calculated in Azure DevOps?

In Azure DevOps, under the Scrum template, is there a way to auto calculate the Backlog Item's "Effort" field based on the summation of its child Task items' "Remaining Work" field? Example: A new ...
14
votes
4answers
3k views

Should a Scrum team formally track daily commitments?

Should a Scrum team be tracking the daily commitments each team member makes during the Daily Scrum? We write them down in a kind of a mini task manager, and then we mark them as done during the work ...
0
votes
1answer
738 views

In Microsoft Project how to get change in resource max units to cascade to tasks automatically

I had already defined a bunch of tasks, and assigned resources 1 and 2. The durations of the tasks were calculated on the resources Max Units availability at the time of assignment. Later I went ...
3
votes
5answers
934 views

Who is responsible for passing a task when going for vacation?

Recently, I had a following problem on my team: One team member was going for vacation and he had two critical tasks assigned. He wasn't able to finish them before leaving. So we had a discussion ...
75
votes
7answers
129k views

What is the weighting difference between Epic/Story/Task

I am slightly confused between the three. From my understanding: Epic - Create a web site (T shirt size) (L) Story - Create the Home page (1 point) Task - Create a button on the home page that is ...
0
votes
2answers
250 views

I want to create a summary task without indenting the subtasks

Is there a way to create a highlevel task that will summarize all the subordinate tasks without indenting the subtasks?
0
votes
1answer
225 views

What is the difference between ABCD analysis and Eisenhower method?

According to Wikipedia, the ABCD analysis is: Activities are ranked by these general criteria: A – Tasks that are perceived as being urgent and important, B – Tasks that are important but ...
3
votes
3answers
697 views

User Story breakdown - Technical Task + User Feature

My team is building a web application that has the following high-level user story: As a user, I would like the ability to bulk exclude components from a given country. The work breaks down into ...
1
vote
1answer
48 views

Microsoft Project 2013 - Auto leveling according to Resource Availability

I am building a project plan on Microsoft Project 2013 and can't understand why it is not allocating a resource. I have a task set as auto scheduled, fixed work, with a 7 day effort assigned to a ...
2
votes
1answer
44 views

Is it wrong to put all projects in one VSTS project and then create nested epics

I had been reading on structuring VSTS. The guideline on structure of projects isn't very clear. Our scenario is that we have lots of projects and only a small team of 3 developers, 2 testers and 2 ...
23
votes
4answers
4k views

Task estimation for PMs who are not developers

While working Agile, how can a PM estimate a task when he/she is not a developer?
40
votes
14answers
23k views

Should bugs be treated as stories or as tasks?

If you're using scrum you should know that there is a clear difference between tasks and stories. A story is something that is valuable to user. A task is a step to produce that value to user. So, ...
3
votes
1answer
167 views

How can I show short tasks (less than 8 hours) in a JIRA Gantt chart?

I recently installed a few apps (like BigPicture) which help you see the order of work of each programmer. The problem is that when I link some tasks with estimates less than one work day, the Gantt ...
1
vote
1answer
35 views

How can you represent a task which only takes place at specific days on MS Project?

I want to represent a task which only takes place at specific days on MS Project: for example, on 01/01/2018 between 9:00 and 11:00, on 03/03/2018 between 10:00 and 12:00 and on 12/03/2018 between 11:...
1
vote
1answer
883 views

Why are tasks split while updating plan?

I inserted the actual start for updating a task and then inserted the %comp and reschedule and resource leveling for the plan with ms project 2013. The problem is that the task has been split in ...
2
votes
0answers
89 views

Ms project - Avoid task split up in minutes

I am trying to update my ms project plan with the following: - replan al 0% and partly completed tasks from the new status date. - Tasks can be split up - Plan based on priority and available time for ...
0
votes
1answer
101 views

How to Kick off a Task with just 1 predecessor complete

So I have Task A,B,C, Task B is based on CSF-5, (needs to have finish date 5 days prior to C date), but I want the task to kick off as soon as Task A is completed. Is there a way to set that? ...
1
vote
1answer
227 views

MS Project - Summary Task split by leveling

I have a summary task, and have the 'Leveling Can Split' option set to No. The four subtasks which are in sequence, also have LCS set to No. In the Leveling options I also have 'Leveling can create ...
3
votes
2answers
121 views

How to correctly define tasks in a user story? And can you split the tasks between sprints?

I'm fairly new to Scrum and I'm working with a group of colleagues on a project to learn more about it. Long story short our project is simply creating a website for tourists of our country where they ...
3
votes
5answers
308 views

Is it possible to give accurate estimates and planning without tracking time for tasks?

I work within a small team of developers. We don't track our time so we have no data to work off when we give estimates. Basically, I'm wondering if it's possible to have a successful plan and give ...
1
vote
1answer
1k views

EOT and LOT vs EET and LET

Are the Earliest Occurrence time and Latest occurrence time same as the Earliest Event time and Latest event time or are they different? If they are different can you please explain to me what are EOT ...
1
vote
1answer
752 views

In MS Project 2010, how to avoid a task of being split by non working time?

I am scheduling a series of 30 small training sessions (2,5d each), and I wish that each training would not be Split by weekends or holidays. All tasks are to be performed by the same person. If ...
1
vote
1answer
147 views

How to create a “smart” checklist in excel or google sheets?

We have a need to create a template checklist for our workflow and at a past job we had a template checklist that had various tabs for each process of the workshare that needed to be complete. For ...
1
vote
4answers
1k views

MS Project Calendar

I'm new MS Project user; I'm trying to sync my Ms Project 2016 calendar with Outlook 2013, I want tasks due dates give notification in Outlook. How can I do that?
0
votes
1answer
116 views

MS Projects show task always in timesheet

I am currently using Microsoft projects 2016 with time sheets. How can i create a task which is always shown in my time sheet with 0 planned work time? I have administrative tasks beside my project ...
6
votes
3answers
5k views

Should Summary Tasks or Detail Tasks be Predecessors?

When setting up a project, what are the advantages and disadvantages to using Summary Tasks vs Detail tasks as predecessors? If it matters, I am experimenting with MS Project 2010 as a tool.
4
votes
4answers
663 views

How to deal with a team that fails to complete a task?

I had been in a situation where details about the task and the target to be followed have been explained to the team. However, in spite of multiple follow-ups, they fail to complete the defined tasks ...
0
votes
1answer
52 views

How to model extended period of 'searching for product' tasks in MS-Project?

We run a sale of second hand goods from clients. We would set a target say 200 items this season and start contacting people we know who have items they want to sell. We would spend about 2 months ...
2
votes
2answers
793 views

ProjectLibre: One person two tasks at the same time

I'm trying to schedule a few tasks in ProjectLibre and I'm also fairly new to PM The problem Suppose we have Person1, and he'scheduled on two tasks (100%): Install device (duration=1hr) Test ...
3
votes
4answers
982 views

Tool to track recurrent tasks [closed]

There are many great tools helping you to manage your projects or just to track team tasks. But I am looking for a tool to track recurrent tasks of my team. For example, there are lot's of tasks like ...
2
votes
3answers
853 views

How to split or manage a PBI/User Story in multiple sprints for different task types

We're struggling to break Product Backlog Items (PBIs)/User Stories into Sprint-sized chunks as we have multiple steps that need to be completed in a linear fashion. Each release goes through ...